renewable energy approvals under Part V.0.1 of the Act, O. Reg. 359/09
Section 39
Water bodies
Cite as renewable energy approvals under Part V.0.1 of the Act, O. Reg. 359/09, s. 39 · current to November 11, 2026 · consolidated from July 28, 2026 · read from e-Laws on November 16, 2026
The text
(1) No person shall construct, install or expand a renewable energy generation facility as part of a renewable energy project in a project location that is in any of the following locations:
1. A lake or within 30 metres of the average annual high water mark of a lake.
2. A permanent or intermittent stream or within 30 metres of the average annual high water mark of a permanent or intermittent stream.
3. A seepage area or within 30 metres of a seepage area. O. Reg. 359/09, s. 39 (1).
(2) Subsection (1) does not apply if the facility is a facility mentioned in subsection (3) and, as part of the application for the issue of a renewable energy approval in respect of the renewable energy project, the applicant submits a report that,
(a) identifies and assesses any negative environmental effects of the project on a water body referred to in paragraphs 1 to 3 of subsection (1) and on land within 30 metres of the water body;
(b) identifies mitigation measures in respect of any negative environmental effects mentioned in clause (a);
(c) describes how the environmental effects monitoring plan set out in paragraph 4 of item 4 of Table 1 addresses any negative environmental effects mentioned in clause (a); and
(d) describes how the construction plan report prepared in accordance with Table 1 addresses any negative environmental effects mentioned in clause (a). O. Reg. 359/09, s. 39 (2).
(3) Subsection (2) applies in respect of the following facilities:
1. A Class 3 or 4 wind facility, if no wind turbine or transformer substation is constructed, installed or expanded in a project location described in subsection (1).
2. A Class 5 wind facility, if no transformer substation is constructed, installed or expanded in a project location described in subsection (1).
3. A Class 3 solar facility, if no solar photovoltaic panel or device and no transformer substation is constructed, installed or expanded in a project location described in subsection (1).
4. An anaerobic digestion facility, if no biomass storage areas, source separated organics storage areas, farm material storage areas, digestate storage tanks, generating units, flares, anaerobic digesters and transformer substations are constructed, installed or expanded in a project location described in subsection (1).
5. A thermal treatment facility, if no biomass storage areas or transformer substations are constructed, installed or expanded in a project location described in subsection (1). O. Reg. 359/09, s. 39 (3); O. Reg. 521/10, s. 22 (1-5).
(4) For the purposes of this section,
“transformer substation” means a transformer substation capable of operating at a nominal voltage of 50 kV or more. O. Reg. 521/10, s. 22 (6).
Read the renewable energy approvals under Part V.0.1 of the Act on e-Laws ↗
Made under Environmental Protection Act, R.S.O. 1990, c. E.19.