renewable energy approvals under Part V.0.1 of the Act, O. Reg. 359/09
Section 32.2
Application and report, proposed change
Cite as renewable energy approvals under Part V.0.1 of the Act, O. Reg. 359/09, s. 32.2 · current to November 11, 2026 · consolidated from July 28, 2026 · read from e-Laws on November 16, 2026
The text
(1) A person who proposes to engage in a renewable energy project as described in subsection 32.1 (1) may submit an application for one or both of the following:
1. The issue of a renewable energy approval in respect of the proposed change.
2. The alteration of the terms or conditions of a renewable energy approval in respect of the proposed alteration. O. Reg. 195/12, s. 17.
(2) For the purposes of subsection (1), an application shall consist of the following:
1. An application, in a form or format approved by the Director, for the proposed change or alteration.
2. One or more reports that set out a description of and rationale for the proposed change or alteration, including any proposed changes or alterations in respect of the following:
i. The name plate capacity of the renewable energy generation facility.
ii. The energy sources to be used to generate electricity at the renewable energy generation facility.
iii. The project location.
iv. The renewable energy generation facility, including any associated or ancillary equipment, systems or technologies.
v. The activities that will be engaged in as part of the project.
vi. The negative environmental effects that may result from engaging in the project.
vii. The measures to mitigate the negative environmental effects that may result from engaging in the project.
3. Any document that is required to be submitted for the purposes of obtaining an exemption from a provision of Part V.
4. If the application relates to a change that would increase the name plate capacity of the renewable energy generation facility and the change would not take place on the same parcel or parcels of land on which the facility is approved to be constructed, installed, operated or used, one or more of the following documents:
i. A copy of one or more agreements, entered into for a period of at least 10 years between the person who proposes to engage in the renewable energy project and one or more persons, in respect of the supply of the additional electricity to be generated at the facility, identifying the amount of electricity that is to be supplied under the agreement.
ii. Documentation that establishes that the person who proposes to engage in the renewable energy project proposes to generate the additional electricity at the facility for their own use.
iii. Documentation that establishes that the person who proposes to engage in the renewable energy project has, in respect of the additional electricity to be generated at the facility,
A. entered into a net metering agreement with a distributor, in conformity with Ontario Regulation 541/05 (Net Metering) made under the Ontario Energy Board Act, 1998, or
B. applied to connect the facility for the purposes of entering into a net metering agreement with a distributor or notified the distributor that it wishes to be billed on a net metering basis, in conformity with the regulation mentioned in sub-subparagraph A.
iv. A declaration prepared by the person who proposes to engage in the renewable energy project, indicating that the person intends to participate in the IESO-administered markets as a market participant.
v. A declaration prepared by the person who proposes to engage in the renewable energy project, indicating that the person intends to participate in a procurement process established by the Independent Electricity System Operator.
5. If the application relates to a change that would not take place on the same parcel or parcels of land on which the facility is approved to be constructed, installed, operated or used, written confirmation from the following bodies that any proposed change that would take place on the parcel or parcels of land on which the facility has not been approved to be constructed, installed, operated or used would not result in a use of the land that is prohibited by a zoning by-law or zoning order under Part V of the Planning Act:
i. Any local municipality in which the project location is situated.
ii. Any planning board that has jurisdiction in an area without municipal organization in which the project location is situated.
iii. The Ministry of Municipal Affairs and Housing, if the project location is situated in an area without municipal organization and no planning board has jurisdiction in respect of that location. O. Reg. 195/12, s. 17; O. Reg. 122/19, s. 4.
Read the renewable energy approvals under Part V.0.1 of the Act on e-Laws ↗
Made under Environmental Protection Act, R.S.O. 1990, c. E.19.