Construction Remedies Act, 2020, c.29
Section 47
Holdback periods
Cite as Construction Remedies Act, 2020, c.29, s. 47 · current to June 16, 2023 · read from New Brunswick Acts and Regulations on November 16, 2026
The text
(1) If a contract has been certified or declared to be substantially performed under section 41, the holdback required to be retained under subsection 34(1) with respect to the contract and any subcontract under the contract shall be retained for 60 days after the date the certificate of substantial performance is signed or the declaration of substantial performance is made, as the case may be.
(2) If a contract has not been certified or declared to be substantially performed under section 41, the holdback required to be retained under subsection 34(1) with respect to the contract and any subcontract under the contract shall be retained for 60 days after the contract is completed, abandoned or terminated.
(3) The holdback required to be retained under subsection 34(2) with respect to a contract and any subcontract under the contract shall be retained for 60 days after the contract is completed, abandoned or terminated.
(4) If a subcontract has been certified or declared to be completed under section 44, the holdback required to be retained under subsection 34(1) with respect to the subcontract and any subcontract under the subcontract shall be retained for 60 days after the date the certificate of completion of subcontract is signed or the declaration of completion of subcontract is made, as the case may be.