Construction Remedies Act, 2020, c.29
Section 46
Notice of certificate of completion of subcontract
Cite as Construction Remedies Act, 2020, c.29, s. 46 · current to June 16, 2023 · read from New Brunswick Acts and Regulations on November 16, 2026
The text
(1) Any lienholder in respect of an improvement may, by written request, require the contractor to notify them that a subcontract has been completed by giving the lienholder a copy of the certificate of completion of subcontract, if any, with respect to the subcontract.
(2) A request under subsection (1) may be made before or after a certificate of completion of subcontract is signed.
(3) Within seven days after a request is made under subsection (1), a contractor shall give the lienholder who made the request a copy of any certificate of completion of subcontract signed with respect to the subcontract or, if no certificate of completion of subcontract has been signed at the time the request is made, within seven days after receiving a copy of the certificate or after signing the certificate with the owner, as the case may be.
Read the Construction Remedies Act on the Province's website ↗