Geothermal Operations Regulation, B.C. Reg. 79/2017

Section 2

Notification

Cite as Geothermal Operations Regulation, B.C. Reg. 79/2017, s. 2 · last amended September 1, 2023 · read from BC Laws on November 17, 2026

The text

A notification under section 4 (6) of the Act must be made at least 7 days before starting work other than well drilling and must contain the following information: (a) the commencement date of the field work; (b) the name and phone number of the field contact; (c) a summary of the work to be undertaken in the field; (d) plans to deal with emergencies that may arise; (e) the estimated end date of the field work.
Read the Geothermal Operations Regulation on BC Laws ↗

Made under Geothermal Resources Act, RSBC 1996, c. 171.