Geothermal Operations Regulation, B.C. Reg. 79/2017

Section 10

Testing of well control equipment

Cite as Geothermal Operations Regulation, B.C. Reg. 79/2017, s. 10 · last amended September 1, 2023 · read from BC Laws on November 17, 2026

The text

(1) A well authorization holder must ensure that (a) pressure-control equipment associated with well operations is pressure-tested on installation and as often as necessary during well operations to ensure the continued safe operation of the equipment, and (b) the rig crew conducting the well operation has an adequate understanding of, and is able to operate, well control equipment. (2) At the request of an official, a well authorization holder's contractor or rig crew, when it is safe to do so, must test the operation and effectiveness of the well control equipment installed on the authorization holder's well. (3) A well authorization holder must maintain, for 60 days from the date of rig release, a record of the results of tests required under subsection (2).
Read the Geothermal Operations Regulation on BC Laws ↗

Made under Geothermal Resources Act, RSBC 1996, c. 171.