renewable energy approvals under Part V.0.1 of the Act, O. Reg. 359/09
Section 57.2
Demonstration of electricity demand
Cite as renewable energy approvals under Part V.0.1 of the Act, O. Reg. 359/09, s. 57.2 · current to November 11, 2026 · consolidated from July 28, 2026 · read from e-Laws on November 16, 2026
The text
(1) No renewable energy approval shall be issued in respect of a renewable energy project unless the person who proposes to engage in the renewable energy project submits documentation mentioned in subsection (2) to the Director, demonstrating that there is demand for the electricity that is proposed to be generated at the renewable energy generation facility. O. Reg. 122/19, s. 5.
(2) For the purposes of subsection (1), the demand for the electricity must be demonstrated by submitting one or more of the following types of documentation:
1. A copy of one or more agreements, entered into for a period of at least 10 years between the person who proposes to engage in the renewable energy project and one or more persons, in respect of the supply of the electricity to be generated at the facility, identifying the amount of electricity that is to be supplied under the agreement.
2. Documentation that establishes that the person who proposes to engage in the renewable energy project proposes to generate the electricity at the facility for their own use.
3. Documentation that establishes that the person who proposes to engage in the renewable energy project has, in respect of the electricity to be generated at the facility,
i. entered into a net metering agreement with a distributor, in conformity with Ontario Regulation 541/05 (Net Metering) made under the Ontario Energy Board Act, 1998, or
ii. applied to connect the facility for the purposes of entering into a net metering agreement with a distributor or notified the distributor that it wishes to be billed on a net metering basis, in conformity with the regulation mentioned in subparagraph i.
4. A declaration prepared by the person who proposes to engage in the renewable energy project, indicating that the person intends to participate in the IESO-administered markets as a market participant.
5. A declaration prepared by the person who proposes to engage in the renewable energy project, indicating that the person intends to participate in a procurement process established by the Independent Electricity System Operator. O. Reg. 122/19, s. 5.
(3) The documentation shall be submitted to the Director as part of the application for the issue of a renewable energy approval or, if the application was submitted before this section came into force, when the documentation has been obtained or prepared. O. Reg. 122/19, s. 5.
(4) For greater certainty, this section applies in respect of a decision under subsection 47.5 (1) of the Act to issue a renewable energy approval even if the application for the issue of the renewable energy approval was submitted before this section came into force. O. Reg. 122/19, s. 5.
Read the renewable energy approvals under Part V.0.1 of the Act on e-Laws ↗
Made under Environmental Protection Act, R.S.O. 1990, c. E.19.