Drilling and Production Regulation, B.C. Reg. 282/2010
Section 33
Deviation and directional surveys
Cite as Drilling and Production Regulation, B.C. Reg. 282/2010, s. 33 · last amended April 1, 2025 · read from BC Laws on November 17, 2026
The text
(1) A well permit holder must ensure that deviation surveys are made during drilling at intervals not exceeding 150 m in depth, unless there are significant wellbore stability problems, in which case a survey may be omitted.
(2) A well permit holder must ensure that a directional survey of a well to total depth is made if
(a) the surface position of the well is nearer to the boundary of its target area than 2% of the measured depth of the well,
(b) the surface position of the well is outside its target area, or
(c) the well is directionally drilled.
(3) A well permit holder must submit to the regulator within 14 days of rig release the results of the directional survey under subsection (2).
(4) A permit holder must not drill a well, other than a relief well, so that it intersects with an existing well.
Read the Drilling and Production Regulation on BC Laws ↗