Municipal Wastewater Regulation, B.C. Reg. 87/2012

Section 46

Notification of discharge

Cite as Municipal Wastewater Regulation, B.C. Reg. 87/2012, s. 46 · last amended October 27, 2025 · read from BC Laws on November 17, 2026

The text

A discharger must do both of the following: (a) within 30 to 60 days before beginning to discharge, provide to a director (i) notice that discharge will begin, and (ii) a copy of final design drawings reflecting the actual construction of the wastewater facility, certified as correct and signed and sealed by a qualified professional; (b) not more than 7 days after beginning to discharge, provide to a director notice of the date that discharge began.
Read the Municipal Wastewater Regulation on BC Laws ↗

Made under Environmental Management Act, SBC 2003, c. 53.