Liquefied Natural Gas Facility Regulation, B.C. Reg. 146/2014
Section 3
Submissions before construction
Cite as Liquefied Natural Gas Facility Regulation, B.C. Reg. 146/2014, s. 3 · last amended April 1, 2025 · read from BC Laws on November 17, 2026
The text
(1) An LNG facility permit holder must not begin any phase of the construction of an LNG facility unless the permit holder has submitted all of the following to the regulator, to its satisfaction:
(a) a description of what will be constructed during that phase of construction;
(b) an engineering design completed in accordance with section 4;
(c) detailed plot plans;
(d) reports that include findings and recommendations respecting each of the following:
(i) an updated hazard identification study;
(ii) a process hazard analysis;
(iii) a safety integrity level study;
(e) a report referred to in section 4 (4) (a) and (5), as applicable;
(f) a report from either
(i) a third party acceptable to the regulator, in the case of a modular unit that is to be constructed outside British Columbia, or
(ii) a qualified professional, in any other case,
indicating that all of the elements of a quality assurance program necessary for the construction of the LNG facility or modular unit are documented;
(g) subject to subsections (2) and (3), a notice, at least 14 days before beginning construction, of the permit holder's intention to begin construction.
(2) An LNG facility permit holder may not submit a notice referred to in subsection (1) (g) for the first phase of the construction of an LNG facility unless the permit holder has submitted to the regulator, to its satisfaction,
(a) an updated construction schedule for the entire LNG facility, and
(b) a description of the management of change system that will be followed during the construction phase and throughout the operational life of the LNG facility.
(3) On receiving the notice referred to in subsection (1) (g), the regulator may
(a) extend the period referred to in subsection (1) (g) if the regulator considers it necessary to further review submissions referred to in subsection (1) (a) to (f), or
(b) reduce the period referred to in subsection (1) (g).
(4) An LNG facility permit holder must maintain the documents referred to in subsection (1) (f).