Occupational Health and Safety Regulation, B.C. Reg. 296/97

Section 14.91

Hoisting ropes

Cite as Occupational Health and Safety Regulation, B.C. Reg. 296/97, s. 14.91 · last amended September 1, 2027 · read from BC Laws on November 17, 2026

The text

(1) A rotation resistant hoisting rope on a tower crane must be shortened by the removal of 3 m (10 ft) of rope at the dead end after every 500 hours of use unless (a) otherwise specified by the rope manufacturer, (b) the rope has 14 or more outer strands, or (c) the rope has a plastic coated inner core. (2) The hoisting rope on a tower crane must be properly seized before cutting. (3) The equipment records for a tower crane must contain the following information about the hoisting rope installed on the crane: (a) the name of the manufacturer or supplier of the rope; (b) the type of rope installed as described by the rope construction, number of outer strands, type of lay, direction of lay and type of core; (c) the diameter and the length of the rope; (d) the nominal or minimum rated breaking strength of the rope; (e) the rated working load limit for the rope; (f) the date the rope was installed; (g) if the rope was not new at the time of installation, the name of the qualified person who inspected the rope before installation on the crane to ensure that the rope was in a suitable condition for use as the hoist line on the crane; (h) the name of the qualified person who installed the rope.
Read the Occupational Health and Safety Regulation on BC Laws ↗

Made under Workers Compensation Act, RSBC 2019, c. 1.