Drilling and Production Regulation, B.C. Reg. 282/2010

Section 8

Notification of well construction and drilling operations

Cite as Drilling and Production Regulation, B.C. Reg. 282/2010, s. 8 · last amended April 1, 2025 · read from BC Laws on November 17, 2026

The text

(1) A well permit holder must notify the regulator, in electronic form, of the following actions taken by the permit holder: (a) beginning the construction of a well; (b) beginning the drilling of a well; (c) releasing a rig, if drilling is completed or temporarily suspended; (d) resuming drilling operations after a temporary suspension. (2) The notice under subsection (1) (a) must be sent at least 2 days before construction is to begin, and a notice under subsection (1) (b), (c) or (d) must be sent within 24 hours of the action being taken.
Read the Drilling and Production Regulation on BC Laws ↗

Made under Energy Resource Activities Act, SBC 2008, c. 36.