renewable energy approvals under Part V.0.1 of the Act, O. Reg. 359/09
Section 32.3
Additional notice and consultation requirements
Cite as renewable energy approvals under Part V.0.1 of the Act, O. Reg. 359/09, s. 32.3 · current to November 11, 2026 · consolidated from July 28, 2026 · read from e-Laws on November 16, 2026
The text
(1) In the circumstances described in subsection (2), the Director may, by written notice to a person who submitted an application under section 32.2, require the person to do one or more of the following:
1. Prepare a notice, in a form approved by the Director, of,
i. the proposed change or alteration, or
ii. the location and time of a public meeting to be held for the purpose of conducting consultations in respect of the proposed change or alteration.
2. Distribute a notice mentioned in paragraph 1,
i. in accordance with paragraphs 1, 2, 3 and 4 of subsection 15 (6), to the persons mentioned in paragraph 5 of subsection 15 (6), and
ii. at least 30 days before the meeting mentioned in subparagraph 1 ii, if a public meeting is required under paragraph 3.
3. Hold one or more public meetings,
i. in each local municipality in which the project location is situated, and
ii. if the project location is in unorganized territory,
A. within 25 kilometres of the project location, or
B. in the local municipality that is closest to the project location, if there is no appropriate place to hold a public meeting in the area described in sub-subparagraph A.
4. Make the report or reports prepared under paragraph 2 of subsection 32.2 (2) and any of the documents that are mentioned in paragraph 3 of subsection 32.2 (2) or required to be obtained or prepared under section 32.4 available in the manner described in clauses 16 (5) (a) to (d) for a period of time specified by the Director. O. Reg. 195/12, s. 17; O. Reg. 333/12, s. 9.
(2) The Director may provide written notice under subsection (1), if, in the opinion of the Director, failure to require additional public notification or public consultation under this section might result in an inadequate understanding by the public of the negative environmental effects of the proposed changes or alterations. O. Reg. 195/12, s. 17.
Read the renewable energy approvals under Part V.0.1 of the Act on e-Laws ↗
Made under Environmental Protection Act, R.S.O. 1990, c. E.19.