Drilling and Production Regulation, B.C. Reg. 282/2010
Section 43
Flaring notification and reporting
Cite as Drilling and Production Regulation, B.C. Reg. 282/2010, s. 43 · last amended April 1, 2025 · read from BC Laws on November 17, 2026
The text
(1) A permit holder must notify the regulator at least 24 hours before a planned flaring event if the quantity of gas to be flared exceeds 10 000 m3.
(2) If an unplanned flaring event occurs and the quantity of flared gas exceeds 10 000 m3, the permit holder must notify the regulator within 24 hours of the flaring event.
(3) A permit holder must maintain a log of all flaring that occurs at each facility.
(4) When gas is flared at a well, the permit holder with respect to the well must report the quantity of gas flared to the regulator no later than 20 days after the end of the month in which the flaring occurred.
Read the Drilling and Production Regulation on BC Laws ↗
Made under Energy Resource Activities Act, SBC 2008, c. 36.