In this Part:
“clean coal” means coal that has undergone a washing process to remove waste before it is transported from the mine site for marketing or testing;
“industrial minerals” means the substances listed in Appendix 3;
“mine” has the same meaning as in the Mines Act;
“mineral mine” means a mine where a mineral, as defined in the Mineral Tenure Act, is or could be mined, but does not include a mine where industrial minerals are or could be mined;
“offshore mine” means a platform, artificial island or other physical work or structure, including any associated facilities, that is intended to be used, or is used, for the exploration for or production of a minable substance from the foreshore or submerged land along a marine coastline, or from an offshore site located in salt water;
“pay dirt” means mined placer gravel that is or could be processed in a sluice box, wash plant or other device for extracting precious metals;
“permitted for disturbance” in relation to land, means that the land would be or has been disturbed by mining activities approved under a Mines Act permit or another permit that was issued as part of a previous mine approval;
“placer mineral mine” means a mine where a placer mineral, as defined in the Mineral Tenure Act, is or could be mined;
“production capacity”, in relation to a mine project, means a capacity to generate product for marketing or testing, not including waste materials;
“proposed project”, in relation to the proposed modification of the existing facility referred to in section 10 (1) or (2), means all of the physical works and structures of the existing facility together with all of the physical works and structures that would be constructed as part of the proposed modification;
“quarry” means a quarry or other operation where construction stone, an industrial mineral or another substance is or could be mined, but does not include a mineral mine, placer mineral mine or coal mine or a sand or gravel pit;
“raw coal” means coal that does not require processing in a coal preparation plant before it is transported from the mine site for marketing or testing;
“threshold E” means the criteria described in section 10 (1);
“threshold F” means the criteria described in section 10 (2);
“threshold G” means the criteria described in section 10 (3).