(1) A well authorization holder must notify the regulator at least 2 days before (a) beginning to construct or modify a production facility associated with a well, or (b) carrying out pressure tests at a production facility. (2) A well authorization holder must notify the regulator at least one day before (a) beginning production, or (b) putting new or modified equipment into service.
Read the Geothermal Operations Regulation on BC Laws ↗

Made under Geothermal Resources Act, RSBC 1996, c. 171.