ON-SITE AND EXCESS SOIL MANAGEMENT, O. Reg. 406/19
Section 21.2
Class 2 soil management site, notice requirements
Cite as ON-SITE AND EXCESS SOIL MANAGEMENT, O. Reg. 406/19, s. 21.2 · current to November 11, 2026 · consolidated from January 1, 2026 · read from e-Laws on November 16, 2026
The text
(1) In this section,
“project leader” means, in respect of a Class 2 soil management site at which dry excess soil or excavated engineered aggregate is managed, the project leader for the project from which the excess soil or excavated engineered aggregate was excavated. O. Reg. 235/25, s. 19 (1).
(2) This section applies in respect of a Class 2 soil management site at which the management of dry excess soil or excavated engineered aggregate is exempt from sections 27, 40 and 41 of the Act under section 21. O. Reg. 235/25, s. 19 (1).
(3) The project leader or the operator of the site shall provide written notice to the Director in accordance with subsection (4) before the excess soil or excavated engineered aggregate begins to be deposited at the site. O. Reg. 235/25, s. 19 (1).
(4) The notice shall include the following:
1. The location of the Class 2 soil management site.
2. The quantity of excess soil or excavated engineered aggregate to be deposited at the site, and, if known, its quality.
3. The name, mailing address, postal code, telephone number and email address of the project leader and an indication whether the project leader is a public body.
4. If the site is not operated by the project leader, the name, mailing address, postal code, telephone number and email address of the operator of the site.
5. The date on which the storage of the excess soil or excavated engineered aggregate at the site is expected to begin and the date on which it is expected to end. O. Reg. 174/24, s. 12; O. Reg. 235/25, s. 19 (2).
(5) If the project leader or the operator of the site becomes aware that any information in the written notice described in subsection (4) is no longer complete or accurate, they shall ensure that, within 30 days after the day they become aware, the Director is notified and provided with the completed or corrected information. O. Reg. 174/24, s. 12.