Groundwater Protection Regulation, B.C. Reg. 39/2016

Section 71

Requirements for decommissioning wells

Cite as Groundwater Protection Regulation, B.C. Reg. 39/2016, s. 71 · last amended December 1, 2022 · read from BC Laws on November 17, 2026

The text

(1) Subject to section 72, the person responsible for decommissioning a well must (a) if practicable, remove from the well the well pump and all other equipment and instrumentation, (b) fill the well throughout its depth with layers of sealant and backfill materials in a manner that precludes any lengthwise movement of liquids (i) within the well, (ii) in any visible annular space between the outer casing and the surrounding geological formation, and (iii) between casings, (c) seal off all known aquifers and known water-bearing zones within an aquifer, as shown in Figure 4 of Schedule 5, to prevent mixing of groundwater from different aquifers or different water-bearing zones within an aquifer, (d) subject to paragraph (e), subsection (5) of this section and section 74 (2), install a closure plug that is at least 1 m in length and, if the depth of the well is insufficient to have a closure plug length of 1 m, the greatest possible length up to 1 m, and (e) if the well is a water supply well, or a well that was used at any time as a water supply well, install a closure plug that, subject to subsection (5), is not less than 5 m in length and, if the depth of the water supply well is insufficient to have a closure plug length of 5 m, the greatest possible length up to 5 m. (2) The person responsible for decommissioning a well may leave casings in place. (3) If there is a potential for entry of liquids into a well, the person responsible for decommissioning the well must fill any entry points or openings with sealant. (4) The person responsible for decommissioning a well must ensure that (a) the uncased portion of the well has layers of sealant, as shown in Figure 4 of Schedule 5, that are (i) at least 1 m in length, and (ii) separated by not more than 6 m of backfill materials, and (b) all sealant is placed in the well in a manner that ensures the physical integrity and continuity of the seal. (5) A closure plug may extend to within 0.3 m of the surface of the ground to allow for up to 0.3 m of backfill materials above the closure plug, but the total length of the closure plug must not be less than the length required under subsection (1) (d) or (e), as applicable. (6) If a well that is being decommissioned is a closed-loop geoexchange well, the person responsible for decommissioning the well must remove the circulation fluids from the ground loops in the closed-loop geoexchange system. (7) If a well that is being decommissioned is a flowing artesian well, the person responsible for decommissioning the well must, in addition to complying with this section, (a) stop the artesian flow through the casing, and (b) prevent any leakage of the artesian flow at the surface of the ground or into another aquifer.
Read the Groundwater Protection Regulation on BC Laws ↗

Made under Water Sustainability Act, SBC 2014, c. 15.