Drilling and Production Regulation, B.C. Reg. 282/2010

Section 9

Well control equipment

Cite as Drilling and Production Regulation, B.C. Reg. 282/2010, s. 9 · last amended April 1, 2025 · read from BC Laws on November 17, 2026

The text

(1) A well permit holder must ensure that, during all well operations, reliably operating well control equipment is installed to control kicks, prevent blow-outs and safely carry out all well operations. (2) If a well barrier fails, the well permit holder must ensure that no other activities, other than those intended to restore or replace the barrier, take place in the well.
Read the Drilling and Production Regulation on BC Laws ↗

Made under Energy Resource Activities Act, SBC 2008, c. 36.