Reduction in the Release of Volatile Organic Compounds Regulations (Petroleum Sector), SOR/2020-231
Section 33
Heavy-liquid equipment components — three inspections
Cite as Reduction in the Release of Volatile Organic Compounds Regulations (Petroleum Sector), SOR/2020-231, s. 33 · current to July 24, 2025 · regulation last amended January 1, 2023
Statute Watch
Get an alert when a bill in Parliament would change this section, and every time it moves.
The text
(1) The annual report must contain, with respect to the heavy-liquid equipment components that are required to be inspected visually three times per calendar year under paragraph 6(1)(a) and that are set out by type in Schedule 1, the following information with respect to those inspections for each of those types of equipment components:
(a) the number of equipment components that were required to be inspected;
(b) the number of inspections that were carried out under paragraph 6(1)(a);
(c) the number of those inspections during which a significant leak was detected in an equipment component;
(d) the number of repairs that were completed
(i) within 15 days after the day on which a significant leak was detected in an equipment component during such an inspection,
(ii) more than 15 days but not more than 60 days after the day on which such a leak was detected,
(iii) more than 60 days but not more than 365 days after the day on which such a leak was detected, and
(iv) more than 365 days after the day on which such a leak was detected; and
(e) the number of equipment components in which a significant leak was detected during such an inspection but that were not repaired as of the date of the report.
(2) The annual report must contain, with respect to the heavy-liquid equipment components that are required to be inspected visually once per calendar year under paragraph 6(2)(a) and that are set out by type in Schedule 1, the following information with respect to those inspections for each of those types of equipment components:
(a) the number of equipment components that were required to be inspected;
(b) the number of inspections that were carried out under paragraph 6(2)(a);
(c) the number of those inspections during which a significant leak was detected in an equipment component;
(d) the number of repairs that were completed
(i) within 15 days after the day on which a significant leak was detected in an equipment component during such an inspection,
(ii) more than 15 days but not more than 60 days after the day on which such a leak was detected,
(iii) more than 60 days but not more than 365 days after the day on which such a leak was detected, and
(iv) more than 365 days after the day on which such a leak was detected; and
(e) the number of equipment components in which a significant leak was detected during such an inspection but that were not repaired as of the date of the report.
(3) The annual report must contain, with respect to the heavy-liquid equipment components that are listed in the inventory referred to in paragraph 3(2)(a) and that are set out by type in Schedule 1, the following information for each of those types of equipment components:
(a) the number of leaks that were detected, other than during the inspections required by paragraphs 6(1)(a) and (2)(a), for which the heavy-liquid drop rate was
(i) less than three drops per minute, and
(ii) equal to or greater than three drops per minute;
(b) the number of leaks that were detected, other than during the inspections required by paragraphs 6(1)(a) and (2)(a), in an equipment component that was not inspected before it was repaired because an authorized official determined, under subsection 8(5), that it could not be inspected without exposing any individual to immediate danger;
(c) the number of repairs, following the detection of a significant leak in an equipment component other than during the inspections required by paragraphs 6(1)(a) and (2)(a), that were completed
(i) within 15 days after the day on which the leak was detected,
(ii) more than 15 days but not more than 60 days after the day on which the leak was detected,
(iii) more than 60 days but not more than 365 days after the day on which the leak was detected, and
(iv) more than 365 days after the day on which the leak was detected; and
(d) the number of equipment components in which a significant leak was detected, other than during the inspections required by paragraphs 6(1)(a) and (2)(a), but that were not repaired as of the date of the report.
Read the Reduction in the Release of Volatile Organic Compounds Regulations (Petroleum Sector) on the Justice Laws Website ↗
Made under Canadian Environmental Protection Act, 1999, S.C. 1999, c. 33.
Bills in Parliament that would change this section 0
No bill we hold would amend or repeal this section.