Liquefied Natural Gas Facility Regulation, B.C. Reg. 146/2014
Section 4
Engineering design and LNG facility siting
Cite as Liquefied Natural Gas Facility Regulation, B.C. Reg. 146/2014, s. 4 · last amended April 1, 2025 · read from BC Laws on November 17, 2026
The text
(1) An LNG facility permit holder must, subject to anything in the LNG facility permit, ensure that the engineering design and siting for an LNG facility
(a) subject to subsections (4) and (5), is completed in accordance with CSA Z276,
(b) takes into account the results referred to in section 3 (1) (d),
(c) is based on a consideration of the effects of noise associated with the normal operation of the LNG facility,
(d) includes designs for a storage tank system that
(i) includes tank design fatigue life, and
(ii) complies with subsection (2), and
(e) is based on a consideration of the effects of light associated with the normal operation of the LNG facility.
(2) A storage tank system at an LNG facility must
(a) conform with CSA Z276, or
(b) Repealed. [B.C. Reg. 80/2016, s. 3 (e).]
(c) provide for the safe storage of LNG at a level of protection from failure that meets or exceeds the level of protection provided under paragraph (a).
(3) Subject to subsections (4) and (5), an LNG facility permit holder must ensure a flare or ignited vent stack is sited so that the thermal radiation flux at the locations identified in column 1 of Schedule 1 does not exceed the maximum radiation flux identified in column 2.
(4) Instead of complying with subsection (1) (a), an LNG facility permit holder may complete the engineering design and site the LNG facility in a manner consistent with the results of a quantitative risk assessment if the permit holder
(a) completes the quantitative risk assessment and submits to the regulator a report respecting that assessment, including an identification of key assumptions, input data, methodologies and consequence analyses made or used in carrying out the assessment, and
(b) demonstrates to the regulator that the risks associated with the completed engineering design and siting of the LNG facility
(i) are as low as reasonably practicable, and
(ii) do not fall within the range indicated as intolerable risks in the chart in Schedule 2.
(5) If, in complying with subsection (4), an LNG facility permit holder demonstrates that the risks associated with the completion of the engineering design for the LNG facility and the siting of the LNG facility fall within the range indicated as ALARP in the chart in Schedule 2, the permit holder must include in the report referred to in subsection (4) (a) an evaluation of its risk reduction strategies, mitigation measures and recommended actions to substantiate compliance with subsection (4) (b) (i).
(6) An LNG facility permit holder must prepare and maintain records that evidence the permit holder's compliance with subsections (1) to (5), as applicable.
Read the Liquefied Natural Gas Facility Regulation on BC Laws ↗
Made under Energy Resource Activities Act, SBC 2008, c. 36.