Municipal Wastewater Regulation, B.C. Reg. 87/2012

Section 78

Drainage pipe length requirements

Cite as Municipal Wastewater Regulation, B.C. Reg. 87/2012, s. 78 · last amended October 27, 2025 · read from BC Laws on November 17, 2026

The text

(1) A discharger must ensure that drainage pipes are at least the length set out for the applicable municipal effluent class and percolation rate, as listed in Table 4. (2) Despite subsection (1), a discharger may use a chamber distribution system with an equivalent length to the minimum pipe length listed in Table 4. (3) If (a) percolation rates are less than 2 minutes per 25 mm, (b) the maximum daily flow is less than 37 m3/d, and (c) class A or B municipal effluent is discharged by pressure distribution, a discharger may use American Society for Testing and Materials C33 sand-filled trenches to reduce percolation. (4) If percolation rates exceed 20 minutes per 25 mm, a qualified professional must (a) supervise construction, and (b) ensure that construction has not reduced the trench wall permeability, except that, for maximum daily flows of less than 37 m3/d, permeability may be reduced if the native undisturbed permeable soil depth exceeds 1.35 m as measured from the bottom of the field to the level of the water table. Table 4 — Minimum Drainage Pipe Length for Each Field Metres of Drainage Pipe for Each 10 m3/d of Maximum Daily Flow for Percolation Rates Shown percolation rate (minutes / 25 mm) 2 5 10 15 20 25 30 class A, B or C municipal effluent 50 75 100 110 120 135 150 class D municipal effluent 120 215 280 320 360 400 430
Read the Municipal Wastewater Regulation on BC Laws ↗

Made under Environmental Management Act, SBC 2003, c. 53.