Occupational Health and Safety Regulation, B.C. Reg. 296/97

Section 20.2

Notice of project

Cite as Occupational Health and Safety Regulation, B.C. Reg. 296/97, s. 20.2 · last amended September 1, 2027 · read from BC Laws on November 17, 2026

The text

(1) Subject to subsection (4), either the owner or the person engaged by the owner to be the prime contractor on a construction project must ensure that the Board receives, in writing, a notice of project that contains the information required by subsection (2) at least 24 hours before work on the construction project begins at the worksite if any of the following apply: (a) the estimated total cost of labour and materials for the construction project exceeds $100 000; (b) all or part of the construction project, whether a temporary or a permanent aspect of the project, is designed by a professional engineer except for pre-engineered or pre-manufactured building and structural components; (c) the construction project is a new erection, a major alteration, a structural repair or a demolition of (i) a building more than 2 storeys or 6 m (20 ft) high, (ii) a bridge, (iii) an earth or water retaining structure more than 3 m (10 ft) high, or (iv) a silo, chimney or other similar structure more than 6 m (20 ft) high; (d) workers will be working in a cofferdam or in a compressed air environment other than an underground working as defined in section 22.1; (e) a worker may be required to enter (i) a trench over 30 m (100 ft) long, or (ii) an excavation, other than a trench, over 1.2 m (4 ft) deep. (2) The notice of project must contain the following information: (a) the name and contact information of the owner and of the person engaged by the owner to be the prime contractor, if any; (b) the address of the construction project or its location in relation to the nearest highway; (c) the scope of the construction project, including a list of the items referred to in subsection (1) that apply to the construction project; (d) the starting date and the estimated duration of the construction project; (e) the estimated total cost of labour and materials for the construction project; (f) if the construction project involves construction of a cofferdam, confirmation by the owner or the person engaged by the owner to be the prime contractor that drawings for all temporary or permanent ground support will be available at the worksite for the duration of the construction project, if ground support is used. (3) Subject to subsection (4), if a notice of project is required under subsection (1), the owner or the person engaged by the owner to be the prime contractor must ensure that a copy of the notice of project is posted at the worksite before work on the construction project begins at the worksite and is kept posted for the duration of the construction project. (4) If it is necessary to do immediate work on a construction project to which subsection (1) applies in order to prevent the risk of injury to workers or other persons or damage to property, work on the construction project may begin at the worksite immediately and the owner or the person engaged by the owner to be the prime contractor on the construction project must ensure that (a) the Board receives, in writing, a notice of project that contains the information required by subsection (2) as soon as possible, and (b) a copy of the notice of project is posted at the worksite as soon as possible and is kept posted for the duration of the construction project. (5) If any of the information required by subsection (2) changes significantly, the owner or the person engaged by the owner to be the prime contractor must ensure that (a) the Board receives, in writing, the new information as soon as possible, and (b) a copy of the new information is posted at the worksite as soon as possible and is kept posted for the duration of the construction project.
Read the Occupational Health and Safety Regulation on BC Laws ↗

Made under Workers Compensation Act, RSBC 2019, c. 1.