Drilling and Production Regulation, B.C. Reg. 282/2010

Section 32

Daily drilling reports

Cite as Drilling and Production Regulation, B.C. Reg. 282/2010, s. 32 · last amended April 1, 2025 · read from BC Laws on November 17, 2026

The text

(1) A well permit holder of well being drilled or otherwise worked on must (a) ensure that a daily drilling report (tour sheet) is kept at the well site, (b) if a kick occurs during drilling operations, notify the regulator immediately and submit a written kick report to the regulator within one day of the incident, (c) submit a copy of the daily drilling report (tour sheet) to the regulator within 30 days of rig release, (d) submit a summary report of drilling operations to the regulator within 4 days of the following: (i) the rig is released; (ii) drilling operations have ceased with the intention of resuming drilling at a later date, and (e) maintain all data recorded by the electronic drilling recorder for at least 30 days from the date of rig release. (2) A daily drilling report (tour sheet) under subsection (1) (a) must set out complete data on all operations performed during the day, including but not limited to the following: (a) the depth at the beginning and end of each tour; (b) all casing data, including size, type, grade, weight, whether new or used and the depth at which the casing is set; (c) particulars of cementing; (d) a report of any tests made, including blowout prevention system function tests; (e) full details of all formation tests, unless the details are submitted on a confidential report form provided by the regulator; (f) details of any loss of drilling fluid into the formation; (g) the allocation of time to each operation; (h) the name of the drilling contractor or service company and rig number; (i) the spud and rig release dates; (j) details of any casing bowl welding; (k) the results of all deviation surveys.
Read the Drilling and Production Regulation on BC Laws ↗

Made under Energy Resource Activities Act, SBC 2008, c. 36.