Occupational Health and Safety Regulation, B.C. Reg. 296/97

Section 14.92

Wind limitations

Cite as Occupational Health and Safety Regulation, B.C. Reg. 296/97, s. 14.92 · last amended September 1, 2027 · read from BC Laws on November 17, 2026

The text

(1) An anemometer must be mounted on the crown, apex or operator's cab of each tower crane. (2) The readout for the anemometer required by subsection (1) must be readable by the operator while at the crane controls. (3) Tower crane operations must stop when a load cannot be handled safely because of wind. (4) In the absence of the manufacturer's specifications for maximum permitted wind speed during crane operation, the maximum allowable wind speed in which a tower crane may be used is 50 km/h (30 mph), or less if a load cannot be handled safely because of wind. (5) A sign or other item that would increase the surface area of a crane structure exposed to wind must not be installed unless authorized by the crane manufacturer or a professional engineer. (6) A tower crane must not be erected, operated or dismantled when the wind speed exceeds the upper limit specified by the crane manufacturer for erection, operation or dismantling of the crane.
Read the Occupational Health and Safety Regulation on BC Laws ↗

Made under Workers Compensation Act, RSBC 2019, c. 1.