Regulation of Canada

Reduction in the Release of Volatile Organic Compounds Regulations (Petroleum Sector)

Statute Watch

Get an alert when a bill in Parliament would change this regulation, and every time it moves.

Citation
SOR/2020-231
Current to
July 24, 2025
Last amended
January 1, 2023
Made under
Canadian Environmental Protection Act, 1999, S.C. 1999, c. 33
Official text
Justice Laws Website ↗

Bills in Parliament that would change it 0

No bill we hold would amend or repeal it.

Contents 47 entries

Interpretation

1 Definitions

Application

2 Facilities subject to the Regulations

Leak Detection and Repair Requirements

3 Leak detection and repair program 4 Equipment components to be listed in inventory 5 Portable monitoring instruments 6 Inspection — equipment components 7 Required training 8 Repairs 9 Record keeping 10 Retention period

Requirements for Certain Equipment Components

11 Responsibilities of operator 12 Pipes 13 Sampling systems 14 Pressure relief devices 15 Centrifugal compressors 16 Record keeping

Fenceline Monitoring Requirements

17 Standard fenceline monitoring program 18 Selection of fenceline 19 Selection of sampling equipment and supplies 20 Sampling locations 21 Deployment of sampling tubes 22 Storage of sampling tubes 23 Analysis of samples 24 Condition for less frequent analysis 25 Meteorological data 26 Application for permit — modified fenceline monitoring program 27 Application for permit — alternative fenceline monitoring program 28 Record keeping — standard or modified fenceline monitoring program

Reporting Requirements

29 Information to be provided on request 30 Information to be submitted for existing facility 31 Standard fenceline monitoring plan for existing facility 32 Annual report beginning in 2023 33 Heavy-liquid equipment components — three inspections 34 Gas and light-liquid equipment components — three inspections 35 Valves with three significant leaks 36 Equipment components exempt from certain inspections 37 Reasons for no inspection 38 Reasons for no inspection before repair 39 Significant leak not repaired within 15 days 40 Estimated VOC releases by type of component 41 Monitoring data — standard or modified fenceline monitoring program 42 Auditor’s report to be submitted in 2024 43 Corrective action plan 44 Independent auditor with no conflict of interest 45 Format of applications, reports and plans

Related Amendment

46 [Amendments]

Coming into Force

47 December 1, 2020