Geothermal Operations Regulation, B.C. Reg. 79/2017
Section 21
Disposal of drilling and production material
Cite as Geothermal Operations Regulation, B.C. Reg. 79/2017, s. 21 · last amended September 1, 2023 · read from BC Laws on November 17, 2026
The text
(1) A well authorization holder must ensure that formation water, oil, drilling fluid, completion fluid, waste, chemical substances or refuse from a well, tank or other facility do not do any of the following:
(a) create a hazard to public health or safety;
(b) run into or contaminate any water supply well, usable aquifer or water body or remain in a place from which it might contaminate any water supply well, usable aquifer or water body;
(c) run over, pollute or damage any land or public road;
(d) pass into or, in the case of ice, over any water body that is frequented by fish or wildlife or that flows into any such water body.
(2) A well authorization holder who deposits into a pit drilling fluids that may be harmful to domestic livestock or big game must maintain the pit so as to prevent domestic livestock or big game from ingesting the fluids.
(3) A well authorization holder who uses an earthen pit to store liquid waste from a well drilling operation must ensure that the pit is
(a) not located within 100 m of the natural boundary of a water body,
(b) not located within 200 m of a water supply well,
(c) constructed of clay or other suitable impermeable material with the bottom of the pit above ground water level,
(d) located or ditched so that it will not collect natural run-off water,
(e) filled to not more than one metre below the point of overflow at any given time, and
(f) completely emptied and any excavation filled without unreasonable delay after completion of the drilling of the well.
(4) Within 90 days of completing a drilling waste disposal, a well authorization holder must submit to the regulator a report of the drilling waste disposal.
(5) A well authorization holder who, in a structure, stores water-based fluids with a concentration of total dissolved solids greater than 4 000 ppm that have been generated from or are being stored for the purpose of hydraulic fracturing operations must ensure all of the following:
(a) that the ground surface on which the structure will be constructed is prepared to the satisfaction of an official;
(b) that the structure is not located within 100 m of the natural boundary of a water body unless the structure is on a permitted well location;
(c) that the capacity of each structure is not greater than 6 600 m3;
(d) that the structure is located and constructed in a place and manner that ensures the contained fluids will not significantly migrate beyond the structure in the event of a containment failure;
(e) that the retaining walls of the structure are designed to withstand the hydraulic pressure of the contents at full capacity;
(f) that the installation of the liner system is completed to the satisfaction of an official;
(g) that the structure is filled to not more than 50 cm below the point of overflow at any given time;
(h) that the structure is equipped with measures to prevent waterfowl from coming in contact with the fluids;
(i) that when the structure contains fluid, it is inspected daily for leaks and a record of inspection is maintained until the site is decommissioned;
(j) that any sign of leakage is reported to the regulator within 24 hours of discovery;
(k) that the structure is decommissioned and removed from the site within one year from the date of first use unless there exists an engineered, lined or otherwise impermeable secondary containment system designed and maintained to be capable of holding a minimum of 110% of the fluid in the structure.
Read the Geothermal Operations Regulation on BC Laws ↗
Made under Geothermal Resources Act, RSBC 1996, c. 171.