Occupational Health and Safety Regulation, B.C. Reg. 296/97
Section 14.73.3
Notice of project
Cite as Occupational Health and Safety Regulation, B.C. Reg. 296/97, s. 14.73.3 · last amended September 1, 2027 · read from BC Laws on November 17, 2026
The text
(1) In this section, “crane activity” means any of the following work activities:
(a) erecting a tower crane;
(b) climbing a tower crane;
(c) repositioning a tower crane;
(d) dismantling a tower crane.
(2) Every employer responsible for a crane activity at a workplace, and either the owner or any person engaged by the owner to be the prime contractor, must ensure that,
(a) at least 2 weeks before the crane activity begins, the Board receives a written notice of project containing the information required by subsection (3), and
(b) before the crane activity begins and for the duration of that crane activity, a notice containing the information described in subsection (3) (a) to (e) is posted at the workplace.
(3) The notice of project must include the following information:
(a) the name and contact information for
(i) every employer responsible for the crane activity,
(ii) the owner and any person engaged by the owner to be the prime contractor, and
(iii) every person who may be a qualified supervisor in relation to the crane activity;
(b) the address of the workplace or the location of the workplace in relation to the nearest highway;
(c) the nature and scope of the crane activity and the nature and scope of the project that involves the crane activity;
(d) the starting date and estimated duration of the crane activity;
(e) the manufacturer, type, model number and configuration of the tower crane to which the crane activity relates and, if the information is available, the serial number of the tower crane and the year in which the tower crane was manufactured;
(f) work procedures established specifically for the workplace to ensure the safety of a person during the crane activity at that workplace;
(g) the qualifications of the person who is the qualified supervisor for the crane activity or the identity of a registry, acceptable to the Board, from which the qualifications may be obtained.
(4) Every employer responsible for a crane activity at a workplace, and either the owner or any person engaged by the owner to be the prime contractor, must ensure that the information described in subsection (3) (f) and (g) is kept up to date and made readily available at the workplace.
(5) If a crane activity is necessary in order to prevent the immediate risk of injury to a person or damage to property, that crane activity may, despite subsection (2), begin immediately after the Board has been notified of the intended crane activity.
(6) As soon as possible after the crane activity referred to in subsection (5) has begun, every employer responsible for the crane activity, and either the owner or any person engaged by the owner to be the prime contractor, must ensure that
(a) the Board receives a written notice of project containing the information required by subsection (3), and
(b) a notice containing the information described in subsection (3) (a) to (e) is posted at the workplace and remains posted for the duration of the crane activity.
(7) If any of the information included in a notice of project provided to the Board changes significantly, every employer responsible for the crane activity to which the notice of project relates, and either the owner or any person engaged by the owner to be the prime contractor, must ensure that
(a) the Board receives the new information, in writing, as soon as possible, and
(b) if the new information is information described in subsection (3) (a) to (e), an updated notice containing the new information is posted at the workplace as soon as possible and remains posted for the duration of the crane activity.
Read the Occupational Health and Safety Regulation on BC Laws ↗
Made under Workers Compensation Act, RSBC 2019, c. 1.