Drilling and Production Regulation, B.C. Reg. 282/2010
Section 36
Completion and workover reports
Cite as Drilling and Production Regulation, B.C. Reg. 282/2010, s. 36 · last amended April 1, 2025 · read from BC Laws on November 17, 2026
The text
(1) For each separate completion or workover operation on a well, a well permit holder must submit to the regulator, within 30 days of the end of each completion or workover operation, a report, in chronological format, detailing all significant operations, treatments and resulting well behaviour, and including a downhole schematic diagram.
(2) A report under subsection (1) is not required for maintenance operations, including injection of corrosion inhibitors, scale removal or pressure testing operations.
Read the Drilling and Production Regulation on BC Laws ↗
Made under Energy Resource Activities Act, SBC 2008, c. 36.