United States Code
16 U.S.C. § 806
Time limit for construction of project works; extension of time; termination or revocation of licenses for delay
Statute Watch
Get an alert when any bill in Congress would change this law — and every time it moves.
Bills that would change it 27
- S 5653 Bipartisan American Affordability and Jobs Act of 2026 Amends its part · in committee · 119th Congress
- HR 9806 FLOWS Act Fair Licensing for Operations of Water Structures Act Amends its part · in committee · 119th Congress
- S 3500 Hydropower Licensing Transparency Act Amends its part · in committee · 119th Congress
- S 3518 FLOWS Act Amends its part · in committee · 119th Congress
- HR 8033 No Harm Data Centers Act Amends its part · in committee · 119th Congress
- HR 8968 Keeping the Lights On Act Amends its part · in committee · 118th Congress
- HR 4045 Hydropower Clean Energy Future Act Amends its part · in committee · 118th Congress
- S 1521 Community and Hydropower Improvement Act Amends its part · in committee · 118th Congress
- HR 1512 CLEAN Future Act Amends its part · in committee · 117th Congress
- HR 1588 Hydropower Clean Energy Future Act Amends its part · in committee · 117th Congress
- HR 7410 Hydropower Clean Energy Future Act Amends its part · in committee · 116th Congress
- S 3021 America's Water Infrastructure Act of 2018 Amends · enacted · 115th Congress
- S 724 A bill to amend the Federal Power Act to modernize authorizations for necessary hydropower approvals. Amends · passed one chamber · 115th Congress
- S 2655 Promoting Hydropower Development and Jobs Act Amends its part · in committee · 115th Congress
- HR 4696 Promoting Hydropower Development at Existing Nonpowered Dams Act Amends its part · in committee · 115th Congress
- HR 2872 Promoting Hydropower Development at Existing Nonpowered Dams Act Amends its part · passed one chamber · 115th Congress
- HR 2880 Promoting Closed-Loop Pumped Storage Hydropower Act Amends its part · passed one chamber · 115th Congress
- HR 3043 Hydropower Policy Modernization Act of 2017 Amends · passed one chamber · 115th Congress
- S 1460 Energy and Natural Resources Act of 2017 Amends · in committee · 115th Congress
- HR 2274 HYPE Act Amends · passed one chamber · 115th Congress
- S 2012 North American Energy Security and Infrastructure Act of 2016 Amends its part · in committee · 114th Congress
- S 2399 Climate Protection and Justice Act of 2015 Amends its part · in committee · 114th Congress
- HR 8 North American Energy Security and Infrastructure Act of 2015 Amends its part · in committee · 114th Congress
- S 1338 Small HyDRO Act of 2015 Small Hydropower Dependable Regulatory Order Act of 2015 Amends its part · in committee · 114th Congress
- S 1236 Hydropower Improvement Act of 2015 Amends · in committee · 114th Congress
- S 1419 Marine and Hydrokinetic Renewable Energy Act of 2014 Amends its part · in committee · 113th Congress
- S 539 Clean Renewable Energy and Economic Development Act Amends its part · in committee · 111th Congress
The law today
From the official United States Code, current through Public Law 119-142.
The licensee shall commence the construction of the project works within the time fixed in the license, which shall not be more than two years from the date thereof, shall thereafter in good faith and with due diligence prosecute such construction, and shall within the time fixed in the license complete and put into operation such part of the ultimate development as the commission shall deem necessary to supply the reasonable needs of the then available market, and shall from time to time thereafter construct such portion of the balance of such development as the commission may direct, so as to supply adequately the reasonable market demands until such development shall have been completed. The periods for the commencement of construction may be extended for not more than 8 additional years, and the period for the completion of construction carried on in good faith and with reasonable diligence may be extended by the commission when not incompatible with the public interests. In case the licensee shall not commence actual construction of the project works, or of any specified part thereof, within the time prescribed in the license or as extended by the commission, then, after due notice given, the license shall, as to such project works or part thereof, be terminated upon written order of the commission. In case the construction of the project works, or of any specified part thereof, has been begun but not completed within the time prescribed in the license, or as extended by the commission, then the Attorney General, upon the request of the commission, shall institute proceedings in equity in the district court of the United States for the district in which any part of the project is situated for the revocation of said license, the sale of the works constructed, and such other equitable relief as the case may demand, as provided for in section 820 of this title.
Official text at uscode.house.gov ↗