Occupational Health and Safety Regulation, B.C. Reg. 296/97

Section 21.84

Seismic blasting

Cite as Occupational Health and Safety Regulation, B.C. Reg. 296/97, s. 21.84 · last amended September 1, 2027 · read from BC Laws on November 17, 2026

The text

(1) If seismic blasting is carried out in an isolated location, loaded holes may be left unattended only if (a) the blaster has first ensured that all leg wires are shunted, drill cuttings are spread out and levelled, the leg wires are coiled as close to the ground as possible while never exceeding 15 cm (6 in) above the ground level, and the holes are suitably user identified, and recorded in the blasting log, and (b) the holes are blasted within 30 days. (2) Repealed. [B.C. Reg. 207/2021, App. A, s. 64 (a).] (3) In a seismic blasting operation a misfired or unfired charge may be left unfired only if (a) it cannot be conventionally and safely detonated, (b) it is in an isolated location, (c) it is at a depth sufficient to minimize the risk of injury to workers or other persons, (d) its location is effectively marked, and (e) a permanent record of its location is kept. (4) Seismic water tank trucks having open flame water heaters must not be used to transport explosives unless (a) the distance between the heat tube and the outside of the tank is at least 35 cm (14 in), (b) a heater, if woodburning, has a fire box of a type that fully contains the fuel and two dampers mounted in the heat tube, one at the vent end and the other at the fire box, so the flame may be shut in instantly in the event of an accident, and (c) the detonator storage is located on the opposite side of the vehicle from the explosive magazine, and both are built to type 6 magazine standard. (d) Repealed. [B.C. Reg. 312/2003, App. D, s. 21 (c).] (5) In a seismic operation where there is no alternate route, a vehicle may be driven over a loaded hole if (a) bypassing the hole is not practicable, (b) operational planning minimizes the requirement to travel through a loaded area, (c) safe work procedures are developed and communicated to all workers before they start work at the site, (d) loaded holes are in compliance with subsection (1), (e) explosive charges are at a minimum depth of 6 m (20 ft), and (f) all radio transmission equipment is turned off, or the transmission capability is disabled by disconnecting the microphone. (6) In a seismic blasting operation, the blaster of record must ensure that explosives are initiated by 2 detonators if the total weight of the explosives in the hole is (a) 4 kg (8.8 lbs) or more, or (b) more than 0.5 kg (1.1 lbs) and (i) the hole is less than 5 m (16.4 ft) deep, (ii) the condition of the soil may compromise the loading of the explosives in the hole, or (iii) the blasting operation is accessible only by helicopter.
Read the Occupational Health and Safety Regulation on BC Laws ↗

Made under Workers Compensation Act, RSBC 2019, c. 1.