- FAST 41 AND THE FEDERAL PERMITTING IMPROVEMENT STEERING COUNCIL: PROGRESS TO DATE AND NEXT STEPS [Senate Hearing 115-334] [From the U.S. Government Publishing Office] S. Hrg. 115-334 FAST 41 AND THE FEDERAL PERMITTING IMPROVEMENT STEERING COUNCIL: PROGRESS TO DATE AND NEXT STEPS ======================================================================= ROUNDTABLE before the PERMANENT SUBCOMMITTEE ON INVESTIGATIONS of the COMMITTEE ON HOMELAND SECURITY AND GOVERNMENTAL AFFAIRS UNITED STATES SENATE ONE HUNDRED FIFTEENTH CONGRESS SECOND SESSION __________ JUNE 27, 2018 __________ Available via the World Wide Web: http://www.fdsys.gov Printed for the use of the Committee on Homeland Security and Governmental Affairs [GRAPHIC(S) NOT AVAILABLE IN TIFF FORMAT] _________ U.S. GOVERNMENT PUBLISHING OFFICE 31-410 PDF WASHINGTON : 2018 COMMITTEE ON HOMELAND SECURITY AND GOVERNMENTAL AFFAIRS RON JOHNSON, Wisconsin, Chairman JOHN McCAIN, Arizona CLAIRE McCASKILL, Missouri ROB PORTMAN, Ohio THOMAS R. CARPER, Delaware RAND PAUL, Kentucky HEIDI HEITKAMP, North Dakota JAMES LANKFORD, Oklahoma GARY C. PETERS, Michigan MICHAEL B. ENZI, Wyoming MAGGIE HASSAN, New Hampshire JOHN HOEVEN, North Dakota KAMALA D. HARRIS, California STEVE DAINES, Montana DOUG JONES, Alabama Christopher R. Hixon, Staff Director Margaret E. Daum, Minority Staff Director Laura W. Kilbride, Chief Clerk Bonni Dinerstein, Hearing Clerk PERMANENT SUBCOMMITTEE ON INVESTIGATIONS ROB PORTMAN, Ohio Chairman JOHN McCAIN, Arizona THOMAS R. CARPER, Delaware RAND PAUL, Kentucky HEIDI HEITKAMP, North Dakota JAMES LANKFORD, Oklahoma GARY C. PETERS, Michigan STEVE DAINES, Montana MAGGIE HASSAN, New Hampshire Andrew Dockham, Staff Director and Chief Counsel John Kilvington, Minority Staff Director Kate Kielceski, Chief Clerk C O N T E N T S ------ Opening statement: Page Senator Portman.............................................. 1 Senator McCaskill............................................ 3 Senator Harris............................................... 24 Prepared statement: Senator Portman.............................................. 33 WITNESSES Wednesday, June 27, 2018 Alexander Herrgott, Associate Director for Infrastructure, Council on Environmental Quality............................... 4 Angela Colamaria, Acting Executive Director, Federal Permitting Improvement Steering Council................................... 7 Joseph Johnson, Ph.D., Executive Director, Federal Regulatory Process Review and Analysis, Environment, Technology, and Regulatory Affairs, U.S. Chamber of Commerce................... 9 Christy Goldfuss, Senior Vice President, Energy and Environment Policy, Center for American Progress........................... 10 Sean McGarvey, President, North America's Building Trades Union.. 12 Hon. Mary L. Landrieu, Senior Policy Advisor, Van Ness Feldman, LLP; Accompanied by Megan K. Terrell, Legal Advisor, Coastal Activities, Environment and Natural Resources Office of the Governor of Louisiana.......................................... 14 Jolene S. Thompson, Executive Vice President, Member Services and External Affairs, American Municipal Power, Inc................ 16 Alphabetical List of Witnesses Colamaria, Angela: Testimony.................................................... 7 Prepared statement........................................... 38 Goldfuss, Christy: Testimony.................................................... 10 Prepared statement........................................... 47 Herrgott, Alexander: Testimony.................................................... 4 Prepared statement........................................... 35 Johnson, Joseph, Ph.D.: Testimony.................................................... 9 Prepared statement........................................... 42 Landrieu, Hon. Mary L.: Testimony.................................................... 14 Prepared statement........................................... 56 McGarvey, Sean: Testimony.................................................... 12 Prepared statement........................................... 51 Thompson, Jolene: Testimony.................................................... 16 Prepared statement........................................... 59 APPENDIX Statements submitted for the Record from: Marc S. Gerken, PE, CEO/President, American Municipal Power, Inc........................................................ 77 Coastal Protection and Restoration Authority................. 93 Responses to post-hearing questions for the Record from: Ms. Colamaria................................................ 103 ROUNDTABLE ON FAST-41 AND THE FEDERAL PERMITTING IMPROVEMENT STEERING COUNCIL: PROGRESS TO DATE AND NEXT STEPS ---------- WEDNESDAY, JUNE 27, 2018 U.S. Senate, Permanent Subcommittee on Investigations, of the Committee on Homeland Security and Governmental Affairs, Washington, DC. The Subcommittee met, pursuant to notice, at 2:34 p.m., in room 106, Dirksen Senate Office Building, Hon. Rob Portman presiding. Present: Senators Portman, McCaskill, Peters, and Harris. OPENING STATEMENT OF SENATOR PORTMAN\1\ Senator Portman. All right, we are going to get going. --------------------------------------------------------------------------- \1\ The prepared statement of Senator Portman appears in the Appendix on page 33. --------------------------------------------------------------------------- Senator McCaskill I know has three things going on at once, as do all of us, and yet we have something really important to talk about today so we are delighted you are here. We may have other colleagues who come in and out. Everybody is busy today. It is kind of crazy. I guess I need to do this. [Pounds gavel.] I just love doing that. First of all, you know why we are here. We are here to talk about Federal permitting, and this is, I think, a great story, what we have accomplished so far with very little resources, too little in my view, and with a permanent executive director. I think the Obama Administration was slow to get it started. I think the Trump Administration has not been aggressive enough in permitting a permitting reform executive director to be permanent. I think Congress has not provided adequate funding. But notwithstanding all that, we have made real progress and we are going to continue to do so. This issue affects everything. It affects the roads we drive, the bridges we cross, the airports we use, the infrastructure projects, including environmental projects, which we will hear about today, that are important, and the electricity that we use. It is all about infrastructure. Right now the system, as we have heard from our constituents constantly, takes too long. It is complicated, sometimes very bureaucratic. Those delays have real costs. They have costs in terms of money, in terms of jobs, in terms of safety, in terms of the ability for the private sector to invest as well as the public sector, and often it is a matching investment. It is an opportunity to say as we improve infrastructure and maybe do something exciting later this year on legislation, let us be sure that the permitting part of this is fixed. That way the Federal dollar will go even further toward doing what everybody wants to do, I hope, to create more jobs and more economic activity through better infrastructure. Five years ago, actually, probably 7 years ago, Senator McCaskill and I started in on this project, and about 2\1/2\ years ago we passed legislation. That was in 2015, and it is called Fixing America's Surface Transportation (FAST-41), because it was part of the FAST Act, Title 41. FAST-41 tries to streamline the permitting process and it focuses on the largest infrastructure projects. We call them covered projects. For those listening today, when we talk about covered projects, those are ones that, under FAST-41, are included. We also created the Federal Permitting Improvement Steering Council (FPISC). We will hear a lot about the Council today, bringing all the permitting agencies together at the start of covered projects to coordinate and streamline the permitting process. I think we will hear some good things today about that, but also the need, again, for more resources. The law has a number of common-sense measures, encourages agencies to do their reviews concurrently rather than sequentially. That always seemed like a no-brainer to us. Let us not finish one of maybe a couple dozen regulatory reviews and then have to go to the next and the next. Let us try to do them together. It also requires one agency to be the lead agency. Common sense, this provides for some accountability, so that there is some responsibility built into the system. It also requires agencies to post a timeline on a public online dashboard so that project sponsors and the public can keep track of where they are in the permitting process, another common-sense measure that is making a big difference in my view, with these covered projects. When we first came up with this idea, and I think Senator McCaskill would agree with this, we had hoped it would save money, both by project sponsors and government, and save time. Based on the testimony we are going to hear today, I think it is safe to say that much of what we had hoped for has happened. Expectations have been met in the sense that there have been some significant savings in time and money. Over the past year and a half, the Council informs me that they have saved projects $1 billion in avoided costs. That is a pretty good start, $1 billion. We will hear more about that through your testimony. And we have done this without a permanent executive director and with a bare minimum of funding. I do want to take a moment to offer Acting Executive Director Angie Colamaria, who is with us here today at the panel, former Acting Executive Director and current Deputy Director Janet Pfleeger, who is here, and your whole team, our sincere thanks. You pulled together groups. I have had a chance to speak with the Council and seen your work first-hand. We need a permanent executive director. I hope that will happen soon. We will also continue to advocate for funding for the Council that is adequate to be able to have enough infrastructure within the Council to get infrastructure moving. Based on our experience of the past 2\1/2\ years, and listening to you all and talking to outside stakeholders, Senator McCaskill and I have now introduced follow-on legislation. It is called S. 3017. It is the Federal Permitting Reform and Jobs Act. The whole idea is to improve FAST-41 and learn the lessons, what worked, what did not work, and how we can make it work better. Most critically to me, the bill would remove the 7-year sunset in FAST-41. We know enough about it now to know that we should not be sunsetting this in 7 years. We should keep it going. It would also allow more projects to apply to be covered. I think that is important, including some areas like transportation and energy. You definitely want to be covered. It would set a 2-year goal for each project's permitting process. By the way, if agencies determine they will need longer to permit a project they can explain why and what they are going to do to mitigate those delays. I think that 2-year goal is really important. The bill will allow the Permitting Council to consult on non-covered projects as well, to take your expertise and be able to use it for non-covered projects, if asked, and to help resolve conflicts. These are modest, smart, common-sense reforms that will build on the success we are already seeing. We are looking forward to hearing from each of the roundtable participants today about FAST-41's performance so far, what you think has worked, what has not worked, and where we can improve the permitting process going forward. With that I would turn to my former Ranking Member on the Subcommittee and co-author, Senator McCaskill. OPENING STATEMENT OF SENATOR McCASKILL Senator McCaskill. Thank you, Senator Portman. We have been working on this for a long time but things do not happen around here quickly. Good ideas have a way of latching on, and this is a good idea. This is an idea that is going to make a difference in terms of saving taxpayers money. It is going to make a difference in terms of being able to get infrastructure in place in a way that saves local jurisdictions money and saves money for the companies that are willing to invest in some of these infrastructure projects. It is a win-win all the way around. I am disappointed, along with my colleague, that we do not have a permanent executive director. I am disappointed, since we have already saved $1 billion, that the President's budget only allocated $1 million for the Council when we know the requirements to do it right would take about $10 million. That is a small amount. If they have managed to already save $1 billion, the potential is huge in terms of the amount of money that could be saved if this works the way it is supposed to work. I think my friend from Ohio will be more persuasive with this Administration than I will be. But we have played tag team before, we have handed the baton back and forth, and that is what it means to work in a bipartisan way. I am hopeful that we can continue to do that and get our new bill through, which will make improvements. But most importantly, make this work as robustly as it has the potential to work, in terms of saving money and putting some common sense into the public sector that would match the desires of the private sector when they are more driven by a bottom line. Thank you and I will look forward to our conversations and the information that we get here today. Senator Portman. Excellent. Senator Peters, who was just here, had to leave, may come back, and other Senators may come and go and we are going to be informal here so allow them to interject when they come in. We are going to hear from our participants now. Let me introduce them briefly. Alexander Herrgott currently serves as the Associate Director for Infrastructure on the Council on Environmental Quality (CEQ). Angela Colamaria, I already mentioned, currently serves as Acting Executive Director of the Federal Permitting Improvement Council. Joe Johnson is the Executive Director of Federal Regulatory Process Review and Analysis for Environment, Technology, and Regulatory Affairs--fit that on a business card--at the U.S. Chamber of Commerce. Christy Goldfuss is the Senior Vice President for Energy and Environment Policy at the Center for American Progress. Sean McGarvey is the President of North America's Building Trades Union. Our former colleague, Senator Landrieu, is here. She currently serves as Senior Policy Advisor at Van Ness Feldman. I understand that Megan Terrell, Legal Advisor to Louisiana Governor John Bel Edwards on Coastal Activities, Environment, and Natural Resources is also on hand. Thank you for being here, Megan, to answer questions about the project. Finally, last but not least, we have Jolene Thompson, who is the Executive Vice President of Member Services and External Affairs for the American Municipal Power (AMP), Inc., which is the sponsor of the R.C. Byrd hydropower project in Ohio. Actually, it was American Municipal Power that first came to me, probably 8 years ago, about this permitting problem, and the difficulty of getting private investment, because the capital is not that patient. Investors were going somewhere else because their permitting was taking so long. We look forward to hearing how things are going and what you think about it. Mr. Herrgott, we will hear from you first. We are going to try to keep these to 5 minutes on the timer. TESTIMONY OF ALEXANDER HERRGOTT,\1\ ASSOCIATE DIRECTOR FOR INFRASTRUCTURE, COUNCIL ON ENVIRONMENTAL QUALITY Mr. Herrgott. Before I begin, if you will permit me a small sentimental moment. In 2015, when I was senior staff for Senator Inhofe negotiating the FAST Act, my father, unfortunately, passed away, and I rushed back to Arizona. Two days later Senator Boxer called me and said, ``Would you please come back to the Hill'' because the bill had been hung up on our streamlining negotiations. Right outside this room, Senator Boxer gave me a hug, as we walked back in with Senate staff, and she said, ``Get back to work.'' I think that spirit of bipartisanship is something that Senator McCaskill and you, Senator Portman, have exemplified is something that we need to remember when we are talking about FAST-41 and the streamlining initiatives that the President has engaged in, because once we inject facts into this debate we can make pragmatic successes together. --------------------------------------------------------------------------- \1\ The prepared statement of Mr. Herrgott appears in the Appendix on page 35. --------------------------------------------------------------------------- Thank you for having this hearing because I think it is an opportunity for us to show the world how we can actually turn a light on a process that previously has been somewhat of a black box. Senator Portman, Ranking Member McCaskill, thank you for the invitation to discuss the Federal permitting process for major infrastructure projects. I am looking forward to having a meaningful dialogue on the topic today as we work toward a shared goal of reducing permitting delays, providing the American people the modernized infrastructure they deserve. As you know, a major cause of delay in the permitting process for major infrastructure projects is that there are too many decisionmakers without effective cross-agency coordination or communication. Multiple Federal agencies oversee dozens of Federal statutes that project sponsors must navigate before beginning construction. Over time, this has created a redundant and often inconsistent Federal permitting process with no single framework and no varying times. We can do better. By looking at the chart behind me, you can see that you need a Ph.D. or you need to hire a consultant to navigate the 29 statutes and 5 Executive Orders (EO) that dictate a process just to build a highway project. For example, a highway project could use as many as 10 different Federal agencies involved in 16 different permitting decisions, in addition to the State, local, and tribal permitting schedules. The result is a Federal permitting process that often takes too long, increases costs, and creates uncertainty. The Administration is actively trying to fix this problem by addressing the challenges while maintaining environmental protections. With process enhancements and common-sense, harmonized approaches among the Federal agencies, infrastructure projects will move through the environmental permitting process more efficiently. Federal agency coordination is imperative to long- term process reforms throughout the agencies. That is why, last August, President Trump signed Executive Order 13807, implementing a policy we have referred to as ``One Federal Decision.'' Under this policy, Federal agencies will administer the National Environmental Policy Act (NEPA) procedures so that a single Environmental Impact Statement (EIS) and a single Record of Decision (ROD) and that for all applicable permitting decisions it will conduct it concurrently with the NEPA process. One Federal Decision also provides that Federal agencies will seek to complete the environmental review process within an average of 2 years. In April, President Trump announced that 11 Federal agencies and the Permitting Council signed a Memorandum of Understanding (MOU) where agencies agreed to an unprecedented level of coordination and communication in conducting their environmental reviews. Under this MOU, CEQ, in coordination with other White House components, has convened a Federal agency working group to develop the framework under which the Permitting Council and other agencies will implement this Executive Order. The agencies are working together to identify the appropriate level of analysis needed to conduct the necessary environmental reviews, synchronize the public engagement, and complete the other procedural steps to ensure that all necessary decisions are made within the timelines established by the Executive Order. Since the agencies signed the MOU, CEQ and agency leadership have been coordinating extensively on agency streamlining efforts to identify and implement policy process and regulatory changes. Some significant steps have already been taken. For example, the Federal Highway Administration signed an agreement with the Fish and Wildlife Service (FWS), the U.S. Army Corps of Engineers (USACE), the Environmental Protection Agency (EPA), the Coast Guard, and the National Oceanic and Atmospheric Administration (NOAA), coordinating agencies' processes and committing to working together to achieve the goals of the Executive Order, something that seemed so simple but something that previously had been so complicated. Additionally, the Secretary of Interior issued a Secretarial Order and additional guidance that advanced the department's NEPA streamlining efforts within the Executive Order. Next, the Army Corps of Engineers issued a Section 408 policy change adopting other agencies' NEPA documents and issued a policy to improve coordination and risk management among the Federal family. This is not rocket science. Many agencies are expanding the use of time-saving, programmatic consultation, improving internal clearance processes along with increasing agency capacity for staffing projects. Moving forward, agencies will be issuing directives and conducting training with all levels of organizations, from headquarters down to the field offices, which we all know is some of the most important activity, to ensure that timetables and plans to implement One Federal Decision are done nationwide. And the Office of Management and Budget (OMB) and CEQ, in collaboration with agencies, are implementing a performance accountability system to ensure agencies meet the permitting timetables. While CEQ is focused on the development of a better process for all infrastructure project permitting, the Permitting Council is focused on overcoming obstacles on a project-by- project basis. Ms. Colamaria will expand further on the implementation of FAST-41 and the Permitting Council's role in streamlining the Federal permitting process. As a result of One Federal Decision, and the work of the Permitting Council, Federal environmental review and permitting processes will be streamlined, more transparent, and, most importantly, more predictable. Our goal is to give the American people the process they deserve and not the process they have. We are looking forward to continuing to work together with you on advancing One Federal Decision. Thank you again for the invitation, and I look forward to the discussion. Senator Portman. Thank you, Mr. Herrgott. We will now hear from Ms. Colamaria. TESTIMONY OF ANGELA COLAMARIA,\1\ ACTING EXECUTIVE DIRECTOR, FEDERAL PERMITTING IMPROVEMENT STEERING COUNCIL Ms. Colamaria. Thank you. Senator Portman, Senator McCaskill, thank you for this opportunity to speak to you today about our progress in improving the Federal permitting process for infrastructure projects. --------------------------------------------------------------------------- \1\ The prepared statement of Ms. Colamaria appears in the Appendix on page 38. --------------------------------------------------------------------------- Throughout my career, I have participated in the Federal permitting process from various perspectives. As an attorney, I represented project sponsors who were trying to build new projects. I worked within a permitting agency where I oversaw the NEPA review for infrastructure projects. I am currently leading a working group tasked with improving the Federal permitting process across all agencies. And after FAST-41 was passed in December 2015, I helped lead the Administration's efforts to set up the Council and the new governance system and to provide guidance to agencies as we started to implement FAST-41. FAST-41 codifies many of the best practices that experts identify as essential to creating the sea change needed to overall process improvements for the Federal permitting process. This is all to say I believe in the principles of FAST-41 and it is my priority to ensure it is a success. Today I want to describe some of the project-specific successes we have been able to achieve so far, using the tools provided by FAST-41. We have accomplished this in three main ways: breaking down silos through enhanced coordination, ensuring efficiency in the permitting process, and providing oversight and issue resolution. As Senator Portman mentioned, these efforts already have resulted in saving FAST-41 projects over $1 billion in costs through avoided permitting process delays. I would first like to point to our efforts to break down silos across government to create a more standardized, predictable permitting process. The enhanced interagency coordination that supports our ability to identify and resolve potential impediments to the permitting process are led by deputy secretary-level Council members as well as agency chief environmental review and permitting officers (CERPOs). My office has established regular in-person meetings to bring these CERPOs together and appropriate staff for in-depth conversations on specific FAST-41 projects. These meetings allow interagency discussion and identification of potential delays so that they can be resolved early in the process. To my second point, ensuring efficiency in the permitting process, my office ensures agencies work together to ensure each FAST-41 project has a permitting schedule that is optimized. For example, my office serves as a communication bridge to connect personnel at all levels of the government with staff and subject matter expertise, both within an agency and then across agencies, to identify and resolve project issues. My third point on oversight and issue resolution, my office uses FAST-41 tools, including the Coordinated Project Plans (CPPs), the publicly available permitting dashboard, agency representatives, and that is both at the working group level, the CERPO level, and the Council level, and the provisions limiting modifications to permitting timetables, all to ensure that each FAST-41 project receives the most efficient and effective permitting process possible. I would like to share just three examples of our work this year in keeping projects on schedule and on track. The first success story is our effort to facilitate cooperation among agencies involved in the Nexus Gas Transmission Line, to ensure an efficient and timely 106 review under the National Historic Preservation Act. The resulting coordination among agencies allowed subsequent authorizations to move forward and saved an estimated 6 months and $300 million in capital costs to the project. The second success story results from my office's oversight role leading to the successful drafting and implementation of a Programmatic Agreement for the 106 review for two FAST-41 projects. Our actions supported the Advisory Council on Historic Preservation in facilitating issue resolution with three different Federal agencies and the States that were involved in that project. For one of those projects, the Atlantic Coast Pipeline, the completion of the Programmatic Agreement allowed other Federal permitting actions to proceed forward, which then allowed the project sponsor to use that year's tree-clearing window for construction. That avoided a 1- year delay for that project. The final success story is an example of an effective Federal-State coordination in the Mid-Barataria Sediment Diversion (MBSD) Project. I will not say a lot about that because I know we have distinguished speakers that are going to talk about that some more. But the project created the first FAST-41 MOU, which established clear roles and responsibilities for not just the Federal agencies but also the State agencies involved in that project. To address complex issues related to NEPA implementation, our office worked with CEQ to provide subject matter expertise to the agencies to help them identify the next steps for that project. These actions resulted in a reduction in the current permitting schedule by nearly 2 years for this project. In summary, I look forward to building on the $1 billion in avoided permitting delays as we work to fully implement the potential of FAST-41, while maintaining important environmental protections. Thank you. Senator Portman. Great. Thank you. Dr. Johnson. TESTIMONY OF JOSEPH JOHNSON, PH.D.,\1\ EXECUTIVE DIRECTOR, FEDERAL REGULATORY PROCESS REVIEW AND ANALYSIS, ENVIRONMENT, TECHNOLOGY, AND REGULATORY AFFAIRS, U.S. CHAMBER OF COMMERCE Mr. Johnson. Thank you. Good afternoon, Senator Portman, Ranking Member McCaskill. The U.S. Chamber of Commerce has been involved in permit streamlining for a long time. The Chamber greatly appreciates this Committee's interest in Federal permit streamlining and the work the Committee did in the 114th Congress that led to passage of Title 41 in the Fixing America's Surface Transportation Act. --------------------------------------------------------------------------- \1-\ The prepared statement of Mr. Johnson appears in the Appendix on page 42. --------------------------------------------------------------------------- My statement today details the Chamber's strong support for the Federal permit streamlining provisions in FAST-41, our members' experience with it since passage, and our continued support for next steps to improve the permitting process in S. 3017, the Federal Permitting Reform and Jobs Act. FAST-41 actually did a lot. It established the multi-agency Federal Permitting Improvement Steering Council and it established a process that includes designation of lead agency, timetables for projects, coordination between agencies, dispute resolution mechanisms, and judicial review reforms. One example of the benefits of FAST-41 is the transparency and certainty generated by the permitting timetable. Simply put, our members find this feature indispensable. Knowing an expected schedule for all the steps in the permitting process from the beginning allows project sponsors to better coordinate and manage scheduling of contractors, suppliers, and resource needs. Simply by reducing the uncertainty of permitting through the timetable, coupled with the other provisions to keep this process on track, our members who work on covered projects, including those all along the supply chain, not only project sponsors, are better able to manage resources, reduce down time and waste, and manage workflows to get more done, hire more employees, and help grow the economy. With the Council recently reporting that 97 percent of covered projects had timetables in their 2017 annual report, we are near full implementation on covered projects across all agencies. This is a significant step forward. Not surprisingly, Chamber members are also highly supportive of speeding up the permitting process. The Council recently reported that they were able to reduce the permitting timetable on the Mid-Barataria project by 22 months. I am not the expert here on that project. I will not go into details but this is a significant step. It is only one case study but it is a positive indication that the FAST-41 process works and that we should expect to see more benefits from reductions in permitting timetables in the near future. It has only been 2\1/2\ years since implementation began and we are already beginning to see massive payoffs in terms of projects scheduling reductions. An important next step is further improving the permitting process and increasing the number of covered projects. To that end, the Chamber strongly supports S. 3017, the Federal Permitting Reform and Jobs Act. The bill does four crucial things-eliminating the 7-year sunset in FAST-41, by far the most important. This will ensure that FAST-41 continues into the future and serves as the foundation for additional future permitting reforms. Two, it expands the statutory definition of covered projects. By removing exclusions in FAST-41, more transportation infrastructure projects will become eligible. This is crucial for modernizing America's infrastructure moving forward. Three, it sets a 2-year goal for permitting covered projects, by requiring agencies to submit a plan that adheres to this timetable. An expected 2-year permitting schedule is a powerful incentive to increase investment in covered projects. The Chamber firmly believes there is no good reason why any Federal permit should ever take longer than 2 years to obtain. And four, it expands the Council's consulting authority by codifying provisions of EO 13807, which grants the Council enhanced consultation authority and expands the Council's dispute resolution authority, allowing for it to better coordinate agency actions and keep the process on schedule to further reduce project timetables. In conclusion, the Chamber applauds the work that has been done to implement FAST-41 so successfully and expediently, and strongly supports passage of S. 3017. Early successes have shown that the FAST-41 process works. Enhancing the system with the common-sense improvements in S. 3017 will allow a broader range of projects to take advantage of improvements in the permitting process and ensure that this process continues to be refined without the clock running out on FAST-41. In January 2018, the Chamber laid out a four-point plan to modernize American's infrastructure, of which enhancing the usage rate and effectiveness of FAST-41 is one of the four key components. We look forward to working with this Committee to ensure that we have the necessary tools to modernize America's infrastructure moving forward. Thank you. Senator Portman. Thank you, Dr. Johnson. Ms. Goldfuss. TESTIMONY OF CHRISTY GOLDFUSS,\1\ SENIOR VICE PRESIDENT, ENERGY AND ENVIRONMENT POLICY, CENTER FOR AMERICAN PROGRESS Ms. Goldfuss. Thank you. Thank you for having me today, Senators Portman and McCaskill. --------------------------------------------------------------------------- \1\ The prepared statement of Ms. Goldfuss appears in the Appendix on page 47. --------------------------------------------------------------------------- What we are talking about today, as you two know very well, is not and should not be politically divisive. Both Republicans and Democrats have sought to improve the process by which the government permits major infrastructure projects. As Managing Director at the Council on Environmental Quality under President Obama, I worked closely with my colleagues at OMB and the National Economic Council (NEC), at the time, to implement the FAST Act by standing up the Permitting Council, writing its inaugural guidance, and staffing it with talented people, some who are in this room still, who knew how to move the levers of government to overcome barriers. Prior to being at CEQ, I was Deputy Director at the National Park Service (NPS), which gave me a front-row seat to a lot of the interagency conflicts and disputes that can lead to the delays. Both at the White House and at NPS, I saw first- hand the need to coordinate agencies, establish milestones, and create transparency so that environmental review can be improved where necessary and, quite honestly, not blamed for the burdens of a complicated network of public and private requirements. That is why I supported the creation of FPISC and all the other permitting reforms when some of my other colleagues did not. Through the Title 41 and FAST Act and other recent actions, Congress has done a lot to give the Federal Government the tools to modernize the way it does business. However, those tested measures only work if the government uses them and builds trust with industry to demonstrate that this model can work in the complex government structure. Unfortunately, the Administration has pushed Congress to expand its authority rather than effectively exercising all the tools you have already given them. As a result, I have reservations and concerns about amending the Act without more proof points from the implementation of existing authorities. The Administration and others point to the permitting process as the main cause of project delays. Existing data show, however, that delays are more often the result of a lack of funding. Recognizing the need for further study and causes of project delays, the Congress gave the U.S. Department of Transportation (DOT) the permitting dashboard, which is still very much a work in progress, with incomplete data and limited mapping capabilities. It has significant potential but we are not there yet. While we were pleased to see an acting director announced, the FPISC executive director position is still vacant. A political appointee is particularly important in this role to demonstrate to departments and agencies the level of priority and commitment from the White House. The same is true for project sponsors who may question the legitimacy of FPISC without political leadership. This person would have broad authority to advance the group's mission and move large projects forward. Most importantly, though, the FAST Act allowed FPISC to establish a fee structure for project proponents. The FPISC has not yet implemented this initiative, which would help facilitate faster reviews at the expense of project sponsors, in this case private developers. These additional funds will improve the process and perhaps allow for other funds to be invested in the dashboard or other important measures. The Administration has failed to use the basic tools of governing that have been proven to improve permitting times. When the Committee, or if the Committee chooses to advance other legislation to enact more permitting reforms, I would like to offer a few recommendations. First, the FAST Act, the Water Resources Reform and Development Act (WRRDA), and the Moving Ahead for Progress in the 21st Century Act (MAP-21) all contained permitting reforms and changes to environmental review that need to be harmonized to make clear which authorities apply to which projects. Next, given the slow implementation pace, it would be prudent to keep a sunset date for provisions of FAST-41 that have not yet been implemented, such as advancing a preferred alternative or judicial review. Last, I strongly recommend against any consideration of legislated deadlines. Little can be gained by forcing under- resourced agencies to develop the projects faster. This will only lead to more court battles and additional stops and starts in permitting timelines as agencies rush reviews and communities are cut out of the process. Instead, thorough implementation of FAST-41 and other permitting reforms will net excellent data for the Committee to truly diagnose any additional problems in process and procedure. In conclusion, I thank you again for inviting me to speak to you about this top priority issue for all of us, which is addressing the needs of the Nation's crumbling infrastructure while protecting the air, water, and wildlife on which we all depend. Thank you. Senator Portman. Thank you, Ms. Goldfuss. Mr. McGarvey. TESTIMONY OF SEAN McGARVEY,\1\ PRESIDENT, NORTH AMERICA'S BUILDING TRADES UNION Mr. McGarvey. Good afternoon, Senator Portman, Senator McCaskill. Thank you both for your leadership on this issue and for convening this Roundtable to discuss permitting reform. As President of North America's Building Trades Union (NABTU) and on behalf of the three million construction workers in North America that I proudly represent, thank you for allowing me to join this distinguished panel to discuss an issue that directly impacts the building and construction trades men and women across the Nation. --------------------------------------------------------------------------- \1\ The prepared statement of Mr. McGarvey appears in the Appendix on page 51. --------------------------------------------------------------------------- Before we begin I would like to take a very brief moment to make a few comments. America's labor leaders and businesses agree: the permitting process for major U.S. infrastructure projects must continually be modernized to ensure efficiency, safety, accountability, and transparency. These projects employ hundreds of thousands of building trades members, and the sooner projects can break ground, the sooner our members can get to work applying their crafts and providing for their families. The general problem with the permitting process is this: project owners in the public and private sectors often confront an overly complex, slow, and inconsistent Federal permitting process. Gaining approval for a new bridge or factory typically involves negotiating a maze of review by multiple Federal agencies with overlapping jurisdictions and no real deadlines. Usually, no single Federal entity is responsible for managing the process. Even after a project has cleared extensive review and a permit is granted, lawsuits and judicial intervention can stymie effective approval for years, or even worse, halt a half-completed construction project in its tracks. This problem still needs more attention. Senators, your bipartisan work and leadership on the Federal Permitting Improvement Act, which we were proud to support through several sessions of Congress, demonstrated a steadfast commitment to cutting red tape in order to get much needed infrastructure projects moving forward. NABTU, and the entire building trades community, was tremendously grateful that these efforts were finally enacted and resulted in Title 41 of the FAST Act. Already, Title 41 has started to streamline the Federal permitting process, providing new hope for construction workers, project owners, and industry leaders across the country that our system can be transparent and efficient. The reforms instituted in FAST-41 were designed to take steps to rectify the problem. We believe the creation of the Federal Permitting Improvement Steering Council was a long- overdue step in the right direction. We are confident that the new procedures set forth in FAST-41 to standardize interagency coordination and consultation will ultimately lead us toward the better coordination among agencies and deadline-setting that has been lacking in the permitting process and frustrating construction owners, contractors, and workers for years. As an organization that relies upon standards, we welcome this. Furthermore, by tightening litigation timeframes surrounding some permitting decisions, major infrastructure projects may 1 day no longer be subject to the seemingly never- ending cycle of lawsuits project opponents advocate. The new process is working, not only to the benefit of the construction industry but also to the Nation at large. However, as with any program or agency, there is always room for improvement and innovation. I commend you on your continued efforts to address this critical work in improving the permitting process with your introduction of S. 3017, the Federal Permitting Reform and Jobs Act. I must also acknowledge the Trump Administration's efforts to help alleviate some of the logjams in the permitting system as a whole. We have supported the thoughtful steps they have taken to reform the system while maintaining the underlying regulations that protect the health and safety of our members on the jobsite and the environmental and human impacts of projects on communities across the country. I know there has been much confusion on the issue of permitting reform versus regulatory reform, and it is important to note that while permitting and regulations are intertwined, they are still exclusive of one another. We can reform the permitting process without sacrificing the integrity of the underlying regulations, and we have testified before the Senate on this point. I will be very clear: North America's Building Trades Union supports responsible regulations that protect the environment, public health, and worker safety. We believe these regulations are critical to responsible infrastructure development that lasts for decades and allows for future generations to use these invaluable assets. What we are opposed to is the lack of certainty and transparency in the process and the unnecessary delay and redundancy in the permitting process. These unnecessary barriers, coupled with the constant stream of endless lawsuits that project opponents rely upon because they cannot defeat a project on the merits of the project itself, leads to a loss of investment and job opportunities. When projects are tied up in the courts our members are not working, they are not putting food on the table, and they are not providing for their families. North America's Building Trades Union strongly supported the FAST-41 reforms because they lead us toward a path of standardization and finality in the permitting process. That pathway has created a floor on which future streamlining efforts can build upon. But more must be done, and we are committed to advancing practical, bipartisan solutions to further improve this process. We welcome collaboration from all interested parties who are serious about advancing this issue. Thank you. Senator Portman. Thank you, Mr. McGarvey. And now a co-sponsor of FAST-41, former Senator Mary Landrieu. TESTIMONY OF THE HONORABLE MARY L. LANDRIEU, SENIOR POLICY ADVISOR, VAN NESS FELDMAN, LLP; ACCOMPANIED BY MEGAN K. TERRELL, LEGAL ADVISOR, COASTAL ACTIVITIES, ENVIRONMENT & NATURAL RESOURCES OFFICE OF THE GOVERNOR OF LOUISIANA Senator Landrieu. Thank you, Senator Portman and Senator McCaskill. It is wonderful to be here with you again, working on some very important legislation and thoughts. I want to commend you both for your steadfast commitment to this issue and working closely together to build a bipartisan solution, which many of the colleagues, or those testifying today have mentioned, because without bipartisan support, what we are suggesting may not move forward. Both of you are so wise to understand that you could talk all day about infrastructure and the need to provide more infrastructure for our Nation, but if this process is not fixed or focused or made better, it would really be not worth speaking about, because there is such a gap between what our aspirations are and what is actually possible in processing these many projects. I am here representing Van Ness Feldman, an entity that represents many clients, but today I was asked to speak in my role representing the Louisiana Coastal Protection and Restoration Authority (CPRA). It is a $1.3 billion project, which is one of the largest on the dashboard. It has actually been mentioned in the testimony of those before me. Unlike other projects that are struggling to find the funding, Senator McCaskill and Senator Portman, we have our funding. We have the plan to restore our wetlands. It is one of the largest wetlands restoration projects underway in the Nation. The funding will come from a variety of sources. There is some Natural Resource Damage Assessment (NRDA) funding that must be approved but it is basically designated. We are not one of the projects that Christy might have mentioned, that are waiting for funding, so there is no reason to speed us up because we do not have the money. We actually have the money, and we have the scientific plan. We have a master plan for restoring Louisiana's coast that, Senator McCaskill, you and Senator Portman are somewhat familiar with because you have been very helpful. That was passed unanimously by our legislature. That, amazingly, through Republican and Democratic Governors has been supported. That is uniformly supported by our environmental community. We have our scientific plan, we have our political blessing, if you will, but we are struggling to get our permits. When we first started this project, Senator McCaskill, representing this client, the Corps of Engineers told us, in a calm voice, that it would take us 10 years--10--to get our permit. Now this is after you passed the FAST Act. And so we would respond to them, ``Have you read about the FAST Act?'' ``Oh, yes. We have read about it but we really do not, you know, have to, like, pay a lot of attention to it.'' I said, ``Well, I think you might want to pay attention to it, because it says that you have got to go fast, and 10 years is not fast.'' Then they thought they were doing us a big favor by coming back about a year later. Megan will tell you the details--and said, ``Oh, we have figured this out. We have figured out how to take it down to 6 years.'' We said, ``Six years is still too long.'' We have lost 1,800 square miles of coastline since 1932. We lose a football field of land every hour. Louisiana is in a race against time to restore our wetlands, so while I most certainly respect all of the projects that are on FAST-41-- building highways, building airports, to our trade unions--this is really important. These are not just any jobs. These are well-paying jobs that keep a lot of people employed. But our project is a coastal restoration project with its own money. Its sole purpose is restoring the environment, whole-scale restoring of the environment, building this marsh. And they are saying to us, ``You have to wait 10 years.'' ``You have to wait six.'' I was proud, in representing our client, to lead an effort, and the team is here, to work the first MOU, Senator McCaskill and Senator Portman, under your law. Using your law as the guideline, we worked the first MOU to bring clarity, transparency, a 2-year aspirational goal--and I understand you may not want to put 2 years in the law but it sure sounds good to people trying to build projects. It sounds better than 10. Now whether you put it in the law or not, but a 2-year goal for these projects, transparency, etc., is so helpful. I am going to turn in the rest of my statement for the record\1\ and turn it over to Megan. But the MOU that we established, I am turning in as a part of the record.\2\ Hopefully it can serve as a template. I generally support the goals of the enhancements to the FAST Act, and do believe, as Senator McCaskill said, that having--and both of you--a permanent director, a budget, a staff to give some strength to what you all are trying to do. --------------------------------------------------------------------------- \1\ The prepared statement of Senator Landrieu appears in the Appendix on page 56. \2\ The MOU referenced by Senator Landrieu appears in the Appendix on page 93. --------------------------------------------------------------------------- But thank you for continuing your focus on this, because the work is not done, and there are billions and billions of dollars of projects that could be built. Many have their own funding. Many have their own capital that need not 10 years or 6 years, but need more reasonable timelines. Thank you so much and I will turn it over to Megan Terrell. Senator Portman. Well, thank you, Senator Landrieu, and, Ms. Terrell, would you like to speak now or be available to answer questions, because Senator Landrieu, even though she is no longer a Senator, has learned how to use all of her time. Senator Landrieu. Oh, I am sorry. Was I supposed to save my time? I did not know. Senator Portman. No. We are going to have Megan there for questions. Senator Landrieu. OK. Do the questions. Ms. Terrell. No, that is fine. I am happy to answer any project-specific questions. Senator Portman. That is great. We are going to have some for you. Ms. Terrell. Great. Senator Portman. Ms. Thompson. TESTIMONY OF JOLENE S. THOMPSON,\1\ EXECUTIVE VICE PRESIDENT, MEMBER SERVICES AND EXTERNAL AFFAIRS, AMERICAN MUNICIPAL POWER, INC. Ms. Thompson. Thank you, Chairman Portman and Senator McCaskill. I am pleased to have the opportunity to participate in this Roundtable and discuss our experience with the FAST-41 process. --------------------------------------------------------------------------- \1\ The prepared statement of Ms. Thompson appears in the Appendix on page 59. --------------------------------------------------------------------------- AMP is a nonprofit, wholesale power supplier and services provider for 135 municipal electric systems across nine States, including Ohio, which is where we are based. We have a diverse generation portfolio that includes fossil resources and renewable resources. We have a unique experience with permitting and infrastructure processes as we recently completed the largest development of new run-of-the-river hydropower generation in the United States. We built four projects at the same time, along the Ohio River, at existing Army Corps dams. These represent more than 300 megawatts of new emissions-free, long- life generation and a $2.6 billion investment. I want to express our sincere appreciate to Senator Portman for his support of our projects as well as his leadership in pursuing balanced permitting reform. As he indicated, this process started with our telling him the tales of woe that we went through in all of our permitting processes with the four projects that we were doing. Last fall, our CEO testified before this group about the importance of reasonable and cost-effective permitting processes. He talked about the project that we still have remaining--the R.C. Byrd project, which would be a 48-megawatt facility located in Ohio at an existing Army Corps dam. The Byrd project is one of the 34 projects in the initial FAST-41 inventory. We understand the need to balance environmental protection with development. However, the distinct Federal Energy Regulatory Commission (FERC) licensing and then Army Corp and resource agency permitting processes for hydropower are especially arduous, often duplicative, and typically take more than a decade. Licensing for the Byrd project began in April 2007, obviously predating the effort on FAST-41. We received our license a decade later, in August 2017. We believe if the FAST- 41 process had existed earlier this would have moved much more quickly. Today our economic commitment to the Byrd project exceeds $4 million with permitting remaining. To tie this into the FAST-41 process, let us back up to July 2014, when FERC issued its draft environmental assessment for the Byrd project. A stalemate developed with AMP and FERC on one hand, and the Army Corps and Fish and Wildlife on the other, regarding a disagreement about the timing of the modeling study, a study which would cost up to $2 million. We were asked to complete the full study prior to receiving the FERC license. We agreed to perform the study post-license but were unwilling to do so pre-license as that would have placed the study cost at risk if the project did not move forward. We spent much of 2016 gathering additional information in an attempt to address this issue with the resource agencies. Concurrent with this stalemate, our experience with the FAST-41 process began in September 2016. We had conference calls with the Permitting Council staff to discuss the hydropower approval process and the challenges we were facing with our project. In June 2017, FERC and Fish and Wildlife finally reached concurrence on the issue at hand, and Fish and Wildlife issued their biological opinion. This broke the logjam and FERC subsequently issued the license a few months later. We attribute this movement to the visibility that the Byrd project received as a result of being included in the FAST-41 inventory. We are now at a juncture where we are experiencing a Catch-22 involving the staging of the conditions contained in the FERC license with other requirements and deadlines. One condition in the license requires us to reach an agreement with the Army Corps to coordinate plans for construction site access. Importantly, other separate license obligations are contingent upon completion of this agreement. For instance, we cannot begin certain modeling prior to completion of the agreement because we are not permitted to begin the core drilling absent the agreement. Without the core drilling, powerhouse locations cannot be determined. Without powerhouse locations, certain studies would be premature. We drafted the agreement and sent it to the Army Corps for their review in October 2017. They sent their proposed changes back this month and we are reviewing those. The fact that the FERC license conditions do not marry up to the Army Corps agreement results in a schedule that can be illogical, at best. My point in describing this post-licensing situation is to highlight the importance for hydropower projects of continuing the Permitting Council process post-licensing into the permitting phase. From our experience, FAST-41 has been successful in improving the transparency of the Federal environmental review and authorization process for covered projects. Concurrent reviews, lead agencies, firm deadlines, and a top-down approach are very important steps in improvements to the permitting process. The permitting dashboard can identify delays caused by intra- and inter-agency disputes, which can help facilitate resolutions. However, State agencies are not currently participants and they do play a critical role in the approval process for many projects. We recommend providing the appropriate resource commitments for the Steering Council and broadening the scope of the Council process to ensure that there is an ability for full resolution of disputes that can exist between State and Federal agencies, as well as between developers and agencies. Thank you for providing us with the opportunity to appear before you today and for your work on this important topic. We appreciate the R.C. Byrd project having been included in the initial inventory and we view the FAST-41 process as an important tool in balanced permitting reform and infrastructure development. Senator Portman. Thank you so much. Ms. Thompson, the testimony this afternoon has been very helpful because it gives us a lot to chew on, a lot to talk about, and I look forward to getting into questions. I am going to ask Senator McCaskill if she is interested in going first. She is the Ranking Member of the full Committee and I know she has to get to another commitment shortly, so I want to have her have the chance to ask questions and we will get into a little dialogue here. By the way, this is not a hearing in the sense that if you have something important to say, speak up. I promise not to wield the gavel too much, and let us have a dialogue. Senator McCaskill. Senator McCaskill. Let me start with FERC. The AMP hydropower project is a perfect example of how frustrating it is when FERC and the Army Corps do not talk to each other and require duplicative information. The whole point was to get agencies to work together. I understand that FERC has resisted in participating in the development of the initial timeline, saying that they are an independent agency. Can you address this, Ms. Colamaria, and is there something we can do in the new legislation that would-- other than a two-by-four--that would convince FERC that whether it is the Army Corps or FERC, they all need to play nicely within this law. Can you speak to that? Is this accurate, that FERC is pretending as if they do not have to participate? Ms. Colamaria. I would just say, both with FERC and the Nuclear Regulatory Commission (NRC), the two independent agencies we have on the Council, they are actively participating in the implementation of FAST-41 now. They participate regularly in the working group and, as you know, FERC has many of our current FAST-41 projects on the dashboard. They are the lead agency. There are statutory limitations to some of the things that they can and cannot do, ex parte communications, for example, which we are working with FERC environmental staff, licensing staff, and their General Counsel (GC) to think of creative ways to move forward so that they can still continue their coordinating roles with the agencies and use all the FAST-41 tools while still maintaining their independent agency status. Senator McCaskill. Well, I think it would be helpful for us if there is language---- Senator Portman. Yes. Senator McCaskill [continuing]. That would clear this up and that would be more directive and not discretionary. If you could share that with us I think what we need to do is make sure we draw this legislation as cleanly and tightly as possible. Because it does not do us any good, if we get everybody working except one. Ms. Colamaria. Right. Senator McCaskill. I mean, it is like you, Mary, and the Army Corps. Ms. Colamaria. Exactly. Senator McCaskill. Everybody is working well but if the Army Corps thinks that somehow they are outside of this, then the whole thing falls apart. Senator Landrieu. Senator, I would like to just jump in and add to what has been said. Our office is actually an expert on FERC. It is not work that I do personally but I am very proud that Van Ness Feldman has one of the largest FERC practices. If you do not mind, I would like to submit that question, if the record stays open, and we could provide probably several---- Senator McCaskill. That would be great. Senator Landrieu [continuing]. Ideas to the Committee, if you would accept it, and we could provide it within, what, 48 hours or a few days? Senator Portman. Yes. That would be great. We had a hearing on the Energy and Natural Resources Committee last week where we had the FERC Chairman--actually, we had all the commissioners there, which is, if not the first time it has ever happened, it is unusual--and I asked him this very question, as you probably know. I talked to him about the Council, asked him why they were not posting on the dashboard. And I asked him to get back to us on it because he was not aware of the issue. But the point is, to Senator McCaskill's question specifically, are the Nuclear Regulatory Commission and FERC actually posting on your dashboards, or not? Are they posting their information and their deadlines? Ms. Colamaria. They are posting some of their milestones, but they still do believe they have some limitations on the way that it is posted, and so that is an example of---- Senator Portman. And they said those are legal limitations, right? Ms. Colamaria. What was that? Senator Portman. They say those are legal limitations. Ms. Colamaria. Correct. Senator Portman. Even statutory limitations? OK. We should take a look at that. Senator McCaskill. We can fix that. Senator Portman. Yes. Senator McCaskill. We can write that law. We can change that legal problem. Senator Landrieu. Amen. Senator McCaskill. I know we have some disagreements about whether or not we do the sunset or do not do the sunset. I have to go to another hearing, because I am Ranking Member and it has to do with all the stress and conflict we have around the border right now, and I need to go down there to that. But I want to ask you Sean--it is so important in this era that we listen to workers and that we pay attention to the workers. I want to make sure from the perspective of your membership, if there is anything that we need to put in the legislation that would be helpful. I know getting these jobs ready to go faster, making them so that your folks can get to work in a more quick and efficient way matters, but if there is anything else I sure would like to have your input as it relates to our improvements to FAST-41. Mr. McGarvey. Well, I appreciate that, Senator. And, we are not only interested in expediting the permitting timeframe to more quickly deploy men and women that we represent onto those projects, but also we are running about 140 apprenticeship residence centers across the United States, one in Columbus, Ohio; Cleveland; one in St. Louis; Kansas City, where we are taking communities that have not had a lot of opportunity in their lifetime--communities of color, women, veterans--and using these infrastructure projects as their entryway into apprenticeship and on to the middle class, once they learn the skills sets. The more quickly we can go, the more people we can help. On top of that, over the next 10 years, we are going to move about $70 billion of our pension money out of other investments into alternatives in infrastructure and commercial real estate. So, like the Hair Club for Men, we are not just a client; we are an owner. When we are investing our dollars, it is important to us too. Senator McCaskill. I am not going to say anything about the Hair Club for Men. [Laughter.] You gave me an opening there that a Mack truck could drive through, Sean, but I am not going to say anything. Mr. McGarvey. You are correct. But there is a second opportunity for us, not only to get good help invested in the Nation's infrastructure, also to get good returns for our pension funds that need them, but to create the jobs. With all the uncertainty and unpredictability, in the years that I have been working now at the C-suite level, with people who are investing hundreds of billions of dollars in gas and oil, petrochem, public and private other types of infrastructure, this predictability is the whole thing when it comes to the financing. The banks on Wall Street and others that are putting up a lot of this money, they cannot be in a position where they do not know when they are going to start to get the return on investment (ROI) on the investment, and as pension fund investors we are the same way. Again, if we could ever get to that magic 2-year where we knew, from start to finish, in 2 years we were going to know whether we were going or not, that would change the whole ballgame, I think. And not sun setting the bills. The other thing. Senator McCaskill. Let us go to that, because this is in the predictability place, and this will be my last question. You raised concerns about removing the sunset, Ms. Goldfuss. I just think that this predictability, if people think it might go away, then all of a sudden all of the speed that they had gained they think could dissolve, and not that our government is not totally predictable and stable and functioning smoothly. I am not being partisan there. We have the same problem. I mean, this is a door that swings both ways. Do you see that removing the sunset has some advantages as it relates to predictability? Ms. Goldfuss. Yes, and just to clarify, I think for the portions of the law that we know are working--so the dashboard and the Council and the pieces that we see are demonstrating success--putting the sunset in place makes perfect sense. But we have not had the law long enough for specifically the judicial review pieces. The only recommendation I would make there is look at--is there a point in time that Congress could come back to some of the untested provisions of the law and see whether or not they are working. The sunset gives you that opening to maybe extend it several years and come back and look at the judicial review, or some other version of that, where you would check in. Senator McCaskill. So your objection to removing the sunset is about the untested parts dealing with the judicial review that we really have not---- Ms. Goldfuss. Right. We have not determined whether or not they work. Correct. Senator McCaskill. That makes sense. Thank you all very much. Thank you. Senator Portman. Thanks, Senator McCaskill. We are joined by Senator Harris, and feel free to jump in at any time you would like. Senator McCaskill went first because she has to head down to another committee hearing. But again, there is so much to talk about here, and I thought, Mr. McGarvey, you pretty well summarized where we are in terms of the problem. The problem is we all want more infrastructure and we need it badly, and relative to other developed countries, we have a real gap in our infrastructure, across the board. Certainly that includes energy projects, as we heard about and environmental restoration projects, but also roads and bridges, ports, and things that directly affect the economic development of our country. So this helps a little bit. We have seen the billion dollars in savings already. It is awesome. The question is, what can we do to make it work better? I wanted to ask a couple of questions. First, to Ms. Colamaria, I know that you are in sort of an awkward position because we are talking about your Council and how it could work better, and you would be the last one to ask for more money for yourself, I am sure. Maybe not. But looking at what you have been able to do with $4 million over this period of time, saving about $1 billion, what could you do with $10 million? What could you do with $15 million? What would you do if you could get a higher appropriation? Ms. Colamaria. Before I answer that I just want to clarify something that Senator McCaskill said. Our budget through appropriations this year was $1 million, but that was significantly lower than what was requested by the President's Fiscal Year budget. We did request $10 million and we were given $1 million. This year we requested $6.07 million and that is currently in both the House and Senate appropriations bills. As you alluded to, we are kind of skating by on a skeleton budget right now, but we have been able to accomplish some significant successes. But I do think that to fully realize the potential of FAST-41, to create that sea change across all agencies, we really are going to need the full budget in order to really spend the time on each project that we do, shepherding each project through the process, having the one- stop-shop service for project sponsors, and then also just creating all the tools that the agencies will need in order to make their internal process and their intra-agency processes more efficient as well, including the GIS tools, making the dashboard more of a tool as opposed to a reporting function, that type of thing. Senator Portman. Let me just be specific. You talked about $6 million, roughly, in the budgets this year. Neither of those bills have been voted on yet but we are hoping that those bills and others will come to the floor. Would that be adequate for what you are currently experiencing--the number of projects on the dashboard, the amount of staff you need, the amount of tools you need, money you need to have the tools to help these agencies and departments? Mr. Herrgott, jump in here too, because I know you are very involved with this. Mr. Herrgott. She is doing a great job. Ms. Colamaria. I think given the current project workload, that is an adequate amount, given the fact that we are also planning on issuing fee regulations to further enhance our budget and to help both in terms of the operating costs for the Office of the Executive Director, as well as the cost to the agencies, for implementing FAST-41. Mr. Herrgott. I would just like to point out it is important to focus on making sure that the Permitting Council is adequately funded, but as you know from your experience in performance management at OMB, the problem that we are dealing with is fierce. We have a legacy, paper-based system that was developed before the Internet, in a way in which we have 59 statutes and up to 14 agencies that oftentimes do not have a central repository for data. It is not just enough to create a dashboard and then to appoint a permanent executive director to make the systemic cultural changes within agencies. Just the way they talk to each other--and this is not a Republican or Democrat issue. This really is a process redesign. And to comments about One Federal Decision or the Permitting Council somehow eroding environmental protections or pushing too far--that would be an inaccurate assessment, because what we are really doing is taking a hard look at how agencies get to a decision. Not to a yes but to a decision, using the best available data. Although folks have talked about resources within the agencies, the important thing here is we do not have a central repository for data on where the resource constraints are. Part of the accountability system that is tied to FAST-41, and to One Federal Decision, is for the first time ever to ask agencies where the resources actually are, where they are being used, so we can pinpoint and target where the resources are. Throwing money at the agencies is not the problem. What we need to figure out is where they actually are. So that is why, on April 9th of this year, we had 11 Federal agencies and the Permitting Council sign the MOU, including FERC, which binds them to do things that are consistent with the spirit of FAST-41. I would argue that they both work hand-in-hand. You need FAST-41 as a project-by- project tool to adjudicate project disputes and to change the way we do business. But you also need One Federal Decision across all Federal agencies, the entire Federal family, to do things a little bit differently, and you need them to work together or else we cannot achieve the coordinated project plan and the timelines that are in FAST-41. Yes, it is important that we address the adequate funding, but we also need the MOU, which is being implemented now, to take root, so that it can further support the FAST-41 successes. Senator Landrieu. Senator Portman, could Megan just say 30 second on this, because it is so important. Senator Portman. Absolutely. I was going to get down to your project next. I am really impressed that so many people know how to pronounce Mid-Barataria too. Everybody on the panel has said that word one time today, except you. Senator Landrieu. They know this project. They have heard a lot about this project. Senator Portman. Probably America's biggest environmental restoration project right now. Right? Senator Landrieu. Yes, it is. Go ahead, Megan. Senator Portman. What is your sense? How is it working? Ms. Terrell. I think the process right now has worked really well. The MOU that we entered into with the United States and the Federal cooperating agencies and the Corps as the lead agency I think was really the trigger to really speed things up for our project. It is one of the Coastal Protection and Restoration Authority's five cornerstone projects in the State of Louisiana, and right now is going through the permitting process. As Senator Landrieu mentioned, it started off as a 10-year process, and then after the project got put on the dashboard in January 2017, the new Coordinator Project Plan was issued with about a 6-year project timeline. Shortly thereafter, there were several months of negotiations, but in early January of this year we entered into that milestone MOU, and that has really been the impetus to see the changes. We being the State of Louisiana, I think one of the key pieces that helped us, as part of the MOU, was allowing the State, as a project sponsor, to have more participation in the process. Where that led to was the State working directly with the Corps but also the other Federal cooperating agencies. We had a whole framework development team, multiple calls, where we sat down and really talked about this is the timeframe within which the modeling is going to take place, this is the timeframe that we can accomplish and working through each stage of the EIS process. Through that, that is where we were really able to create the efficiencies. It was through increased coordination and increased communication between the State, the Federal cooperating agencies, and the lead agency. The agencies also dedicated necessary staff and resources to the project that may not have been there before. One of the other extremely helpful things was to have executive staff in the room. We have Colonel Clancy, who is the commander and District Engineer of the New Orleans District and who was directly involved in the process, checking in and that ensures that his staff and his personnel are focused on the project, but also ensures that it remains a priority. That has been extremely helpful. Senator Portman. Do you feel like the Corps feels accountability for the performance of the other agencies? Ms. Terrell. They do. Senator Portman. That is the idea, to have one agency in charge. Ms. Terrell. The lead agency in charge definitely helps. We have monthly meetings and the Corps is constantly keeping not only CPRA as the project sponsor but also the other cooperating agencies on task, and asking where we are in the timeline, and are we going to meet our milestone goals. I think that has been extremely helpful. I think having that goal of a 2-year permitting timeline has also been extremely helpful. I am acting as sort of a project manager for the environmental and permitting for this project, but I started off my career as an attorney, still am. But we all know, as an attorney, if you have a brief deadline, for example, you are going to make sure you do the prep work and make sure you get that filed on time. That is why I really think having a 2-year timeframe and a goal in mind helps keep people focus on the job at hand. It helps with early identification of issues that may result in delay down the road, and then you can enter into these dispute resolution processes, which we have, as part of our MOU, and that has been extremely helpful. Senator Landrieu. But that MOU would not have been possible without Alex and without the Federal push coming down to tell them, ``You must work together,'' and maybe we need stronger. But your team up here, Senator Portman, was terrific, because they would not be listening if it was not be coming from the top. Senator Portman. By the way, the 2-year goal is that it is a goal. As I said earlier, if agencies cannot meet that goal for some reason, they have to explain why, and how they are going to try to meet it. That is what we are doing here. To the point earlier from Ms. Goldfuss, which I get, sometimes there are going to be situations that are out of the control of the agency. Something happens. But having that goal, as Mr. McGarvey said, is so critical. I want to give Senator Harris a chance to jump in here, if she is interested, and I appreciate you coming. OPENING STATEMENT OF SENATOR HARRIS Senator Harris. I appreciate you. Thank you. Ms. Colamaria, you are probably familiar with what happened back in October in California. PG&E, electric transmission lines, there was failure and it resulted in the death of 18 people and 12 wildfires. At least Cal Fire estimates that the causal connection included the 12 wildfires that we experienced, that devastated communities. Tell me how FAST-41 is addressing, in particular, the safety concerns that we have around electrical transmission wiring. Certainly the efficiency and speed is important, but also safety. Can you talk to me a little bit about that? Ms. Colamaria. Well, I can get back to you on any specifics, if there are any of our projects that are specifically dealing with that issue. I do not know off the top of my head if there are. FAST-41, the purpose of it is to improve the Federal permitting process for environmental reviews and authorizations. Those are typically more environmentally related authorizations, but there are some that also bring in safety concerns as well. The purpose is to ensure all the agencies that have some role in that project are coordinating and are talking and are identifying potential issues, possibly a safety issue that would come up later on in the process, identifying it earlier on so you can address it throughout the process, and making sure that all of those potential dangers are identified so they can be addressed as the project approval, or not approval, goes forward. Senator Harris. OK. If you could follow up with me that would be great. Thank you. Senator Portman. How many projects are on the dashboard right now? Ms. Colamaria. There are 38 projects right now on the dashboard. Sixteen have completed their Federal environmental reviews and authorizations. Seventeen are in progress. One is planned. Additionally, two projects are paused at this time, due to project sponsor financial concerns, and two projects were canceled by the project sponsor, due to economic considerations, and then the need to determine the need for the project. Senator Portman. How many have applied to be covered? Ms. Colamaria. We have had six new projects to apply to become covered projects under FAST-41. Five of them were determined to be covered projects. One was rejected because it was not one of the covered sectors under FAST-41. Senator Portman. OK. Have you looked at our new legislation on the additional coverages on some specific areas? Ms. Colamaria. I am aware of the legislation. As you know, because the Administration has not taken a position on the bill, I cannot comment on any specific legislation. But I will say a lot of the issues addressed in the bill are issues we have seen come up during implementation. Senator Portman. We will just take Mr. McGarvey's word for it. He thinks it is good, to cover more, right, more covered projects. There are just some silly, I think, carve-outs that do not make sense, in terms of what is covered and what is not covered. There is not a big expansion because most things were covered. On the issue of you and your people being able to help give advice or consultation to non-covered projects, have you looked at that part of the legislation? I am not trying to put you on the spot here. That is a part of the bill that came out of some of the concerns that we heard from your folks. Ms. Colamaria. I am aware that it is in the bill. I will say, though, in the 13807 Executive Order we do cover that issue and it does allow, under the Executive Order, the executive director to help out on projects that are not FAST-41 covered projects. Senator Portman. OK. Good. Ms. Colamaria. We are supportive of that, obviously. Senator Portman. Yes. Good. Senator Landrieu. Can I jump in to add to that? Senator Portman. Yes, please. Senator Landrieu. On behalf of our client, we would support a broadening of the coverage, but as long as it does not dilute the focus on the large projects that are on the dashboard. So, of course, we would love to try to expedite as many projects across the country, Senator, as we can, but there are really significant projects that are on this dashboard. We have $1 million and no executive director, as we sit here today. So there are some really important steps that a permanent executive director, a good, solid budget, and continued coordination and transparency would be extremely helpful. Senator Portman. Yes. Ms. Colamaria. Can I respond to that, just quickly? Senator Portman. Of course. Ms. Colamaria. I think that you might have noticed that I qualified my $6.07 million number as sufficient for the current set of projects, but, yes, if we do expand, and we are starting to increase our marketing and letting more project sponsors know about the benefits of FAST-41. As we do start to significantly expand the number of covered projects we would need more money, exactly for that reason. We do not want to dilute the services we are providing. Senator Portman. We wanted to start off with some projects like Mid-Barataria that would be successful, and thanks to your hard work, all of you, it is moving along. I would still like to shorten the time, as Mr. Terrell said. But, as we have successes and build on that foundation, obviously the idea is to give you the opportunity to take on more, and I was interested to see how many projects have applied. I would like to see more, but we need the resources to make it work. And to both of you, Mr. Herrgott and to you, Ms. Colamaria, I think the executive director of permanence would be really helpful for everybody. I am not going to put you on the spot to ask you why we do not have one yet, but I have asked others, including some of the senior officials in the Administration, and they all indicate that they are moving toward that. So I would hope that that is true. Mr. Johnson, you have not had a chance to speak up much since your good testimony, but what do you think the top priorities are going forward, and what should we be doing? I know you said you strongly support the new legislation. What should our emphasis be in that and what is the most important thing going forward? Mr. Johnson. Absolutely. We have already talked about a lot of the most important things. I think one thing to keep in mind is the entire permitting process, with all the interagency coordination that is required, is a complicated problem to solve. We are only roughly 2\1/2\ years into implementation of the Steering Council and getting FAST-41 underway. They have made remarkable progress in that time. But we are just beginning to see the payoff from that, in terms of measurables, metrics that we can actually use to look at the success of the project. I think one of the things that would help, moving forward, is to increase the number and diversity of projects, to make sure that we get a better data set, more information in terms of how useful this is, and make sure that we have a lot of coverage in how we can explain what this does to the process, and to show what this does to the process. Furthermore, I think it is absolutely critical that we remove the sunset provision to ensure that we can do that in a timely way and we can do that in a way that continues forward. Seven years is just too short to make sure that we get this fully implemented, that we have success stories, and that we could show that this process really works. And then, like I said, to build on top of it, to continue the process forward. I think Alex was talking about the complexity of the system and the problems that we have with paperwork and inconsistencies across agencies. These are problems that can be solved without any kind of substantive change in the statutes that require environmental review, or that require environmental review for permitting. We can actually not change the way we do anything but still improve and speed up the process, make it more transparent and better, simply by fixing the bureaucratic overhang that happens because of all of the inefficiencies in the system. The more we can do that and the more projects we can do that on, I think the better we will be in the long run and the better the position of the country will be, in terms of all of the things we have talked about--creating jobs, growing the economy, having more projects, and attracting more investment to these projects. Mr. Herrgott. One point on the judicial review section. It is worth pointing out that in MAP-21 and the FAST Act that those judicial reform remedies, that reduction in time, is already applicable to Section 139 of Title 23 and DOT projects. It is already internally consistent with other parts of the code. Data does exist that it does deliver projects faster, in a way in which projects otherwise would not go from red to green without those judicial reform sections. It would be an inaccurate assessment to say that the judicial reform sections in your bill are any different than other treatment that we have seen in something, that have been bipartisan bills that have passed through Congress. Senator Portman. That is a good point. By the way, more data and the ability to use the data, so it is not just having big data but to be able to put the analytics behind it so it makes sense, will help put the performance measures. Ms. Goldfuss, I think it also helps with some of your concerns, frankly, because the inefficiencies of the process do not lead to a better result. Ms. Goldfuss. I completely agree, and I think the tension of adding more projects versus having a bunch of proof points to show that this works is some of what Senator Landrieu pointed out. This is a new-ish process for government. Unfortunately, we would all like the timeline to go faster. The success that you have was with a shift in Administration, which we know also takes time as new people come in and learn what is happening. So I think---- Senator Portman. By the way, can I interject there for just a moment? Thank you for your work at the end of the Obama Administration getting the Council going. I did not mean to be---- Ms. Goldfuss. No. Senator Portman [continuing]. Ungrateful there, because I know there was lots of back-and-forth. The director and I were, as you know, in constant communication for a while there. Ms. Goldfuss. Constant. Senator Portman. You did get it set up and going, and our job is to push, push, push. Ms. Goldfuss. And show that it works. Barataria is a wonderful project but we need more of that. We need to show that this is what we learned, and have that data to see what is really holding it up. Senator Portman. I did not mean to interrupt you. Keep going, if you can remember your line of---- Ms. Goldfuss. I just wanted to agree with Alex on that point about the data. We may not agree on everything but having data from the system, really the inefficiencies in the bureaucracy are overwhelming. PDFs, for example, in some places, people just refusing to return phone calls or emails. FPISC really has put a big, bright light on the fact that people have to work together, and forcing that and showing that it can work on projects and still have strong environmental outcomes will mean that it will benefit more projects in the long run. Senator Portman. Excellent. Anything else to add from the group? Ms. Thompson, you said you had a 10-year, as I heard you talking about the numbers, a 10-year permit in process, still, on your last hydropower plant. Is that right? Ms. Thompson. For the license for the project currently in the inventory it took 10 years to get the license. The license is the permission to start permitting, which will be another probably 4 to 5 years, at least. A part of that being the amount of studies that you have to do for a hydro project because you are affecting a Corps dam. So there has to be a number of structural studies and those sorts of things. I wanted to echo what I heard--I have heard the words ``cultural change'' come up a couple of times and I just want to talk about how important that is. You are really trying to move some very entrenched bureaucracies, and ways of doing things that are not things that necessarily need to be changed in the statute. But this process can help encourage collaboration and shine a light on it. There are some things that just do not make sense in some of these processes and I think if that becomes apparent to the Permitting Council and there are other folks that are arbiters of the situation, that it could make some serious progress forward on certain things. Particularly you have some differences between the FERC and Corps, when we are dealing with our projects. Some things the Corps does are completely duplicitous of what we have already done in the FERC process. For instance, studies that after 5 years they will no longer accept a study. Once you have done the study and the licensing process, it is going to be expired, but it has already been done, but you redo the study, it is more cost for the developer. It is just more time and more delays. So cultural change, having the arbiter of someone looking at this and saying it does not make sense, is critically important. Senator Portman. That is why I think it is so important that the Council be permitted to consult on non-covered projects, because I think the effect of the Council is actually far more than $1 billion. I think it actually has changed the culture in some agencies and departments that do not have covered projects. I think that could happen even more if you all had the flexibility, and it sounds like you do under Executive Order already. But under statute to be encouraged to consult so that the cultural changes take place, not just with regard to a couple dozen covered projects but with regard to the agencies and departments, in general. That is kind of your job, to be the person who is trying to change a mindset and focus on results, jobs, and economic development. I think that is a really important point, and I am glad to hear you think there is some cultural shift going on in some of these agencies you are working with already, but it sounds like you could see a little more of it. Ms. Thompson. Yes, it could be a lot. There could be a lot more. Senator Portman. Yes. Senator Landrieu. There is a lot of room to avoid duplication. Senator, one other idea I will throw out, and I can follow up with the staff on this. But it occurred to me, sitting here, with the jurisdiction of Homeland Security, that the Committee is responsible for rebuilding cities, counties, and portions of States that are destroyed by disasters. Of course, I led a lot of that effort when I was here. It occurs to me that a special grouping of projects would be infrastructure projects that must be rebuilt quickly after a storm. I am not sure there is any special HOV lane for that. We should think about that. Because, remember, these projects, for instance the bridge over Lake Pontchartrain, that I-10 collapsed, it had already been permitted once. It was a fine bridge. It just was overwhelmed by the force. Why would you have to wait to go through X number of years to rebuild it? Projects like that could go on a fast track if it could quickly be determined that that bridge was, in fact, safe. It needs to be built to a higher standard, but if it is being built in the same footprint as the old bridge, why do you have to do a whole NEPA, because it is on the same footprint? Now if you are moving the bridge a mile away, over land that was never examined, then maybe so. But I have always argued, if you are building back on relatively the same footprint, why do you even need NEPA? You need a safety check. You need safety to make sure that the bridge you are building is stronger. We should think about that, a special category. It would be so helpful to mayors and Governors that are struggling right now in Houston to rebuild, and with all the problems, they do not need that. We should think about that. I do not know if you all have talked about that. Mr. Herrgott. We have talked about that extensively, and at its core what we were trying to do is realign everyone's definition of success, and it is building the project. And unfortunately, the very talented people that work within the agencies, we have failed them. We have not set them up for success because we have not given them a process to address what is behind me. [Points to chart.] That is systemic. We can work within existing statutes, and along with the Permitting Council, which is institutionalizing best practices which helped us to the logical outgrowth, which is One Federal Decision, to change the way in which agencies talk to each other, at the front of the process. To bring stakeholders in, not just for the opt-in projects of the Permitting Council, which is extremely important and it has changed the way in which we do business. For example, one example, we have the Department of Commerce National Marine Fisheries Service who will do an analysis on the Twin Span Bridge on salmon, because they are an ocean-faring fish. But yet the Fish and Wildlife Service is doing analysis on trout because they are river fish and under the jurisdiction of the Department of Interior. When we talk about resources, it is essential that we collaborate and coordinate to ensure that we harmonize those processes, because I do not know how to explain to a taxpayer in Nebraska that we wasted an additional $600,000 on two different biological opinions for something that easily could be done simultaneously and concurrently. That is what is essential, and that is the lessons learned from the Permitting Council, which we have taken to extend onto the rest of the Federal family. And I think the collaborative nature and the one-two punch are essentially what is going to help us really demonstrate what your vision was. Senator Portman. As you probably know, the Administration is proposing a reorganization of government right now, which every Administration does, and usually it does not fare very well up here because of the jurisdictional problems with our committees. One of the reorganization policies maybe comes from you guys, which is about fish, and it is about trying to have one agency be responsible for both the salmon and the trout, to use your example. That would reduce some of the duplication and some of the confusion that people have. I think it is important. By the way, you did help, when you were here, I think, on highway projects with regard to rebuilds, not having to go through such a laborious process. Correct? But it is a good point. It needs to be broadened beyond just that. I do not think it includes bridges, as an example. Highway projects and bridges. You may have done more than you thought while you were here. Senator Landrieu. Thank goodness I did something. Senator Portman. Yes, you did a lot. Senator Landrieu. At least I did one thing when I was here. Senator Portman. This has been very helpful, and needless to say we want to continue to hear from you. Some of you are going to send some things for the record of this particular meeting, and we will be sure and get those. But, in general, please keep working with us. We have, I would say, a nonpartisan approach to this, and in some regard we talked about it. It took us several years to just get this thing into legislation. Now, it has taken us a few years to get it up and going. I think there is an opportunity, with this additional legislation, which I view as common sense, really very modest changes. And I understand, Ms. Goldfuss, your concern about part of it with regard to the sunset not applying to every part of the new bill. But it is really important that we take the lessons we have learned and use it to make this even more streamlined, to use one of your favorite words. So continue to work with us please, our team. We want to move this forward with regard to new legislation, and we want to be sure you get your appropriations this year. We are going to weigh in on that on a bipartisan basis, and talk about the savings, and talk about the incredible return on investment this is for the taxpayer. Finally, there are 15 days that the record will be open, so this gives you not 2 years, but 15 days. To Ms. Terrell's point that lawyers have to get their briefs in, your briefs need to be in within 15 days, for the record. We really want to hear from you and continue to work with you. Thank you for being here today. Thanks for your service. Mr. McGarvey. I cannot share with Senator McCaskill, but I had a full head of hair when this process started. [Laughter.] [Whereupon, at 4 p.m., the Committee was adjourned.] A P P E N D I X ---------- [GRAPHIC(S) NOT AVAILABLE IN TIFF FORMAT]