renewable energy approvals under Part V.0.1 of the Act, O. Reg. 359/09
Section 45
Water bodies, continued
Cite as renewable energy approvals under Part V.0.1 of the Act, O. Reg. 359/09, s. 45 · current to November 11, 2026 · consolidated from July 28, 2026 · read from e-Laws on November 16, 2026
The text
(1) No person shall construct, install or expand a renewable energy generation facility as part of a renewable energy project at a project location that is in any of the following locations:
1. Within 120 metres of the average annual high water mark of a kettle lake that is not a lake trout lake that is at or above development capacity.
2. Within 300 metres of the average annual high water mark of a kettle lake that is a lake trout lake that is at or above development capacity.
3. Within 120 metres of the average annual high water mark of a permanent or intermittent stream.
4. Within 120 metres of a seepage area. O. Reg. 359/09, s. 45 (1).
(2) Subsection (1) does not apply if, as part of an application for the issue of a renewable energy approval in respect of the renewable energy project, the applicant submits a report that,
(a) identifies and assesses any negative environmental effects of the project on a water body referred to in paragraphs 1 to 4 of subsection (1) and on land within 30 metres of the water body;
(b) identifies mitigation measures in respect of any negative environmental effects mentioned in clause (a);
(c) describes how the environmental effects monitoring plan set out in paragraph 4 of item 4 of Table 1 addresses any negative environmental effects mentioned in clause (a); and
(d) describes how the construction plan report prepared in accordance with Table 1 addresses any negative environmental effects mentioned in clause (a). O. Reg. 359/09, s. 45 (2).
(3) Except in respect of a water body mentioned in paragraph 1, 2, 3 or 4 of subsection (1) that is located, in whole or in part, within an Oak Ridges Moraine settlement area, subsection (1) does not apply in respect of the construction, installation or expansion of a renewable energy generation facility as part of a renewable energy project if the project location is entirely within an Oak Ridges Moraine settlement area. O. Reg. 359/09, s. 45 (3).
Read the renewable energy approvals under Part V.0.1 of the Act on e-Laws ↗
Made under Environmental Protection Act, R.S.O. 1990, c. E.19.