Construction Remedies Act, 2020, c.29
Section 49
Holdback – payment on annual basis
Cite as Construction Remedies Act, 2020, c.29, s. 49 · current to June 16, 2023 · read from New Brunswick Acts and Regulations on November 16, 2026
The text
(1) An owner required to retain a holdback under subsection 34(1) may make payments from the holdback on an annual basis, in relation to the services or materials supplied during the applicable annual period, if the conditions in subsection (2) are met.
(2) An owner may make payments from a holdback on an annual basis if
(a) the contract provides for a completion schedule that is longer than one year,
(b) the contract provides for the making of payments from the holdback on an annual basis,
(c) the contract price at the time the contract is entered into exceeds the amount prescribed by regulation, and
(d) as of the relevant payment date,
(i) there are no claims for lien in respect of the contract
(A) registered under paragraph 55(a) or given under subparagraph 55(b)(i) or (ii), or
(B) that are the subject of an action to enforce the lien, or
(ii) all liens in respect of the contract have been extinguished, discharged or otherwise provided for under this Act.
Read the Construction Remedies Act on the Province's website ↗