Power Engineers, Boiler, Pressure Vessel and Refrigeration Safety Regulation, B.C. Reg. 104/2004

Section 62.2

Transition — operating permits for plants

Cite as Power Engineers, Boiler, Pressure Vessel and Refrigeration Safety Regulation, B.C. Reg. 104/2004, s. 62.2 · last amended December 31, 2024 · read from BC Laws on November 17, 2026

The text

(1) In this section, “pre-permit owner” means an owner of a plant (a) at which regulated work was being performed in accordance with this regulation as it read immediately before October 2, 2017, and (b) that is required under section 62.1 to be the subject of an operating permit. (2) A pre-permit owner is deemed to hold an operating permit in respect of the owner's plant until the earliest of the following dates: (a) the date on which an operating permit is issued in respect of the plant; (b) October 1, 2019. (3) Despite section 69.1, that section does not apply to a pre-permit owner in respect of the owner's plant until the earliest of the dates referred to in subsection (2). (4) A pre-permit owner who applies before October 1, 2019, for an operating permit in respect of the owner's plant is not required to pay a fee in respect of the application. (5) This section is repealed effective October 2, 2019.
Read the Power Engineers, Boiler, Pressure Vessel and Refrigeration Safety Regulation on BC Laws ↗

Made under Safety Standards Act, SBC 2003, c. 39.