(1) In this section,
“project leader” means, in respect of a Class 2 soil management site at which dry excess soil or excavated engineered aggregate is managed, the project leader for the project from which the excess soil or excavated engineered aggregate was excavated. O. Reg. 235/25, s. 18 (1).
(2) This section applies in respect of a Class 2 soil management site at which the management of dry excess soil or excavated engineered aggregate is exempt from sections 27, 40 and 41 of the Act under section 21. O. Reg. 235/25, s. 18 (1).
(3) Subject to subsection (4), before dry excess soil or excavated engineered aggregate is deposited at the Class 2 soil management site, the project leader, the operator of the project area or the operator of that site shall do the following:
1. Except if the owner of the reuse site is the project leader, ensure that written consent has been obtained from the operator of the reuse site at which the excess soil or excavated engineered aggregate will be deposited.
2. Ensure that a written record is prepared, setting out the following:
i. Identification of the intended reuse site at which the excess soil or excavated engineered aggregate to be stored at the Class 2 soil management site will be deposited for final placement.
ii. If consent is required under paragraph 1, confirmation that the consent mentioned in that paragraph has been obtained. O. Reg. 235/25, s. 18 (1).
(4) If there is any change in the intended reuse site, the project leader, the operator of the project area or the operator of the Class 2 soil management site shall obtain the consent referred to in paragraph 1 of subsection (3) and update the written record referred to in paragraph 2 of subsection (3). O. Reg. 174/24, s. 12.
(5) If the conditions set out in subsection 8 (3) are satisfied in respect of the excess soil, subsection (3) shall be complied with as soon as possible after complying with section 12 in respect of the project area. O. Reg. 174/24, s. 12.
(6) The project leader or the operator of the Class 2 soil management site shall ensure the following:
1. That subsections 21 (3) to (6) are complied with.
2. That no liquid soil is deposited at the site.
3. That the record mentioned in paragraph 2 of subsection (3) is made available while the excess soil or excavated engineered aggregate is stored.
4. Subject to subsection (7), that the excess soil or excavated engineered aggregate is deposited for final placement at a reuse site no later than two years after the excess soil or excavated engineered aggregate is first deposited at the Class 2 soil management site.
5. That records in respect of the deposit and management of excess soil or excavated engineered aggregate at the Class 2 soil management site and any excess soil or excavated engineered aggregate that is removed from the site are created in accordance with the Soil Rules and are retained at the site.
6. That any other requirements set out in the Soil Rules with respect to the deposit and management of excess soil or excavated engineered aggregate at a Class 2 soil management site are met. O. Reg. 174/24, s. 12; O. Reg. 235/25, s. 18 (2, 3).
(7) The Director to whom written notice is provided under section 21.2 may authorize in writing an extension, not exceeding five years, of the two-year period mentioned in paragraph 4 of subsection (6), if the Director is satisfied that,
(a) the extension is necessary in order for the excess soil or excavated engineered aggregate to be used at a reuse site;
(b) the extension will not result in an adverse effect; and
(c) the project leader or the operator of the Class 2 soil management site has provided an estimated date for the removal of the excess soil or excavated engineered aggregate from the site. O. Reg. 174/24, s. 12; O. Reg. 235/25, s. 18 (4).