Geothermal Operations Regulation, B.C. Reg. 79/2017
Section 39
Requirements
Cite as Geothermal Operations Regulation, B.C. Reg. 79/2017, s. 39 · last amended September 1, 2023 · read from BC Laws on November 17, 2026
The text
A well authorization holder must, for any facility associated with the well,
(a) maintain detailed flow diagrams, metering schematics and gathering schematics,
(b) design, construct and operate all equipment and piping systems in accordance with ASME B31.3 or CSA Z662 and manufacturer's specifications, and
(c) submit to the regulator all as-built drawings and schematics, signed and sealed by a qualified professional, within 3 months of beginning operations at a facility, or after a major modification of a facility.
Read the Geothermal Operations Regulation on BC Laws ↗
Made under Geothermal Resources Act, RSBC 1996, c. 171.