Regulation of Ontario
renewable energy approvals under Part V.0.1 of the Act
ONTARIO REGULATION 359/09
- Citation
- O. Reg. 359/09
- Current to
- November 11, 2026
- Consolidated from
- July 28, 2026
- Read from e-Laws
- November 16, 2026
- Made under
- Environmental Protection Act, R.S.O. 1990, c. E.19
- Official text
- e-Laws ↗
Contents 90 entries
PART I — INTERPRETATION
1 Interpretation 2 Negative environmental effectPART II — CLASSES OF RENEWABLE ENERGY GENERATION FACILITIES
3 Anaerobic digestion facilities 4 Solar facilities 5 Thermal treatment facilities 6 Wind facilitiesPART III — APPLICATION OF THE ACT TO RENEWABLE ENERGY PROJECTS
7 Exemption, standby generator 8 Exemptions, subs. 47.3 (1) of the Act 9 Exemptions, s. 47.3 of the Act 9.1 Exemptions, ss. 47.3 (1) and 186 (3) of the Act 10 Prescribed activitiesPART IV — RENEWABLE ENERGY APPROVALS — APPLICATION PROCESS BEFORE APPROVAL ISSUED
Application of Part
11 Application of PartApplication for Renewable Energy Approval
12 Eligibility, renewable energy approval 13 Supporting documentsConsultation
14 List of Indigenous communities 15 Notices of project and meetings 15.1 Information on website 15.2 Newspaper notice 16 Consultation with public 16.0.1 Proposal to change project, additional notice and consultation 16.1 Exception, ss. 15.1 to 16 17 Consultation with Indigenous communities 18 Consultation with municipalities, local authoritiesProtected Properties, Archaeological and Heritage Resources
19 Protected properties 20 Archaeological resources, specified projects 21 Archaeological resources, other projects 22 Archaeological assessment, documents to be included in application 23 Heritage assessmentNatural Heritage
23.1 Environmental effects monitoring plan 23.2 Assessments etc. by qualified person 24 Natural heritage assessment 25 Natural heritage, records review 26 Natural heritage, site investigation 27 Natural heritage, evaluation of significance 28 AttestationsWater
29 Water assessment 30 Water, records review 31 Water, site investigationNiagara Escarpment
32 Niagara EscarpmentTransition
32.0.1 TransitionPART IV.1 — RENEWABLE ENERGY APPROVALS — APPLICATION PROCESS AFTER APPROVAL ISSUED
32.1 Application of Part 32.2 Application and report, proposed change 32.3 Additional notice and consultation requirements 32.4 Additional information requirements 32.5 Application of s. 13 (3) and (4)PART V — PROHIBITIONS — RENEWABLE ENERGY PROJECTS
Application and Interpretation of Part
33 Application of Part 33.1 Reference to application 34 Significant and provincially significant natural featuresGeneral Prohibitions
35 Associated transformers 36 Non-renewable energy sourcesNatural Features and Water Bodies — General
37 Specified wetlands, provincial parks, conservation reserves 38 Specified natural features 39 Water bodies 40 Water bodies, continuedNatural Features and Water Bodies — Greenbelt
41 Specified natural features in Natural Heritage SystemNatural Features and Water Bodies — Oak Ridges Moraine
42 Oak Ridges Moraine 43 Specified natural features 44 Water bodies 45 Water bodies, continued 46 Rapid infiltration basin or columnAnaerobic Digestion Facilities
47 Class 1 and 2 anaerobic digestion facilities, less than or equal to 500 kW 48 Class 1 and 2 anaerobic digestion facilities, greater than 500 kW 49 Class 2 anaerobic digestion facilities, financial assurance 50 Class 3 anaerobic digestion facilitiesThermal Treatment Facilities
51 Class 2 thermal treatment facilities 52 Class 2 and 3 thermal treatment facilitiesWind Facilities
53 Class 3, 4 and 5 wind facilities 54 Specified wind turbines, prohibition and requirements 54.1 Wind turbine location publication 55 Wind turbines, requirements re location 55.1 Certain wind turbines, requirement re reportPART VI — POWERS AND DUTIES OF DIRECTOR
56 Great Lakes Charter 57 Discretion re reporting requirementPART VI.1 — RENEWABLE ENERGY APPROVALS — CIRCUMSTANCES IN WHICH ISSUING PROHIBITED
57.1 Application of Part 57.2 Demonstration of electricity demand 57.3 Class 4 wind facility, LRP process 57.4 No conformity with zoning by-laws, ordersPART VII — HEARINGS
58 Date to require hearing 59 Date of deemed confirmation 60 Exemption, s. 142.1 of the ActPART VIII — TRANSITION
61 Definitions 62 Transition, Part IV and Table 1, projects commenced before 2011 62.1 Election re ss. 23.1 and 28 of pre-2012 Regulation 62.2 Election re other portions of pre-2012 Regulation 62.3 Election for the application of Part IV 62.4 Transition, Part IV and Table 1, projects commenced after December 31, 2010 63 Transition, definition of “woodland” 64 Transition, s. 1 (4) 64.1 Transition, s. 1 (6) 64.2 ss. 63, 64 and 64.1 cease to apply