Construction Remedies Act, 2020, c.29

Section 48

Holdback – payment on certification or declaration of substantial performance or completion

Cite as Construction Remedies Act, 2020, c.29, s. 48 · current to June 16, 2023 · read from New Brunswick Acts and Regulations on November 16, 2026

The text

(1) If a contract has been certified or declared under section 41 to be substantially performed, the owner shall pay out the holdback required to be retained under subsection 34(1) and any funds retained on receiving a written notice of lien in accordance with section 30, if (a) all liens in respect of the contract have been extinguished, discharged or otherwise provided for under this Act, and (b) the holdback period has expired. (2) If a subcontract has been certified or declared under section 44 to be completed, the owner may, without jeopardy, reduce the holdback required to be retained under subsection 34(1) by paying out the amount of holdback the owner has retained in respect of the completed subcontract, if (a) all liens in respect of the completed subcontract have been extinguished, discharged or otherwise provided for under this Act, and (b) the holdback period has expired. (3) For greater certainty, an owner who pays an amount under subsection (2) is not liable to pay more than the amount of holdback required to be retained under subsection 34(1).
Read the Construction Remedies Act on the Province's website ↗