[House Hearing, 119 Congress] [From the U.S. Government Publishing Office] WATER RESOURCES DEVELOPMENT ACTS IMPLE- MENTATION: REVIEW AND OVERSIGHT OF PAST PROVISIONS ======================================================================= (119-29) HEARING BEFORE THE SUBCOMMITTEE ON WATER RESOURCES AND ENVIRONMENT OF THE COMMITTEE ON TRANSPORTATION AND INFRASTRUCTURE HOUSE OF REPRESENTATIVES ONE HUNDRED NINETEENTH CONGRESS FIRST SESSION __________ SEPTEMBER 10, 2025 __________ Printed for the use of the Committee on Transportation and Infrastructure [GRAPHIC NOT AVAILABLE IN TIFF FORMAT] Available online at: https://www.govinfo.gov/committee/house- transportation?path=/browsecommittee/chamber/house/committee/ transportation __________ U.S. GOVERNMENT PUBLISHING OFFICE 64-440 PDF WASHINGTON : 2026 ======================================================================= COMMITTEE ON TRANSPORTATION AND INFRASTRUCTURE Sam Graves, Missouri, Chairman Rick Larsen, Washington, Ranking Member Eleanor Holmes Norton, Eric A. ``Rick'' Crawford, District of Columbia Arkansas, Jerrold Nadler, New York Vice Chairman John Garamendi, California Daniel Webster, Florida Henry C. ``Hank'' Johnson, Jr., Georgiaomas Massie, Kentucky Andre Carson, Indiana Scott Perry, Pennsylvania Dina Titus, Nevada Brian Babin, Texas Jared Huffman, California David Rouzer, North Carolina Julia Brownley, California Mike Bost, Illinois Frederica S. Wilson, Florida Doug LaMalfa, California Mark DeSaulnier, California Bruce Westerman, Arkansas Salud O. Carbajal, California Brian J. Mast, Florida Greg Stanton, Arizona Pete Stauber, Minnesota Sharice Davids, Kansas Tim Burchett, Tennessee Jesus G. ``Chuy'' Garcia, Illinois Dusty Johnson, South Dakota Chris Pappas, New Hampshire Jefferson Van Drew, New Jersey Seth Moulton, Massachusetts Troy E. Nehls, Texas Marilyn Strickland, Washington Tracey Mann, Kansas Patrick Ryan, New York Burgess Owens, Utah Val T. Hoyle, Oregon Eric Burlison, Missouri Emilia Strong Sykes, Ohio, Mike Collins, Georgia Vice Ranking Member Mike Ezell, Mississippi Hillary J. Scholten, Michigan Kevin Kiley, California Valerie P. Foushee, North Carolina Vince Fong, California Christopher R. Deluzio, Pennsylvania Tony Wied, Wisconsin Robert Garcia, California Tom Barrett, Michigan Nellie Pou, New Jersey Nicholas J. Begich III, Alaska Kristen McDonald Rivet, Michigan Robert P. Bresnahan, Jr., Laura Friedman, California Pennsylvania Laura Gillen, New York Jeff Hurd, Colorado Shomari Figures, Alabama Jefferson Shreve, Indiana Vacancy Addison P. McDowell, North Carolina David J. Taylor, Ohio Brad Knott, North Carolina Kimberlyn King-Hinds, Northern Mariana Islands Mike Kennedy, Utah Robert F. Onder, Jr., Missouri Jimmy Patronis, Florida Subcommittee on Water Resources and Environment Mike Collins, Georgia, Chairman Frederica S. Wilson, Florida, Ranking Member John Garamendi, California Eric A. ``Rick'' Crawford, Jared Huffman, California Arkansas Patrick Ryan, New York Thomas Massie, Kentucky Val T. Hoyle, Oregon Brian Babin, Texas Emilia Strong Sykes, Ohio Mike Bost, Illinois Laura Friedman, California Doug LaMalfa, California Shomari Figures, Alabama Bruce Westerman, Arkansas Julia Brownley, California Brian J. Mast, Florida Mark DeSaulnier, California Tracey Mann, Kansas Chris Pappas, New Hampshire Eric Burlison, Missouri Hillary J. Scholten, Michigan, Kevin Kiley, California Vice Ranking Member Vince Fong, California Nellie Pou, New Jersey Tony Wied, Wisconsin Laura Gillen, New York Jeff Hurd, Colorado Eleanor Holmes Norton, David J. Taylor, Ohio, Vice District of Columbia Chairman Rick Larsen, Washington (Ex Officio) Brad Knott, North Carolina Robert F. Onder, Jr., Missouri Jimmy Patronis, Florida Sam Graves, Missouri (Ex Officio) CONTENTS Page Summary of Subject Matter........................................ vii STATEMENTS OF MEMBERS OF THE COMMITTEE Hon. Mike Collins, a Representative in Congress from the State of Georgia, and Chairman, Subcommittee on Water Resources and Environment, opening statement................................. 1 Prepared statement........................................... 3 Hon. Frederica S. Wilson, a Representative in Congress from the State of Florida, and Ranking Member, Subcommittee on Water Resources and Environment, opening statement................... 4 Prepared statement........................................... 5 Hon. Rick Larsen, a Representative in Congress from the State of Washington, and Ranking Member, Committee on Transportation and Infrastructure, opening statement.............................. 6 Prepared statement........................................... 7 WITNESSES Hon. Adam R. Telle, Assistant Secretary of the Army for Civil Works, Department of the Army, oral statement.................. 9 Prepared statement........................................... 11 Lieutenant General William H. ``Butch'' Graham, Jr., Chief of Engineers and Commanding General, U.S. Army Corps of Engineers, oral statement................................................. 12 Prepared statement........................................... 13 APPENDIX Questions to Hon. Adam R. Telle, Assistant Secretary of the Army for Civil Works, Department of the Army, from: Hon. Mike Collins............................................ 59 Hon. Brian Babin............................................. 60 Hon. Rick Larsen............................................. 60 Hon. Frederica S. Wilson..................................... 66 Hon. Hillary J. Scholten..................................... 66 Questions to Lieutenant General William H. ``Butch'' Graham, Jr., Chief of Engineers and Commanding General, U.S. Army Corps of Engineers, from: Hon. Eric A. ``Rick'' Crawford............................... 67 Hon. David Rouzer............................................ 68 Hon. Rick Larsen............................................. 69 Hon. Frederica S. Wilson..................................... 70 Hon. Eleanor Holmes Norton................................... 71 Questions to Both Witnesses--Hon. Adam R. Telle, Assistant Secretary of the Army for Civil Works, Department of the Army, and Lieutenant General William H. ``Butch'' Graham, Jr., Chief of Engineers and Commanding General, U.S. Army Corps of Engineers--from: Hon. Mike Collins............................................ 72 Hon. Eric A. ``Rick'' Crawford............................... 77 Hon. Bruce Westerman......................................... 79 Hon. Frederica S. Wilson..................................... 80 Hon. John Garamendi.......................................... 81 Hon. Greg Stanton............................................ 82 [GRAPHIC(S) NOT AVAILABLE IN TIFF FORMAT] September 5, 2025 SUMMARY OF SUBJECT MATTER TO: LMembers, Subcommittee on Water Resources and Environment FROM: LStaff, Subcommittee on Water Resources and Environment RE: LSubcommittee Hearing on ``Water Resources Development Acts Implementation: Review and Oversight of Past Provisions'' _______________________________________________________________________ I. PURPOSE The Subcommittee on Water Resources and Environment of the Committee on Transportation and Infrastructure will meet on Wednesday, September 10, 2025, at 10:00 a.m. ET in 2167 of the Rayburn House Office Building to receive testimony at a hearing entitled, ``Water Resources Development Acts Implementation: Review and Oversight of Past Provisions.'' The hearing will provide Members with an opportunity to review implementation of United States Army Corps of Engineers (Corps) projects and policies that were included in previous Water Resources Development Acts (WRDAs), including WRDA 2024. At the hearing, Members will receive testimony from the Honorable Adam R. Telle, Assistant Secretary of the Army (Civil Works) and Lieutenant General William H. ``Butch'' Graham, Chief of Engineers and Commanding General, United States Army Corps of Engineers. II. BACKGROUND THE UNITED STATES ARMY CORPS OF ENGINEERS_CIVIL WORKS The Corps is the Federal Government's lead water resource development and management agency, whose mission is to ``deliver vital engineering solutions, in collaboration with [their] partners, to secure our Nation, energize our economy, and reduce disaster risk.'' \1\ Its water resource program dates back to 1824 when it was established for the purpose of improving river navigation.\2\ The role of the Corps has evolved and expanded since then to include other main water resource responsibilities. --------------------------------------------------------------------------- \1\ Corps, United States Army Corps of Engineers Headquarters Website, (last accessed July 1, 2025), available at https:// www.usace.army.mil/. \2\ Corps, About Corps Water Resources Planning, (last accessed July 1, 2025), available at https://planning.erdc.dren.mil/toolbox/ guidance.cfm?Id=0&Option=Planning%20Fundamentals &Type=About&List=Visitor. --------------------------------------------------------------------------- Today, the Corps' primary civil works responsibilities are to support navigation, flood risk management, and aquatic ecosystem restoration.\3\ Specifically, the Corps manages over 14,000 miles of levees, 740 dams, 12,000 miles of inland and intracoastal waterways, and 218 lock chambers.\4\ --------------------------------------------------------------------------- \3\ Anna Normand & Nicole Carter, Cong. Rsch. Serv. (IF113322), Water Resources Development Acts: Primer and Action in the 118th Congress, (Updated Jan. 14, 2025), available at https://www.crs.gov/ Reports/IF11322 [hereinafter IF113322]. \4\ Corps, Value to the Nation, (last accessed June 30, 2025), available at https://www.iwr.usace.army.mil/Missions/Value-to-the- Nation/ [hereinafter Value to the Nation]. --------------------------------------------------------------------------- The Corps also provides outdoor recreation opportunities, offers water supply and conservation to state and local partners, assists in emergency response, and is a leading producer of hydropower in the United States. Many Corps projects are multipurpose, incorporating navigation, flood risk management, and/or ecosystem restoration in conjunction with water supply and conservation, recreation, and/or hydropower into their design, construction, and operation.\5\ The Corps, at its sites, sees 269 million recreational visitors a year, provides 25 percent of the country's hydropower output, and manages 135 reservoirs with municipal and industrial water supply.\6\ The Corps also provides support in responding to natural disasters by supporting the Federal Emergency Management Agency (FEMA) when requested or through the Flood Control and Coastal Emergencies program (often referred to as ``P.L. 84-99'').\7\ --------------------------------------------------------------------------- \5\ IF113322, supra note 3. \6\ Value to the Nation, supra note 4. \7\ See Id. --------------------------------------------------------------------------- The Corps also administers certain water-related regulatory authorities, such as Sections 9 and 10 of the Rivers and Harbors Act of 1899, Section 404 of the Clean Water Act, and Section 103 of the Marine Protection, Research, and Sanctuaries Act.\8\ --------------------------------------------------------------------------- \8\ Corps, Federal Regulation, (last accessed July 1, 2025), available at https://www.usace.army.mil/Missions/Civil-Works/ Regulatory-Program-and-Permits/Federal-Regulation/. --------------------------------------------------------------------------- IDENTIFYING WATER RESOURCES NEEDS To achieve its civil works mission, the Corps plans, designs, and constructs water resources development projects, typically in partnership with, and utilizing the cost-shared, financial support of, non-Federal interests. The Corps' planning process requires that Federal water resources investments reflect national priorities, encourage economic development, and protect the environment, and that the Corps seek to maximize net public benefits to society.\9\ --------------------------------------------------------------------------- \9\ 42 U.S.C. 1962-3; Title 33 CFR 234.4. --------------------------------------------------------------------------- Generally, the first step in developing a project through the Corps is to study the feasibility of the proposed project, which typically requires Congressional authorization. Once authorized, the Corps enters into a cost-sharing agreement with a non-Federal interest to initiate the feasibility study process. The cost of a feasibility study is usually split evenly between the Federal Government, which is subject to appropriations, and the non-Federal interest.\10\ --------------------------------------------------------------------------- \10\ IF113322, supra note 3. --------------------------------------------------------------------------- Congress has directed that, to the maximum extent practicable, feasibility studies should involve three levels of Corps review (District, Division, Headquarters), be produced within four years, and at a maximum cost of $5 million.\11\ For project studies determined to be especially complex based on size, scope, or significance, Congress has allowed for a waiver process from these requirements.\12\ --------------------------------------------------------------------------- \11\ 33 U.S.C. 2282c. \12\ Id. --------------------------------------------------------------------------- During the feasibility study phase, the Corps' district office prepares a draft study report containing a detailed analysis on the economic costs and benefits of carrying out the project and identifies any associated environmental, social, or cultural impacts. The feasibility study weighs the benefits and costs of each project alternative being considered, and identifies the engineering features, public acceptability, and the purposes, scope, and scale of each.\13\ It also contains the views of other Federal and non-Federal agencies on project alternatives, a description of non-structural alternatives to the recommended plans, and a description of the anticipated Federal and non-Federal participation in the project.\14\ --------------------------------------------------------------------------- \13\ Id. \14\ Id. --------------------------------------------------------------------------- After a full feasibility study is completed, the results and recommendations of the study are submitted to Congress in the form of a Report of the United States Army Corps of Engineers Chief of Engineers (more commonly referred to as a Chief's Report).\15\ If the results and recommendations on the proposed project are favorable, then the next step is Congressional authorization for construction of the project, which is typically provided in a WRDA. --------------------------------------------------------------------------- \15\ See e.g., Corps, Planner's Library, (last accessed July 1, 2025), available at https://planning.erdc.dren.mil/TOOLBOX/ library.cfm?Option=Listing&Type=Corps%20National %20Libraries&Search=Library&Sort=Default. --------------------------------------------------------------------------- ADDITIONAL CORPS AUTHORITIES Congress has granted the Corps programmatic authorities, Continuing Authorities Programs (CAPs), that enable the Corps to undertake small-scale projects with limited scope and cost without requiring project-specific Congressional authorization.\16\ These projects typically require a cost- share with a non-Federal interest.\17\ --------------------------------------------------------------------------- \16\ See generally Anna Normand & Nicole Carter, Cong. Rsch. Serv. (IF12635), Continuing Authorities Programs (CAPs) of the U.S. Army Corps of Engineers (updated Jan. 16, 2025), available at https:// www.crs.gov/Reports/IF12635. \17\ Id. --------------------------------------------------------------------------- While there are also ongoing pilot CAPs, there are currently ten codified CAP categories: LStreambank erosion and shoreline protection; \18\ --------------------------------------------------------------------------- \18\ See Flood Control Act of 1946, 33 U.S.C. 701r Sec. 14. --------------------------------------------------------------------------- LBeach erosion control; \19\ --------------------------------------------------------------------------- \19\ See Act of August 13, 1946, 33 U.S.C. 426g Sec. 3. --------------------------------------------------------------------------- LNavigation improvement; \20\ --------------------------------------------------------------------------- \20\ See River and Harbor Act of 1960, 33 U.S.C. 577 Sec. 107. --------------------------------------------------------------------------- LMitigation of shore damage by Federal navigation projects; \21\ --------------------------------------------------------------------------- \21\ See River and Harbor Act of 1968, 33 U.S.C. 426i Sec. 11. --------------------------------------------------------------------------- LRegional sediment management/beneficial use of dredged material; \22\ --------------------------------------------------------------------------- \22\ See WRDA 1992, 33 U.S.C. 2326 Sec. 204. --------------------------------------------------------------------------- LFlood control; \23\ --------------------------------------------------------------------------- \23\ See the Flood Control Act of 1948, 33 U.S.C. 701s Sec. 205. --------------------------------------------------------------------------- LAquatic ecosystem restoration; \24\ --------------------------------------------------------------------------- \24\ See the WRDA 1996, 33 U.S.C. 2330 Sec. 206. --------------------------------------------------------------------------- LRemoval of obstructions and clearing channels for flood control; \25\ --------------------------------------------------------------------------- \25\ See the Act of August 28, 1937, 33 U.S.C. 701g Sec. 2. --------------------------------------------------------------------------- LProject modifications for improvement of the environment or drought resiliency; \26\ and --------------------------------------------------------------------------- \26\ See the WRDA 1986, 33 U.S.C. 2309a Sec. 1135. --------------------------------------------------------------------------- LStormwater management projects.\27\ --------------------------------------------------------------------------- \27\ See section 1108 of the WRDA 2024, 33 U.S.C. 2289b. --------------------------------------------------------------------------- III. WATER RESOURCES DEVELOPMENT ACTS (WRDAs) WRDA PROCESS Congress generally authorizes Corps' studies, projects, and programs and makes changes to agency policies through legislation referred to as WRDAs. Congress has developed and enacted WRDAs intermittently since the 1980s and has biennially enacted a WRDA since 2014.\28\ --------------------------------------------------------------------------- \28\ Id. --------------------------------------------------------------------------- Authorizing provisions in WRDAs can be project-specific, programmatic, or general policy directives for the Corps. Project-specific authorizations most often fall into one of three broad categories: project studies, construction projects, or modifications to existing projects. Furthermore, water resource projects typically require two types of Congressional authorization: (1) authority to study the feasibility of the project and (2) authority to construct (and operate and maintain, as applicable) the project.\29\ --------------------------------------------------------------------------- \29\ Id. --------------------------------------------------------------------------- WRDA 2024 Most recently, WRDA 2024 was signed into law as Division A of the Thomas R. Carper Water Resources Development Act of 2024 (P.L. 118-272) in January 2025.\30\ WRDA 2024 authorized 17 new construction projects, four project modifications, one project for construction based on a feasibility study carried out by a non-Federal interest, and over 200 new or modified feasibility studies.\31\ --------------------------------------------------------------------------- \30\ WRDA 2024, Pub. L. 118-272, 138 Stat. 2996 [Hereinafter WRDA 2024]. \31\ Id. --------------------------------------------------------------------------- WRDA 2024 made common sense policy reforms that empower the non-Federal sponsors of projects, increase transparency, and improve project delivery. For example, WRDA 2024 facilitated the creation of a new pilot program CAP for alternative project delivery and amended Sections 203 and 204 of WRDA 1986 to clarify and enhance the responsibilities of non-Federal interests in conducting studies and construction activities for authorized projects.\32\ Additionally, WRDA 2024 improved transparency and consistency to assist non-Federal entities achieve compliance with the P.L. 84-99 program and the process to modify existing projects under Section 408.\33\ --------------------------------------------------------------------------- \32\ Id., at Sec. 1107(a), 1109, 1110. \33\ Id., at Sec. 1105, 1146. --------------------------------------------------------------------------- Further, WRDA 2024 included the Grace F. Napolitano Priority for Water Supply, Water Conservation, and Drought Resiliency Act, which emphasizes the Corps' role in water supply and water resiliency efforts.\34\ WRDA 2024 instructed the Corps to prioritize and maximize water supply, water conservation, and drought resiliency efforts that are in alignment with the authorized purposes of water resources development projects.\35\ --------------------------------------------------------------------------- \34\ See Subtitle B, Title I, Division A of WRDA 2024, supra note 32. \35\ Id., at Sec. 1161, 1162, 1108. --------------------------------------------------------------------------- CORPS IMPLEMENTATION OF WRDAS In addition to WRDA 2024, the Corps continues to release implementation guidance and implement provisions from prior WRDAs. WRDA 2024 focused heavily on Congressional oversight, directing the Corps to implement changes in policy based on prior WRDAs more quickly and efficiently. For example, WRDA 2024 directed the Corps to develop a comprehensive plan to implement WRDA 2024 and prior WRDAs, including by identifying and addressing prior provisions that have not been fully implemented and by establishing a WRDA implementation team.\36\ WRDA 2024 also required the Corps to report to Congress on the status of reports the Corps was previously directed to complete by WRDAs.\37\ --------------------------------------------------------------------------- \36\ Id., at Sec. 1102. \37\ Id., at Sec. 1150. --------------------------------------------------------------------------- For WRDA 2024, the Corps held a series of listening sessions and a 60-day public comment period on implementation, which were completed by the end of April 2025.\38\ Through the process, the Corps determined which provisions of WRDA 2024 require specific implementation guidance, and which provisions may be implemented without specific guidance. As of September 5, 2025, the Corps has released implementation guidance for two sections of WRDA 2024.\39\ --------------------------------------------------------------------------- \38\ See Corps, Water Resources Development Act (WRDA) 2024, available at https://www.usace.army.mil/Missions/Civil-Works/Project- Planning/Legislative-Links/wrda_2024/. \39\ Once finalized, Implementation Guidance is posted at the site above. The Corps maintains similar implementation guidance pages for prior WRDAs, which can also be found on the Corps website. --------------------------------------------------------------------------- IV. WITNESSES LHon. Adam R. Telle, Assistant Secretary, United States Army (Civil Works) LLt. Gen. William H. ``Butch'' Graham, Jr., Chief of Engineers and Commanding General, United States Army Corps of Engineers WATER RESOURCES DEVELOPMENT ACTS IMPLEMENTATION: REVIEW AND OVERSIGHT OF PAST PROVISIONS ---------- WEDNESDAY, SEPTEMBER 10, 2025 House of Representatives, Subcommittee on Water Resources and Environment, Committee on Transportation and Infrastructure, Washington, DC. The subcommittee met, pursuant to call, at 10:01 a.m., in Room 2167, Rayburn House Office Building, Hon. Mike Collins (Chairman of the subcommittee) presiding. Mr. Collins. The Subcommittee on Water Resources and Environment will come to order. I ask unanimous consent that the chairman be authorized to declare a recess at any time during today's hearing. Without objection, so ordered. I also ask unanimous consent that Members not on the subcommittee be permitted to sit with the subcommittee at today's hearing and ask questions. Without objection, so ordered. As a reminder, if Members wish to insert a document into the record, please also email it to DocumentsTI@mail.house.gov. I now recognize myself for the purpose of an opening statement for 5 minutes. OPENING STATEMENT OF HON. MIKE COLLINS OF GEORGIA, CHAIRMAN, SUBCOMMITTEE ON WATER RESOURCES AND ENVIRONMENT Mr. Collins. I would like to thank Assistant Secretary Telle and General Graham for joining us today as we review the Corps' performance and implementation of recent Water Resources Development Acts. I want to give special congratulations to you, Assistant Secretary Telle, on your confirmation by the Senate by an overwhelmingly bipartisan vote just over a month ago. Based on the conversations we have had, I am confident that you will provide much needed leadership to the Army Corps of Engineers. I look forward to working with you to ensure the Corps fulfills its critical missions. I know that you both share the same goal as I do: to make the Corps act faster, more efficiently, and more economically. Unfortunately, Corps' project delivery often falls short of where it should be. I have a background in the trucking business where delivering on time is what keeps our doors open. And my goal as chairman of the subcommittee is to get the Corps to complete its protects on time, under budget, and correctly. I understand some of the budgetary problems that the Corps faces, but these are not excuses for study delays, years-long dredging backlogs, and mismanagement of repairs to vital locks and dams on our inland waterway system. Earlier this year, I was able to visit Wilson and Chickamauga locks in Alabama and Tennessee, which are crucial assets that serve America's economic and national security by ensuring two of our Nation's largest rivers are navigable to the Gulf of America. These locks and dams are a testament to the Corps' legacy of building America, but like so many other inland waterway projects, they are past their prime, so, rehabilitating and replacing them is taking too long and costing taxpayers far more than it should. We have a responsibility to invest and manage Americans' hard-earned tax dollars wisely and efficiently. While these projects are expensive, the Corps can and must do better. I am hopeful that section 1126 of the WRDA 2024, which changed the cost-share of these projects required to come from the Inland Waterway Trust Fund, will help the Corps move these projects along. Another area where the Corps can improve is the consistent dredging of America's harbors. My home State of Georgia's economy relies heavily on the consistent dredging of the Ports of Savannah and Brunswick. The year 2025 represented the busiest year on record for the Port of Savannah, and the Port of Brunswick recently became America's number one port for automobiles. Despite this incredible growth at Georgia's seaports, it has been years since Brunswick Harbor had been dredged to its federally authorized depth, leading to shoaling and threats of ships grounding. While I am pleased that the Corps has made Brunswick a priority this year, this vital port should not have gone this long without routine maintenance. The challenge at Brunswick is why I have made streamlining the Corps' dredging processes, including contracting practices and environmental windows that seem to prevent consistent maintenance of Federal channels, a top priority. WRDA 2024 and other recent WRDAs have also focused on Corps' recreation projects. I look forward to the Corps' implementation of these provisions to allow greater local control of the Corps' recreation sites to ensure public access. Recent failures by the Corps to manage and provide access to recreation sites at Lake Lanier in Georgia were a wakeup call that more needs to be done. Ultimately, I would like to get the Corps out of the business of running campgrounds and maintaining recreation sites so we can focus resources on navigation and flood control. Finally, I urge the Corps to prioritize implementation of section 1315 of WRDA 2024 regarding the New Savannah Bluff Lock and Dam in Georgia. This issue has been around for decades, and section 1315 provides a clear legal guideline for the Corps to follow, protecting the water supply behind the dam, providing for rehabilitation of the lock and dam, and clarifying the cost-sharing requirements. The Corps must prioritize finalizing the engineering necessary to complete the project and provide an accurate cost estimate so that all parties involved understand the costs of completing the project and can work to secure the appropriations necessary to put the issue to rest once and for all. [Mr. Collins' prepared statement follows:] Prepared Statement of Hon. Mike Collins, a Representative in Congress from the State of Georgia, and Chairman, Subcommittee on Water Resources and Environment I'd like to thank Assistant Secretary Telle and General Graham for joining us today as we review the Corps' performance and implementation of recent Water Resources Development Acts (WRDAs). I want to give special congratulations to you, Assistant Secretary Telle, on your confirmation by the Senate by an overwhelming bipartisan vote just over a month ago. Based on the conversations we've had, I am confident that you will provide much-needed leadership to the Army Corps of Engineers. I look forward to working with you to ensure the Corps fulfills its critical missions. I know that you both share the same goal as I do: to make the Corps act faster, more efficiently, and more economically. Unfortunately, Corps project delivery often falls short of where it should be. I have a background in the trucking business, where delivering on time is what keeps the doors open. My goal as Chairman of the Subcommittee is to get the Corps to complete its projects on time, under budget, and correctly. I understand some of the budgetary problems the Corps faces, but these are not excuses for study delays, years-long dredging backlogs, and mismanagement of repairs to vital locks and dams on our inland waterway system. Earlier this year, I was able to visit Wilson and Chickamauga Locks in Alabama and Tennessee: crucial assets that serve America's economic and national security by ensuring two of our nation's largest rivers are navigable to the Gulf of America. These locks and dams are a testament to the Corps' legacy of building America, but like so many other inland waterway projects, they are past their prime. Rehabilitating and replacing them is taking too long and costing taxpayers far more than it should. We have a responsibility to invest and manage Americans' hard-earned tax dollars wisely and efficiently. While these projects are expensive, the Corps can and must do better. I am hopeful that Section 1126 of WRDA 2024, which changed the cost-share of these projects required to come from the Inland Waterway Trust Fund, will help the Corps move these projects along. Another area where the Corps can improve is the consistent dredging of America's harbors. My home state of Georgia's economy relies heavily on consistent dredging of the Ports of Savannah and Brunswick. 2025 represented the busiest year on record for the Port of Savannah, and the Port of Brunswick recently became America's number one port for automobiles. Despite this incredible growth at Georgia's sea ports, it has been years since Brunswick Harbor had been dredged to its federally authorized depth, leading to shoaling and threats of ship groundings. While I am pleased that the Corps has made Brunswick a priority this year, this vital port should not have gone this long without routine maintenance. The challenge at Brunswick is why I've made streamlining the Corps' dredging processes, including contracting practices and environmental windows that seem to prevent consistent maintenance of federal channels, a top priority. WRDA 2024 and other recent WRDAs have also focused on Corps recreation projects. I look forward to the Corps' implementation of these provisions to allow greater local control of the Corps' recreation sites to ensure public access. Recent failures by the Corps to manage and provide access to recreation sites at Lake Lanier in Georgia were a wakeup call that more needs to be done. Ultimately, I would like to get the Corps out of the business of running campgrounds and maintaining recreation sites so it can focus resources on navigation and flood control. Finally, I urge the Corps to prioritize implementation of Section 1315 of WRDA 2024 regarding the New Savannah Bluff Lock and Dam in Georgia. This issue has been around for decades, and Section 1315 provides clear legal guidelines for the Corps to follow, protecting the water supply behind the dam, providing for rehabilitation of the lock and dam, and clarifying cost-share requirements. The Corps must prioritize finalizing the engineering necessary to complete the project and provide an accurate cost estimate so that all parties involved understand the costs of completing the project and can work to secure the appropriations necessary to put the issue to rest once and for all. Mr. Collins. Thank you. And I now recognize Ranking Member Wilson for 5 minutes for an opening statement. OPENING STATEMENT OF HON. FREDERICA S. WILSON OF FLORIDA, RANKING MEMBER, SUBCOMMITTEE ON WATER RESOURCES AND ENVIRONMENT Ms. Wilson of Florida. Thank you, Mr. Chairman, for hosting this, the leadership of the U.S. Army Corps of Engineers. The Corps plays a critical role for communities across the country, especially in my home State of Florida. Our ports, beaches, and hurricane preparedness depend on the Corps. We also are home to the Corps' largest environmental restoration endeavor in history, the restoration of the Florida Everglades. Assistant Secretary Telle and Lieutenant General Graham, you each carry a huge responsibility. However, I am concerned with your ability to be successful given the conditions you are facing. In just 9 months, the Trump administration has put the Corps under tremendous pressure. First, Corps funding and budgets are getting slashed, with the President recommending major cuts to the Corps' most essential missions. Second, the Corps is losing thousands of seasoned professionals through the deferred resignation programs, with over 3,000 Corps employees leaving since the beginning of this administration. Meanwhile, the Federal hiring freeze means there is nobody new coming in to fill these roles. Third, the administration is forcing the Corps' hand for political gain by pushing for unscheduled water releases, requiring legally questionable permit expedites, blocking reasonable permit requests for renewable energy, and telling them to look the other way while a detainment camp, Alligator Alcatraz, is constructed in the middle of the Corps' largest project, the Everglades Restoration. Simply put, I question how the Corps is going to fulfill its mandate to address the navigation, flood control, and environmental restoration needs of our communities with too little funding and too few Corps employees, and going against its own careful science- and engineering-based practices. Now that you have been confirmed, Secretary Telle, I hope we can see better leadership and decisionmaking from the Corps. The Corps needs consistent, robust funding to carry out its mission. In the next budget request, I hope to see full utilization of the available Harbor Maintenance Trust Fund dollars to keep our ports running efficiently and smoothly. This is essential for our local and national economies. I also hope to see funding for the environmental infrastructure projects that have become extremely popular in the last couple of WRDAs. There is a clear need and desire for water infrastructure funding, especially for our Tribal and minority communities facing affordability challenges. Lastly, I need assurances that the Corps will stand up for itself and not allow things like Alligator Alcatraz to be constructed. I remain appalled that this detainment camp was allowed to be expanded and operated in the heart of the Everglades. The risk of disturbing the Everglades, and therefore, reversing decades of Federal investment and progress is far too high. The Corps simply cannot sit by idly when something will have such a detrimental impact on the hard work of the Corps. And I will look for your commitment that no Federal Everglades restoration funding will be spent to address any lingering consequences of this hugely misguided decision. Secretary Telle, I am glad that you are here and hope you have been getting up to speed on all the critical projects that I am sure my colleagues will be asking about. I look forward to working with you and getting the Corps back on track. There is a lot of work to be done, and our ports, our waterways, our communities, and our ecosystems are counting on you. Both of you. Thank you, Mr. Chair. [Ms. Wilson of Florida's prepared statement follows:] Prepared Statement of Hon. Frederica S. Wilson, a Representative in Congress from the State of Florida, and Ranking Member, Subcommittee on Water Resources and Environment Thank you, Mr. Chairman, for hosting the leadership of the U.S. Army Corps of Engineers. The Corps plays a critical role for communities across the country, especially in my home state of Florida. Our ports, beaches and hurricane preparedness depend on the Corps. We also are home to the Corps' largest environmental restoration endeavor in history--the restoration of the Florida Everglades. Assistant Secretary Telle and Lieutenant General Graham, you each carry a huge responsibility. However, I am concerned with your ability to be successful given the conditions you are facing. In just nine months, the Trump Administration has put the Corps under tremendous pressure. First, Corps funding and budgets are getting slashed, with the President recommending major cuts to the Corps' most essential missions. Second, the Corps is losing thousands of seasoned professionals through the deferred resignation programs, with over 3,000 Corps employees leaving since the beginning of this administration. Meanwhile, the federal hiring freeze means there is nobody new coming in to fill these roles. Third, the Administration is forcing the Corps' hand for political gain by pushing for unscheduled water releases, requiring legally questionable permit expedites, blocking reasonable permit requests for renewable energy, and telling them to look the other way while a detainment camp is constructed in the middle of the Corps largest project, the Everglades Restoration. Simply put, I question how the Corps is going to fulfil its mandate to address the navigation, flood control and environmental restoration needs of our communities with too little funding and too few Corps employees, and going against its own careful, science- and engineering- based practices. Now that you have been confirmed, Secretary Telle, I hope we can see better leadership and decision-making from the Corps. The Corps needs consistent, robust funding to carry out its mission areas. In the next Budget Request, I hope to see full utilization of the available Harbor Maintenance Trust Fund dollars, to keep our ports running efficiently and smoothly. This is essential for our local and national economies. I also hope to see funding for the Environmental Infrastructure projects that have become extremely popular in the last couple WRDAs. There is a clear need and desire for water infrastructure funding, especially for our Tribal and minority communities facing affordability challenges. Lastly, I need assurances that the Corps will stand up for itself and not allow things like ``Alligator Alcatraz'' to be constructed. I remain appalled that this detainment camp was allowed to be expanded and operated in the heart of the Everglades! The risk of disturbing the Everglades, and therefore reversing decades of federal investment and progress, is far too high. The Corps simply cannot sit by idly when something will have such a detrimental impact on the hard work of the Corps. And I will look for your commitment that no federal Everglades restoration funding will be spent to address any lingering consequences of this misguided decision. Secretary Telle, I am glad you are here and hope you have been getting up to speed on all the critical projects that I'm sure my colleagues will be asking about. I look forward to working with you and getting the Corps back on track. There is a lot of work to be done, and our ports, waterways, communities, and ecosystems are counting on you. Mr. Collins. I now recognize the ranking member of the full committee, Mr. Larsen, for 5 minutes for an opening statement. OPENING STATEMENT OF HON. RICK LARSEN OF WASHINGTON, RANKING MEMBER, COMMITTEE ON TRANSPORTATION AND INFRASTRUCTURE Mr. Larsen of Washington. Thank you, Chair Collins and Ranking Member Wilson, for holding this hearing. Congratulations to Secretary Telle on your confirmation last month. I am happy to welcome you to the T&I Committee for your first appearance at a hearing since your confirmation. And, congratulations, Lieutenant General Graham, on your promotion to Chief of Engineers. I know this isn't your first time in front of the committee, but it is your first time as Chief. Since 2014, this committee has honored its commitment to meet local water resources needs across the country through the bipartisan and biennial enactment of the Water Resources Development Act. Predictable passage of WRDA bills support Corps' projects while creating jobs in construction and the industries and businesses that benefit directly from these projects. Regular enactment of WRDA bills also allows for the timely implementation of critical policy reforms that improve the function and flexibility of the Corps to respond to local water resources challenges. WRDA 2024 built on the historic bipartisan success of this committee. The law successfully authorized the construction of 21 new projects, covering every facet of the Corps' missions, as well as over 150 new feasibility studies for future projects. WRDA 2024 also authorized more than $5 billion in environmental infrastructure assistance for community-driven projects, including $242 million for water and wastewater infrastructure that local officials in western Washington State requested. These Federal, State, and local partnerships are critical to help address the growing water and wastewater infrastructure needs throughout the country. Lastly, WRDA 2024 continued to expand America's navigational capacity, strengthen its supply chains, ensure our communities are resilient to the challenges posed by climate change, and increase opportunities for the Corps to partner with rural, Tribal, and economically disadvantaged communities in addressing their unique needs. However, authorization of projects or studies is only the first step for communities to realize the benefits of water resource improvements. The administration must request, and Congress must provide, sufficient funding for project planning, construction, and operation and maintenance to realize the benefits of these authorized projects and activities. The Bipartisan Infrastructure Law was a great example of how this should work. The BIL provided a large downpayment, about $17 billion, for critical WRDA projects, making a positive impact on communities and creating and supporting good-paying American jobs and the U.S. economy. Contrast that with the significant reductions in Corps funding included in this administration's fiscal year 2026 budget request. This 24-percent reduction in Corps funding will significantly slow project delivery; delay the realization of critical transportation, flood control, and environmental benefits; worsen supply chain delivery challenges; and leave communities vulnerable to extreme weather events. The fiscal year 2026 budget also ignores the legal requirements of WRDA to spend 100 percent of annual Harbor Maintenance Trust Fund collections for critical port maintenance work, as well as to dedicate 12 percent of those expenditures to donor and energy transfer ports. This $1 billion cut in maintenance and dredging work will lead to more costly imports and exports, further increasing costs for U.S. families and businesses. And this cut will equally affect our largest container ports, such as Seattle- Tacoma, Los Angeles-Long Beach, and New York-New Jersey, as well as ports critical to domestic energy production, such as Mobile, Houston, and New Orleans. Robust and sustained Federal investment is necessary for timely implementation of flood control, navigation, environmental restoration, water supply, and other key projects. Cuts to Corps funding will lead to higher costs for communities and families down the road. Deferred maintenance becomes disaster recovery, preventable failures become national emergencies. So, I look forward to a continued partnership with Chair Graves, Chair Collins, and Ranking Member Wilson in developing a new, bipartisan WRDA 2026, and I welcome the leadership of the Corps here today as part of that discussion. With that, I yield back. [Mr. Larsen of Washington's prepared statement follows:] Prepared Statement of Hon. Rick Larsen, a Representative in Congress from the State of Washington, and Ranking Member, Committee on Transportation and Infrastructure Thank you, Chairman Collins and Ranking Member Wilson, for holding this hearing. Congratulations, Assistant Secretary Telle, on your confirmation last month. I'm happy to welcome you to the T&I Committee for your first appearance at a hearing since your confirmation. Congratulations, Lieutenant General Graham, on your promotion to Chief of Engineers. I know this is not your first time in front of the Committee, but I believe it is your first as Chief. Since 2014, this Committee has honored its commitment to meet local water resources needs across the country through the bipartisan and biennial enactment of Water Resources Development Acts (WRDAs). Predictable passage of WRDAs support Corps projects while creating jobs in construction and the industries and businesses that benefit directly from these projects. Regular enactment of WRDA bills also allows for the timely implementation of critical policy reforms that improve the function and flexibility of the Corps to respond to local water resources challenges. WRDA 2024 builds on the historic bipartisan success of this Committee. This law successfully authorized the construction of 21 new projects, covering every facet of the Corps' missions, as well as over 150 new feasibility studies for future water resources development projects. WRDA 2024 also authorized more than $5 billion in environmental infrastructure assistance for community-driven projects, including $242 million for water and wastewater infrastructure requested by local officials in western Washington state. These federal, state and local partnerships are critical to help address the growing water and wastewater infrastructure needs throughout the country. Lastly, WRDA 2024 continued to expand America's navigational capacity, strengthen its supply chains, ensure our communities are resilient to the challenges posed by climate change and increase opportunities for the Corps to partner with rural, Tribal and economically disadvantaged communities in addressing their unique needs. However, the authorization of projects or studies is only the first step for communities to realize the benefits of water resource improvements. The Administration must request, and Congress must provide, sufficient funding for project planning, construction and operation and maintenance to realize the benefits of authorized Corps' projects and activities. The Bipartisan Infrastructure Law was a great example of how this should work. The BIL provided a large downpayment--about $17 billion-- for critical WRDA projects, making a positive impact on communities and creating and supporting good-paying American jobs and the U.S. economy. Contrast that with the significant reductions in Corps' funding included in this Administration's fiscal year 2026 budget request. This 24 percent reduction in Corps funding will significantly slow project delivery, delay the realization of critical transportation, flood control and environmental benefits, worsen supply chain delivery challenges and leave communities vulnerable to extreme weather events. The FY2026 budget also ignores the legal requirements of WRDA to spend 100 percent of annual Harbor Maintenance Trust Fund (HMTF) collections for critical port maintenance work, as well as to dedicate 12 percent of expenditures to donor and energy transfer ports. This $1 billion cut in maintenance and dredging work will lead to more costly imports and exports, further increasing costs for U.S. families and businesses. And this cut will equally affect our largest container ports, such as Seattle/Tacoma, Los Angeles/Long Beach and New York/New Jersey, as well as the ports critical to domestic energy production, such as Mobile, Alabama; Houston, Texas; and New Orleans, Louisiana. Robust and sustained federal investment is necessary for timely implementation of flood control, navigation, environmental restoration, water supply and other water resources development projects. Cuts to Corps funding will lead to higher costs for communities and families down the road. Deferred maintenance becomes disaster recovery; preventable failures become national emergencies. I look forward to a continued partnership with Chairman Graves, Chairman Collins and Ranking Member Wilson in developing a new, bipartisan WRDA 2026 and welcome the leadership of the Corps here today as part of that discussion. Mr. Collins. Thank you. I would now like to welcome our witnesses and thank them for being here today. Briefly, I would like to take a moment to explain our lighting system to our witnesses. There are three lights in front of you. Green light means go; yellow light means you are running out of time; and red means to please conclude your remarks. I ask unanimous consent that the witnesses' full statements be included in the record. Without objection, so ordered. I also ask unanimous consent that the record of today's hearing remain open until such time as our witnesses have provided answers to any questions that may be submitted to them in writing. Without objection, so ordered. I also ask unanimous consent that the record remain open for 15 days for any additional comments and information submitted by Members or witnesses to be included in the record of today's hearing. Without objection, so ordered. As your written testimony has been made a part of the record, the subcommittee asks that you limit your oral remarks to 5 minutes. With that, Assistant Secretary Telle, you are recognized for 5 minutes for your testimony. TESTIMONY OF HON. ADAM R. TELLE, ASSISTANT SECRETARY OF THE ARMY FOR CIVIL WORKS, DEPARTMENT OF THE ARMY; AND LIEUTENANT GENERAL WILLIAM H. ``BUTCH'' GRAHAM, JR., CHIEF OF ENGINEERS AND COMMANDING GENERAL, U.S. ARMY CORPS OF ENGINEERS TESTIMONY OF HON. ADAM R. TELLE, ASSISTANT SECRETARY OF THE ARMY FOR CIVIL WORKS, DEPARTMENT OF THE ARMY Mr. Telle. Thank you, Chairman Collins. Chairman Collins, Chairman Graves, Ranking Member Wilson, Ranking Member Larsen, and distinguished members of the committee, thank you for the opportunity to be here today to discuss the Army Civil Works program and implementation of the Water Resources Development Acts. My name is Adam Telle, and I am honored to serve as the 14th Assistant Secretary of the Army for Civil Works, and as President Trump's, Secretary Hegseth's, and Secretary Driscoll's top official responsible for overseeing the U.S. Army Corps of Engineers Civil Works mission. I was nominated by President Trump on March 24th of this year, and I was confirmed by the Senate on August 2nd. I began working this role immediately and have been on the job for 5\1/ 2\ weeks. During this time, I have been working alongside General Graham and his team to ensure that the Army Civil Works program is positioned to deliver on President Trump's vision for our country and on its critical mission, which this committee has had an important role in defining. I will say that I am pleased that I was able to spend a significant amount of time with the Senate during the confirmation process and throughout my career, but I am very honored to be here in front of the House of Representatives today. And I would just like to compliment the chairman of this subcommittee, Chairman Collins; he is someone who understands this mission. He understands the efficiencies we need to drive, and I believe, under his leadership, he and I will be able to accomplish much together during our time in these roles. When I moved to Washington in 2005, I worked as a staff member in the United States Senate. I took that job because I believed I could make a difference in helping to represent the views and interests of the Americans I grew up with who often felt ignored or forgotten by important people in Washington. This is the reason I am honored to be part of the Army Civil Work's mission. It touches large and small communities every single day in communities across the country. Very few Government agencies' missions capture the interests of American citizens, landowners, communities, States, job creators, and their Representatives here in Washington quite like this one. The U.S. Army Corps of Engineers originated in 1775, 250 years ago. The America we know today is the result of the work of the Corps. Congress has given the Corps missions in addition to its original navigation mission, including flood control, and ensuring the future availability of our natural resources. Because this mission is important to the American public and elected Representatives here in Washington, during my first weeks, I have been working to establish greater consistency and accountability across the four layers of this enterprise, which include my office and the Corps headquarters, divisions, and districts. It is my mission to deliver navigation, flood control, disaster response, and stewardship of our natural resources to the American public as effectively as possible, as quickly as possible, and as cost efficiently as possible. We must optimize our program for quality, speed, and cost if we want to do our part to protect lives and commerce as President Trump is delivering on his vision to ensure the United States remains the greatest Nation in the history of the world during the 21st century. Our partners here on Capitol Hill, and particularly on this committee, have been pivotal in supporting this enterprise, and I request your partnership as I work with General Graham to ensure the Civil Works enterprise evolves to be more efficient and consistent to meet our modern demands. And the demand for the Corps' work continues to grow. To deliver against that workload, we must work in partnership with Congress throughout the executive branch and with our stakeholders to drive efficiency, collaboration, and results in an environment that is necessarily resource constrained. In addition to driving more efficiency into the Civil Works program, we must continue to lift the Federal regulatory burden on local sponsors. This administration is committed to ending the last five decades of confusing and ever-changing definitions of the term ``waters of the United States'' pursuant to the Clean Water Act of 1972. Together with Administrator Zeldin and President Trump's Environmental Protection Agency, the Army has already issued interim guidance that follows the Supreme Court's Sackett decision, and we will move quickly to ensure that a permanent definition that follows the post-Sackett law of the land cuts redtape, cuts overall permitting costs, lowers the cost of doing business in communities across the country, and continues to protect America's waters. In July, my office made much needed changes to our National Environmental Policy Act implementing procedures that will reform, modernize, and expedite the Corps' environmental reviews; eliminate unnecessary delays; and help ensure the growth of highly cost-effective and reliable infrastructure across the Nation. We also recognize the opportunities provided through WRDA 2024 to address navigation, reservoir management, and beneficial use of dredged material. As we spend time today reviewing WRDA 2024, I look forward to getting insight about your views and interests so that together we can serve America's vital infrastructure interests. Finally, I would like to take a brief moment to recognize my father, Whitney Royce Telle, who passed away this past Friday at age 73. He was a brilliant geologist, a passionate historian, a faithful husband to my wonderful mom, Rita, and a great American. He was the type of man our country needs, and the type of father I hope to be. Thank you, Dad. We miss you. Thank you, Chairman Collins, Ranking Member Wilson, and members of this committee. I look forward to any questions you may have. [Mr. Telle's prepared statement follows:] Prepared Statement of Hon. Adam R. Telle, Assistant Secretary of the Army for Civil Works, Department of the Army Chairman Collins, Ranking Member Wilson, and distinguished members of the committee, thank you for the opportunity to be here today to discuss the implementation of the Water Resources Development Acts (WRDA). My name is Adam Telle, and I am honored to serve as the fourteenth Assistant Secretary of the Army for Civil Works and as President Trump's, Secretary Hegseth's, and Secretary Driscoll's top official responsible for overseeing the U.S. Army Corps of Engineers' civil works mission. I was nominated by President Trump on March 24, 2025, and confirmed by the Senate on August 2, 2025. I began work in this role immediately and have been on the job for five-and-a-half weeks. During this time, I have been working alongside General Graham and his team to ensure that the Army Civil Works program is positioned to deliver on its critical mission, which this Committee has had an important role in defining, and on President Trump's vision for our country. When I moved to Washington in 2005, I worked as a staff member in the United States Senate. I believed that I could make a difference helping to represent the views and interests of the Americans I grew up with who often felt ignored or forgotten by important people in Washington. This is the reason I am honored to be a part of the Army Civil Works mission. It touches small and large communities and everyday Americans across the country. Few government agencies' missions capture the interests of American citizens, landowners, communities, states, job creators and their representatives here in Washington quite like this one. The U.S. Army Corps of Engineers originated in 1775, before the Declaration of Independence. The America we know today is a result of the work of the Corps. Congress has given the Corps missions in addition to its original navigation mission: flood control, flood fighting, enabling commerce and critical supply chains through dredging, and ensuring the future availability of our aquatic ecosystem resources. These missions are also important to our current President. Because this mission is also important to the American public and their elected representatives here in Washington, during my first weeks, I have been working to establish greater consistency and accountability across the four layers of this enterprise: My office, and the Corps of Engineers' headquarters, divisions and districts. The Corps supports commercial navigation, helps reduce flood risks, restores aquatic ecosystems, and provides stewardship of the natural resources on Corps lands to benefit the American public as effectively as possible, as quickly as possible, and as cost-effectively as possible. We must optimize our program for quality, speed, and cost if we want to do our part to protect lives and commerce as President Trump is delivering on his vision to ensure that our United States remains the greatest Nation in the history of the world during the 21st century. Our partners here on Capitol Hill, and particularly on this Subcommittee have been pivotal to supporting this enterprise, and I request your partnership as I work with General Graham to ensure the Civil Works enterprise evolves to become more efficient and consistent and meet our modern demands. And the demand for the Corps of Engineers' work continues to grow. To deliver against that workload, we must work in partnership with the Congress, throughout the Executive Branch, and with our stakeholders to drive efficiency, collaboration, and results in an environment that is necessarily resource constrained. In addition to driving more efficiency into the Civil Works program, we must continue to lift the federal regulatory burden on local sponsors. This Administration is committed to ending the last five decades of confusing and ever-changing definitions of the term ``waters of the United States'' in the Clean Water Act of 1972. Together with Administrator Zeldin and President Trump's Environmental Protection Agency, the Army has already issued interim guidance that follows the Sackett decision, and we will move quickly to issue a permanent definition that follows the post-Sackett law of the land, reduces red-tape, cuts overall permitting costs, lowers the cost of doing business in communities across the country, and protects America's waters. In July, my office made much-needed changes to our National Environmental Policy Act implementing procedures that will reform, modernize, and expedite the Corps' environmental reviews, eliminate unnecessary delays, and help ensure the growth of highly cost effective, reliable infrastructure projects across the Nation. We also recognize the opportunities, provided through WRDA 2024, to address navigation, reservoir management, and beneficial use of dredged material. As we spend time today reviewing WRDA 2024, I look forward to gaining insight about your views and interests so that, together, we can serve America's vital infrastructure interests. Thank you, Chairman Collins, Ranking Member Wilson and Committee Members. I look forward to answering any questions you or other Members of the Committee may have. Mr. Collins. Thank you. Next, General Graham, you are recognized for 5 minutes for your testimony. TESTIMONY OF LIEUTENANT GENERAL WILLIAM H. ``BUTCH'' GRAHAM, JR., CHIEF OF ENGINEERS AND COMMANDING GENERAL, U.S. ARMY CORPS OF ENGINEERS General Graham. Chairman Collins, Ranking Member Wilson, Ranking Member Larsen, members of the subcommittee, I am honored to testify before you today in regard to the implementation of the Water Resources Development Acts. Through the Civil Works program, the Army Corps works with our partners to study, build, and operate water resource projects focusing on our three main mission areas of commercial navigation, flood and storm damage reduction, and aquatic ecosystem restoration. Breaking those down. The navigation program, which consists of our coastal, Great Lakes, channels, as well as the inland rivers and intercostal waterways, underpins much of the national economy, and it ensures that commodities can move reliably and efficiently. Our flood and storm damage reduction program maintains 746 dams, over 13,000 miles of Federal levees, and 450 miles of shore protection. That system provides on average $200 billion per year--$200 billion per year--in flood damages avoided. To continuously maintain and improve these mission areas, I want to thank this subcommittee for supporting the Corps' Civil Works program. As you heard from Ranking Member Larsen, your commitment since 2014 to pass biennial Water Resources Development Acts has provided the Corps with the authorities necessary to address the changing needs of the Nation's water resources infrastructure. In WRDA 2024, Congress authorized new construction projects, new feasibility studies, and new environmental infrastructure projects. These studies and projects, when funded, will strengthen the supply chain, better protect Americans from flooding, and improve degraded aquatic environments. We deeply value the authorities you have entrusted to us, and our pledge is to put them to work to deliver for the American people. To that end, the Army Corps' objective every day is to safely deliver quality studies and projects on schedule and within budget. To this end, and I spent 4 hours with the team yesterday looking at this, our current on-schedule rate across the Civil Works portfolio is 80.1 percent. That is a low, low ``B,'' and that is unacceptable. This performance is influenced by factors that we can control and we can't control. Focusing on those things we can control, the Corps is absolutely committed to procedural improvements in the following three areas. First, get the engineering right. The focus here is on the maturity of our designs. We are not to request project authorization unless the design is advanced enough that we truly understand what it is that we are proposing to build. That threshold is usually around the 35- percent level. There are some nuances that we need to work through with Congress on this regarding the complexities of cost share and how to break down large, complex projects, but fundamentally, fundamentally, we need to better understand what it is we are proposing to build before we request that you authorize us to build it. Second thing we need to improve upon is getting the project management right. The focus here is on crafting logical, fully resourced schedules and sticking dogmatically to them, ensuring that we are delivering these important projects with a great sense of urgency. Finally, the third thing is to get the team right. We are striving to bring together the right mix of talent, either onboard manning, or by leveraging the incredible talents of the private-sector firms. So, in closing, the path to successful delivery is clear: plan projects thoroughly and then build them rapidly with the right team of master craftsmen. I look forward to working with this committee to stay on that path. Thank you, again, Chairman, for the opportunity to testify, and I look forward to addressing your questions. [General Graham's prepared statement follows:] Prepared Statement of Lieutenant General William H. ``Butch'' Graham, Jr., Chief of Engineers and Commanding General, U.S. Army Corps of Engineers Chairman Collins, Ranking Member Wilson, and Members of the Subcommittee: I am honored to testify before your committee today, along with Mr. Adam Telle, the Assistant Secretary of the Army for Civil Works, in regard to implementation of Water Resources Development Acts, including review and oversight of past provisions. I look forward to continuing to work with this committee, the Congress, and the Administration to help address the Nation's water resources challenges. Through the Civil Works Program, the U.S. Army Corps of Engineers (Corps) works with other Federal agencies, and with state, Tribal, and local agencies and others, to develop, manage, restore, and protect water resources, primarily through the construction, operation and maintenance, and study of water-related infrastructure projects. The Corps focuses on work that provides high economic, environmental, and public safety returns to the Nation. The Corps also regulates development in waters of the United States and works with other Federal agencies to help communities respond to, and recover from, floods and other natural disasters. The authorizations and funding provided to the Corps by Congress allow us to advance our three main missions of commercial navigation, flood and storm damage reduction, and aquatic ecosystem restoration, as well as support related project purposes, such as water supply, hydropower, and recreation. The Civil Works program is performance- based and focuses on high-performing projects and programs within these three main mission areas. The Corps uses its engineering expertise and relationships with project sponsors and other stakeholders to develop innovative approaches to address some of the most pressing water resources challenges facing the Nation. Since 2014, the Congress has passed a WRDA bill every two years to address evolving water resources issues. The Water Resources Development Act (WRDA) of 2024 advances the Corps principal Civil Works missions by authorizing new navigation, flood risk management, coastal storm risk management, and aquatic ecosystem restoration projects and studies across the country. The legislation reinforces the Corps' partnership with non-federal sponsors by reauthorizing and refining existing programs, while introducing new tools to enhance coordination with non-federal partners, improve project delivery, and address evolving national priorities. WRDA 2024 also formalizes the creation of an implementation planning team to track the status of implementation of prior WRDAs. To promote long-term infrastructure resilience and to support coastal and riverine communities, WRDA 2024 provides expanded authority for forecast-informed reservoir operations and supports beneficial use of dredged material for shoreline restoration and flood risk reduction. It also authorizes recurring coastal mapping activities to ensure timely data for navigation safety and storm preparedness. Across all mission areas, WRDA 2024 includes provisions to streamline project implementation, facilitate crediting for non-federal contributions such as technical models, and improve transparency in project prioritization, strengthening the Corps ability to deliver safe, high- quality water resources infrastructure that supports both local communities and national economic interests. My top priorities include identifying the highest priority potential investments for the Army Civil Works Program, starting with the maintenance of our existing infrastructure, and ensuring that we deliver studies and finish quality projects safely, on time, and within budget. I remain focused on implementing strategies to enhance project delivery efficiency and cost predictability. By strengthening feasibility study and preconstruction engineering and design (PED) requirements, and by using risk management principles, the Corps is working to improve cost and schedule accuracy. Increased industry engagement, including early contractor involvement and market research initiatives, is helping to align expectations and ensure more competitive bids. A sustainable Civil Works program requires effective project delivery methods, and strong partnerships with federal, state, Tribal, and local stakeholders. By enhancing early-stage project development, and proactively managing risks, the Corps is working to ensure that its infrastructure investments will continue to provide the greatest return on investment to the Nation at a reasonable cost. These priorities will ensure a better return on taxpayer investment and improve the lives of all Americans. Thank you, Chairman Collins, Ranking Member Wilson, and Members of the Subcommittee. This concludes my statement. I look forward to answering any questions you or other Members of the Subcommittee may have. Mr. Collins. Thank you all for your testimony. We will now turn to questions from the panel, and I will recognize myself for 5 minutes for questions. As I mentioned in my statement, I am concerned about dredging backlogs. In my home State of Georgia, the Port of Brunswick went years without being dredged to its authorized depth, which led to multiple ship groundings and hurting our supply chain. Unfortunately, this is due to multiple bureaucratic issues within the Federal Government, including antiquated contracting processes, nonsensical environmental windows, and budgeting that doesn't make sense in the real world. For either of you, can you briefly describe how the Corps is improving its dredging processes to ensure that the ports throughout the country get dredged when they need to? Mr. Telle. Chairman Collins, thank you for the question. Dredging capacity is critically important to our ability to be competitive in the 21st century. This is a time when others across the globe are trying to displace the United States of America as the greatest nation in the history of the world. And if we can't open our ports and harbors via regular dredging, we are not going to be as competitive as we enter this global competition. You specifically raised issues around contracting; I think you are right. I think we have to take a very hard look at how we are contracting, looking at the capacity that exists out there in the private sector. You mentioned environmental windows; this is a critically important challenge because our ability to dredge is constrained by these environmental windows quite often. There are ways that we are researching right now to expand those environmental windows, and I will let General Graham expand on that if he would like. And then there is also a need to recapitalize assets that are native to the U.S. Army Corps of Engineers. If we do all of these things, we have the potential to increase our dredging capacity at a time when our Nation desperately needs it. Your port in your State is critically important to our Nation. And I have heard this throughout, on both sides of the aisle and in both Houses of Congress, that this is critically important to the Nation and to the Members of Congress and the Senate. So, I look forward to working with General Graham to help get this right. General Graham, I will defer to you for any additional comments you may have. General Graham. Chairman, we have got many members of the dredging industry with us today, and so, I am pleased to say that we are working collaboratively within the industry to bring capacity on board. And I am delighted to see the progress that has been made. I think, with the pipeline dredges, there is good capacity out there right now, and industry is working to bring more of the oceangoing hopper dredges. As Mr. Telle spoke to, by 2027, we should have a replacement for the Corps' east coast hopper dredge, which will be known as the Donnelly, to backstop where industry capacity falls short. Where I am most concerned right now is dredging capacity up on the Great Lakes, and so, that has our full interest. Mr. Collins. Thank you. I am also concerned about the Corps' involvement in recreation at its sites. Earlier this year, multiple recreation sites in Georgia and around the country were shut down because there were no Corps personnel there to run them. However, it seems to me that some of these responsibilities don't need to fall on the Corps. For either of you, what opportunities exist to either transfer ownership of the Corps' recreational assets to locals or to hand over the responsibility to locals at the Corps' own recreation sites? Mr. Telle. Chairman Collins, thank you for the question. And, as you importantly point out, one of the ancillary benefits of the Corps' work is that it often provides opportunities for Americans to enjoy recreational opportunities on lands owned by the Corps of Engineers. Unfortunately, the recreational workforce is a seasonal one, and I would say that there were some shortages in the workforce this spring that frustrated many Americans who enjoy Corps of Engineers' facilities, frustrated many Members of Congress who represent those Americans. It is unacceptable. But I will say that President Trump's administration recognized this problem very early and worked very quickly to begin rehiring these folks, which is largely seasonal workforce, to restore recreation this summer. And I will assure you, Chairman Collins, that we will get this issue fixed before next summer's recreational season begins. With regard to transferring responsibility to local entities, I am a believer across the board that the more we can delegate our authorities and our responsibilities to State and local partners, the better off we are going to be. They can do things more efficiently, quite often, and more cost effectively than we can here in Washington. And so, I am looking forward to working with you and with General Graham to ensure that we are able to delegate as much of that responsibility as we can so we can get it right for the American public. Mr. Collins. I had one more thing I wanted to run by, unless you want to add to it, General. I wanted to ask you about the New Savannah Bluff Lock and Dam. When are you going to be able to release the implementation guidance for the WRDA 2024, and have you got a cost estimate? General Graham. Chairman, thank you for that question. On the New Savannah Bluff Lock and Dam, we are working with the Assistant Secretary's office on that implementation guidance, but we are not sitting still. We are working right now on doing a structural assessment of the dam and the lock to make sure that we know the shape that that's in. That should take about a year to do that work, and then we will be prepared to ensure that that pull stays stable, and we will be able to comply with the guidance we have been given in WRDA 2024. Mr. Collins. Is that a year from today, or is that a year from when you started, or is that early next year? General Graham. That would be--Chairman, let me get back to you with a full answer on an exact date when we are going to finish. Mr. Collins. All right. Well, I would appreciate that. With that, I yield 5 minutes to the ranking member, Ms. Wilson. Ms. Wilson of Florida. Thank you. Thank you, Mr. Chair. Honorable Telle, Adam Telle, how are you? Mr. Telle. Good ma'am, thank you. Ms. Wilson of Florida. Good, welcome. Section 2019 authorizations for Miami-Dade have grown to over $190 million, and Broward County received a $50 million authorization in WRDA 2024. Secretary Telle, what is your plan to deliver these projects efficiently, and will you commit to putting in priority order section 2019 projects for historically underserved neighborhoods in Miami-Dade that face the most severe flooding and water quality issues? Mr. Telle. Ranking Member Wilson, thank you for the question. In a necessarily resource-constrained environment, I am focused on ensuring that the Corps of Engineers is focused on its core, c-o-r-e, missions, which include navigation, flood control, and aquatic ecosystem restoration. With that said, Congress has often called on the Corps of Engineers to take on municipal water supply that has traditionally been the responsibility of State or local governments. And, in places like your district, where the law says that we ought to prioritize these efforts to help local communities access reliable and safe drinking water, we are committed to following the law, and I absolutely look forward to working with you to make sure that the communities within your district that are most in need of this are benefited by the laws that this committee has helped enact. Ms. Wilson of Florida. Thank you. And, General Graham, as the Corps' top engineer, what specific operational steps are being taken to ensure that timely progress on the comprehensive Everglades restoration plan? General Graham. Ranking Member Wilson, thank you for that question. We are working collaboratively with the State of Florida right now to ensure that we are focusing on the end result, on restoring those Everglades as fast as possible. And whoever is in the best position to do that is who we are going to--basically we are going to turn to them to do the work. And we have got a great governance infrastructure in place right now, met this week, to ensure that that team has the proper oversight and we deliver efficiently. Ms. Wilson of Florida. So, tell me this, workforce losses under the Federal hiring freeze threaten Corps capacity; so, how are you ensuring that the Corps maintains the technical-- technical--expertise necessary to deliver their complex projects like Everglades restoration? General Graham. Ranking Member Wilson, again, thank you for that question. We are continuously--we go through about--our annual attrition rate is around 12 percent. So, for an organization, I will just round up to 40,000 people, that is around 4,000 folks that we have to replace every year. And so, we continuously are on a hunt for talent to bring new people in and train them up. Optimizing the workforce under the guidance of Assistant Secretary Telle is paramount, imperative for us. So, we are working to make sure that the workforce is at the right size to deliver on the work and that they have the right talents, and I am confident that we will be able to do that. Ms. Wilson of Florida. You are confident that you will be able to do that? General Graham. I am. Ms. Wilson of Florida. Okay. So, Secretary Telle, the Back Bay study has been elevated as a priority for addressing storm surge and sea level rise in Miami-Dade County. How will you ensure sustained Federal leadership and funding so that Back Bay study's recommendations are implemented on schedule and equitably benefit the most vulnerable communities? Do you have a plan in place? Mr. Telle. Ranking Member Wilson, thank you for the question. And you have identified an issue that is important in your district and throughout the country. In the deep history of the Corps of Engineers, the focus on flood control related to riverine systems where the flooding was relatively predictable and that it happened on an annual basis, generally during the wet season or during snow melt or during the spring. Riverine systems are more easy to engineer against flood protection than our coastal systems. In recent years, the Congress and various administrations have worked to try to get our hands around how we can protect coastal areas better, and it is a big challenge. And many of these projects are regional in scope. They are complex. They have many different--they are systems of systems that all depend on the other. And General Graham and I have spoken many times in my short time in this office and will continue to work to ensure that we need to have these large complex regional projects, that we need to provide you here in the Congress with elements of those projects that are budgetable, actionable, and separable, which means the Congress can make investments in those projects in a way that allows General Graham and his team to deliver on pieces of them and provide flood protection to communities like yours without studying it forever and to actually build things. And so, that is one of the strategies, there are many more, and I look forward to working with you on getting this right. Ms. Wilson of Florida. Thank you. Thank you, Mr. Chair. Mr. Collins. Thank you. I now recognize Mr. Bost for 5 minutes. Mr. Bost. Thank you, Mr. Chairman. And I want to thank the witnesses for being here. Mr. Telle, the levee maintenance and oversight in my district is vitally important since I have three navigable waterways with the Mississippi, the Ohio, and the Kaskaskia River, and one bad flood can lead to hundreds of acres of farmlands, homes, historical properties, and livelihoods lost in an instant. Mr. Telle, I mentioned in our call last week I was concerned about a scour hole that continues to grow next to the levee in Monroe County, Illinois, and how dangerous it could be if the Mississippi floods. Can you speak to how the Corps keeps track of threats of levees, like the scour hole, and when you know to step in, and, also, how are you working to streamline the levee maintenance process and your communication efforts with stakeholders? Mr. Telle. Congressman Bost, thank you for the question, and thank you for the job you do representing a very important part of our country in southern Illinois where two of our Nation's most important rivers converge. You mentioned the Ohio and the Mississippi. It is very important that we get levee safety right, and levee maintenance right. And so I would defer to General Graham on the inventory process that he uses to help advise us on which levees need our most rapid attention. But I will say that one of my priorities in this role is to work to make sure the four layers of the organization that I mentioned in my opening statement, my office, the Assistant Secretary's office, General Graham's headquarters, our divisions, our 9 divisions and our 39 districts, and I believe that your district is under the jurisdiction of a multiple of those districts, are working in a harmonious way that measures priorities across the Nation in a consistent way, and delivers the results that you and the taxpayers expect from our United States Army Corps of Engineers. I will let General Graham address the question of the inventory of our flood control infrastructure. General Graham. Representative Bost, as the Assistant Secretary mentioned, communication is absolutely key, with the local levee sponsors through the local district to make sure that we truly understand the status of those levees. So our commitment to you is to ensure that the team is prepared and ready to have the dialogue as Mother Nature votes and puts water up on those levees, and we have a slide or a damage, and then can get that rapidly into a funding package and up here for Congress. Mr. Bost. Well, it kind of goes to my next question. Can you, and I think it is probably for you, General Graham, can you provide an update on the Corps' construction and maintenance backlog and any status update on when we will see a report detailing the projects, because when we did the 2018 WRDA, there was a part of that that asked for a report to be done by the Corps and delivered to us by--it was due in 2020, and we still don't have that. General Graham. Representative Bost, I will check on the status of where that report is and will get back to you. Mr. Bost. Okay. It is vitally important that we work together. And, as was mentioned, I do have three Corps that touch my district, and they all try to do a good job, but sometimes we run into--and this is--what we get is, we get a tremendous amount of these questions prepared by staff. This is my question, though. So, since being in Congress, I have dealt with what was known as the Len Small levee. It was not a Federal levee. It was a State levee. But it was a 5-year levee. When it blew in the holiday flood, which was no holiday, in 2015, it actually started trying to cut through and--actually, Dogtooth Bend in the State of Illinois, that is not just a redneck statement; that is what it is actually called. Okay. And it tried to cut through, and it is still trying to cut through. And I know we are doing a lot with riprap and everything there. They are not going to--they are not bringing the farmland back. It has now all been put in reserve and everything like that. But, if you would, could you keep us informed on what your St. Louis Corps continues to see because originally it wasn't a navigable problem, which is kind of embarrassing when they say that and then all of a sudden a barge ends up in a farmland. So, it is a very, very, very, very important issue to the district. Can't get the farmland back for the people that lost it when that levee gave way, but it is something, if you could, I would like you to keep an eye on. General Graham. Representative Bost, the bank stabilization mission along all of our rivers, in particular, the mighty Mississippi, is critical to us. Dogtooth Bend, we are tracking the stability of that bank. Mr. Bost. Thank you. I yield back. Mr. Collins. Thank you. The gentleman yields back. I now recognize Mr. Larsen for 5 minutes for questions. Mr. Larsen of Washington. Thank you. Thank you, Mr. Chair. Mr. Telle, in the Bipartisan Infrastructure Law, Congress made investments in the Corps, the $17 billion. You discussed approaches for speeding up delivery. There is another approach as well, and that is the robust and consistent funding. The Corps' current construction backlog is close to $100 billion, including $7.5 billion in new projects that we authorized, but there is a roughly 27-percent cut to the Corps' construction account in the budget request. So, it doesn't help close the gap. Can you help us understand this relationship between the construction backlog and the President's proposed budget that does not come close to helping us close that gap? Mr. Telle. Ranking Member Larsen, thank you for the question, and it is an important one. To put a finer point on the point you made, there is $78 billion worth of projects that have been authorized but for which Congress has not yet appropriated funding. There is $44 billion worth of work for which Congress has appropriated money, but the money has not been executed. Of that $44 billion, $12 billion of that is greater than 5 years old. I say that to say that the demand for the Corps' services far outpaces the supply. And, even under the most optimistic projections about the ability of Congress to deliver against that work, it is still going to be small in comparison to the demand. And that is when we have to get smarter. One of the things that I have learned that I am going to be working with Chairman Collins and the rest of the committee on is that--and these are rough numbers--but my preliminary work shows that, for every dollar that Congress appropriates to the Corps of Engineers, only about one-third of it actually goes to build or maintain things. One-third of it goes to land acquisition. One-third of it goes to construction, as I mentioned. And one-third of it goes, for each project, goes to employees within the districts at the Corps of Engineers. And so, one of the things I am going to be working with General Graham and this committee on is better understanding how the unique budget structure of the Corps of Engineers, which includes project-based budgeting, like I said, it is delivering about, in that one-third/one-third/one-third breakdown, how that creates incentives throughout the organization that may or may not align with the incentives of the American taxpayer. And so, I look forward to working with you, whatever the appropriated amount is, to deliver the most for the taxpayer dollar. Mr. Larsen of Washington. All right, thanks. Second, this might be a little easier because we directed the administration, any administration, in WRDA 2024, to obligate 100 percent of the Harbor Maintenance Trust Fund, as well as to the donor and energy transfer ports, 12-percent set-aside, and yet the budget just clearly does not do that, even though we said do that. Can you commit to following the Harbor Maintenance Trust Fund spending allocations of funding targets that are required by law? Mr. Telle. Ranking Member Larsen, we do commit to follow the law. And, as it relates to donor and energy ports, these are projects which this committee has determined contribute more to the Harbor Maintenance Trust Fund than they receive in return. And, while we are focused on making sure that we have access to our ports, this program seeks to provide closer to the shore infrastructure to those ports. I will say that the 2025 work plan and the fiscal year 2026 President's budget does not preclude investments in these activities, even if it doesn't specifically call them out. Mr. Larsen of Washington. Doesn't preclude it, but the law says what to do, so. A little closer to my State, can you help us with the status of the salmon recovery continuing authority program? Mr. Telle. I am sorry, sir, could you repeat the question? Mr. Larsen of Washington. What is the status of the salmon recovery continuing authority program? Mr. Telle. Ranking Member Larsen, I will defer to General Graham on the specifics, but what I can say is we are seeing in the continuing authorities program as we enter the end of the fiscal year and into the next fiscal year, there has been some carryover, meaning that there are balances that exist there. And so, we are working with General Graham's team to ensure that we liquidate as many of those balances as we can efficiently, but there may be some carryover into the next fiscal year. Mr. Larsen of Washington. Rather than have General Graham answer that, we will follow up with him, because I also want to be sure that I understand the WRDA 2024 created a pilot program within the Tribal Partnership Program for five projects in my State that were to be carried out off Tribal lands. Is that pilot program ready? Mr. Telle. I will have to get back to you on how ready it is, but I will say that we respect the role that the Tribes play here and the Tribal Partnership Program, which this committee has placed into law. We look forward to working with you to make sure that gets implemented among the 180 provisions that were included in WRDA 2024. Mr. Larsen of Washington. Just one more thing, Mr. Chair, if I may, just a request. So, I sent earlier, the Democrats sent earlier to your office our priorities for the WRDA 2024 implementation committee, and we did that in February. I understand you weren't there then. Maybe it is still sitting there, but that request, appreciate if you ensure that each of those priorities is implemented swiftly. Mr. Telle. Yes, Mr. Ranking Member. Mr. Larsen of Washington. Thank you, Mr. Chair. Mr. Collins. Thank you. The gentleman yields back. And I recognize Mr. Taylor for 5 minutes for questions. Mr. Taylor. Thank you, Chairman Collins and Ranking Member Wilson, for holding this hearing today, and thank you to our witnesses for taking the time and making the sacrifices necessary to be here to speak to us, and thank you all for your service. As we begin the next WRDA reauthorization, with the Ohio River running along my district, we need to ensure that the Army Corps implements policies that utilize the river's resources to create economic activity in the Appalachian region. My district is essentially all Appalachian. The Ohio River continues to be a vital shipping route, transporting over 200 million tons of cargo yearly. Farmers and businesses rely on the locks and dams along the Ohio River to ship their products with minimal delays. With the ongoing maintenance on the Captain Anthony Meldahl locks and dam, commerce and recreation along the Ohio River could be affected. General, what steps does the Army Corps take when undergoing maintenance like this on locks and dams to ensure that navigation can continue? General Graham. Representative Taylor, thanks. Having grown up in Pittsburgh, at the beginning of the Ohio River, I have a great love and affection for that river system. It is a slack water system. It is all confined by locks and dams, and so, the maintenance of those is absolutely critical. Delighted to see the recapitalization of a lot of those facilities, as well as commitments to the long-term maintenance, particularly on the main stem of the Ohio that you spoke to. We work hand in glove with industry and the Inland Waterways Users Board to make sure that we look well in advance on when we are going to take down any main chambers. The good news on the Ohio River is that there is always a backup chamber with its auxiliary chamber. We understand that that's a great inconvenience to and delay to industry when you go from 1,200- foot down to a 700-foot chamber. So, the key there is to provide the navigation industry a reliable transportation system. It is unscheduled outages that are the bane to their industry, and that is our commitment, is to ideally do away with any unscheduled outages and stay ahead of maintenance. Mr. Taylor. Thank you, General. I have been proud of this administration's priority to ensure that taxpayer dollars are being used effectively. Unfortunately, there was a project in my district that faced significant delays and rising costs because of the actions of a third party and was not the fault of the Army Corps. Delays in vital flood provision and infrastructure can cause potential harm to local communities. General, when the Army Corps faces challenges of contractors and other third parties, what steps do you take to ensure that instances like this are prevented in the future? General Graham. Congressman Taylor, so, we have a tracking system where we basically give a grade on how that contractor performs. And, if the contractor performed unsatisfactorily or if they were unsafe, we don't want to do business with them again. As we see that they are starting to fail in their performance, our commitment is to work hand in glove with them to make them successful. But, if they prove themselves not to be a successful contractor--they can't deliver for us--then we do our best not to work with them again. Mr. Taylor. That makes sense. And, when you are choosing a contractor, does their past performance, your ability---- General Graham [interposing]. Absolutely. Mr. Taylor. Their past performance is taken into account even if it is not necessarily the best price? General Graham. Absolutely. Their past performance is one of the main factors we look at. Mr. Taylor. Okay. In April, the Ohio River reached over 60 feet, the highest in more than 28 years, causing massive flooding in Cincinnati. While this is a rare occurrence, it is imperative that the Federal Government and its agencies prepare for potential floods to protect its citizens and mitigate damage. General, following flooding, how does the Army Corps work with State and local leaders and their flood risk management plan to prepare for potential tragedies in the future? General Graham. Representative Taylor, thank you for that question. Immediately after a storm happens, we have authorities, Public Law 84-99, that allow us to responsively work with local communities to immediately repair that damage where we can. We also have a planning assistance to State continuing authority that allows us to assist them to look at that watershed on what just happened and start to look at options to make that community more resilient to flooding in the future, and then that could spin off into future feasibility studies with us. Mr. Taylor. Thank you both, again, for being here today, and I yield back, Chairman. Mr. Collins. Thank you. The gentleman yields back. I now recognize Mr. Garamendi for 5 minutes for questions. Mr. Garamendi. Thank you, Mr. Chairman. Mr. Telle, sorry about the loss of your dad. And so, I am going to kind of back down here a little bit. But you have an extremely important job, as you know. In your testimony, you said that few Government agencies capture the interests of the American citizens, landowners, communities and States, job creators, like the Corps of Engineers. And you went on to say the Corps supports commercial navigation, flood risks, restoration of aquatic systems, and stewardship of our natural resources. Your words, your task. You have got a very, very important task ahead of you. However, you are faced with a very, very difficult situation, as is the General, one in which the administration has decided to go after the Corps of Engineers and significantly reduce the funding and the staff: 3,000 employees are gone. And, General, you say you can figure out how to do this. I would love to see it, because I would like to see that 2026 work plan. That will tell us how you intend to implement the terrible cuts that have been made by this administration to the Corps of Engineers' critical functions to carry out Assistant Secretary Telle's stated tasks and goals. How are you going to do it? You are looking at a 30-percent reduction in operation and maintenance. You have already heard from several members of this committee, and you will hear even more. Operation and maintenance is flood control. It is also the dredging. And, by the way, you better obey the law, which requires 100 percent of the money available through the programs where we tax incoming shipments; 100 percent of that must be spent for the Harbor Maintenance Fund. Apparently, you are going to have to stretch to do that if you have a 30-percent reduction in O&M. You have a very difficult plan, and apparently you are totally ignoring the 1 year of work done by Democrats and Republicans on this committee putting together the 2024 WRDA plan. It is detail. We are not going to get the detail from you today, because you are not giving us the work plan. But you better get it to us quick, because by the end of this month, we will be dealing with the 2026 budget, and I will guarantee you and anybody else that cares to listen, you will not have my vote for that 2026 work plan unless these issues are addressed, including how you intend to obey the law. WRDA is not just a bunch of words. It is the law. And you are required to carry it out. And, unfortunately, you have been dealt a terrible hand by the President as he carries out the 2025 goals. So, where are we? You are in one serious mess. And I will guarantee you this: this is not one-half of what I intend to lay on both of you when you come back here with that work plan. And it had better carry out the law. One hundred percent harbor maintenance, the programs that were authorized, and the work plan that was developed last year; is it going to be carried out, or where are the cuts going to occur? We do know that, in the early days of this administration, you decided, the administration decided to take it out on the blue States on the west coast, and so $200-plus million of necessary programs, a dam in Washington that had to be replaced will not be upgraded and replaced as a result of a decision that was made to take money away from blue State Washington and a smaller but necessary amount of money from California. Will you restore that? If I give you a few minutes, you would probably say, ``We will do our best.'' Well, your best isn't enough. The law is the law. WRDA is the law of the land, and you are required, this administration is required to carry out the law and not to write their own version of it. So, I will see you next time around, and you better have answers for all of these things. Otherwise, I will unload on you then. This is just a touch. I yield back. Mr. Collins. Thank you. The gentleman yields back. I now recognize Mr. Mann for 5 minutes for questions. Mr. Mann. Thank you, Mr. Chairman. Thank you both for being here today. Thank you for your service to the country. I represent the Big First district of Kansas, which is mostly the western two-thirds of the State of Kansas, except for the area around Wichita. Our water in Kansas comes from, of course, rivers and lakes, but we also have the Ogallala aquifer, which is a big priority for us and our agriculture as well. WRDA 2024 made several commonsense policy reforms to improve project delivery and identify areas of focus for the Corps to maximize public benefits. For Kansas, it is vitally important that the Corps is able to quickly and officially implement guidance and provisions from WRDA 2024 and previous WRDAs. I look forward to hearing from you today on ways Congress can work with you to help to achieve this. Just a handful of questions. First off, how will the Corps work with the EPA and the Trump administration to provide a definition of ``WOTUS'' that adheres to the precedent established in the Sackett decision? I know you referenced that in your testimony, but what is the latest there and when do you anticipate a definition coming out and what does that look like? Mr. Telle. Congressman, thank you for the question, and you have identified a critically important issue. The term ``waters of the United States'' was included as the jurisdiction of the Clean Water Act as it relates to section 404 in 1972, and since that time, there has been a lack of certainty and clarity about what that term means, and the Sackett decision by the Supreme Court in 2023 provides a law of the land that provides as much clarity as we have had since 1972 about that. This is an important issue for farmers and landowners in your State, and I would just say that we have taken action, President Trump's administration has taken action. In March, we issued interim guidance to adhere to the Sackett decision as the Corps of Engineers goes about doing its work in partnership with the EPA. We are in the process of issuing a proposed rule that will permanently enshrine the Sackett decision in the way that the Corps and EPA go about carrying out their responsibilities, and so, I look forward to this action providing clarity and understanding to stakeholders across the country so that we can get to work, we can provide liberty and freedom to Americans as they go about doing what they do best, which is innovate and deliver on the economy. Mr. Mann. I wholeheartedly agree. I appreciate your work and efforts on that. It impacts our farmers, our oil and gas producers, manufacturers, a lot of folks as well, so, thank you. Second question, what is the status of implementing subtitle B of WRDA 2024 to elevate water supply as a primary mission of the Corps? Mr. Telle. Thank you for the question, sir. As you identify, the three core missions of the U.S. Army Corps of Engineers have been navigation, flood risk mitigation, and aquatic ecosystem restoration. Water supply winds up being a very important, especially in the western part of our country, an important part of the Corps' mission, and we have to work very closely with our partners at the Bureau of Reclamation within the States to make sure that we are keeping a close eye on water supply as we think about ensuring that communities don't experience floods and that we can quite often respond to natural disasters. And so, water supply is already an important part of what General Graham considers as he is allocating resources that are held in reservoirs, and it is something that we will continue. We have been focused on and will continue to focus on in light of WRDA 2024. Mr. Mann. Great. And then last question, what is the update on the Corps' construction and maintenance backlog? Are there specific categories or projects contributing to the backlog more than others? Mr. Telle. Congressman, I ran through the numbers of the authorized but unappropriated and appropriated but unexpended, and I would say that all categories, feasibility studies, construction, project engineering and design, construction, and maintenance all have issues, and these things take far too long. They cost far too much. And I am committed to working with this committee and with General Graham and his team at the Corps to get at that problem. We can deliver more flood control, more water supply, more navigation for the country for less money and more quickly if we work closely together, and so, I am committed to that, sir. Mr. Mann. I agree. Thank you both, again, for being here, and I yield back the balance of my time. Mr. Collins. Thank you. The gentleman yields back, and I recognize Mr. Ryan for 5 minutes for questions. Mr. Ryan. Thank you, Mr. Chair. Thank you both for being here. Mr. Telle, I want to join in expressing condolences not just from me, but from my constituents, for your loss. I want to take the few minutes I have to highlight my district and an important priority in my community, which is experiencing a major drinking water crisis and ask for your help and your commitment to work with me on that, which you have already been doing a great effect. The village of Kiryas Joel is one of the youngest and fastest growing communities in the Nation. It is also the largest municipality in my district, and the average size of family there is 5.37 people, which is double the national average. The village has experienced continued rapid population growth since 1990. It has 4X increased as the community has grown, which is a great thing. Because of this, the village has been working really hard to ensure it has infrastructure it needs across the board to support this growth. In particular, though, the current water infrastructure is at an incredibly dangerous point where they have literally had to truck in water at peak demand points because they just have not been able to keep up, and to be clear, they have a great plan that they have been executing for decades now. It is just, as we all know, things move too slow, and as that escalates, they are in a critical situation, so that is why we are specifically asking your help. I know this is something that the Corps has taken on in moments of critical need. Specifically, Kiryas Joel has been working on the fifth and final component of a multiphase project more than 20 years in the making called the Catskill aqueduct connection project. It basically runs a 13-mile pipeline from the Catskill aqueduct, which is the water supply for New York City, actually, and connects this community into that supply. It is a great approach and idea that is very synergistic for not only Kiryas Joel, but many other surrounding communities. The current and final stage of the project is a water filtration and treatment plant that will treat around 2 million gallons of water per day. I have been working really close with the village on the project since I have been in office. We got an initial million dollars in community project funding, but we certainly need a lot more. The project was included in section 219 of the environmental infrastructure project going back to 2007, and then in 2024, I was able to 5X that to $25 million authorized with the help of my colleagues on the committee. General Graham, I want to commend you and your team. Colonel Young from the New York District has been phenomenal, and the whole team. They just did a site visit with myself and the village leadership earlier this year. We were able to show them the project. They spent several hours with us and committed at a broad level to continue to support the project working with the State, New York State, as well. So, I just want to flag that for you both, ask your help, and specifically ask if General Graham, and of course we would invite you as well, Assistant Secretary, if you would sit with me to just talk a little bit more about this project to figure out how we can get it moving, because we are just--I mean, we are really running out of time and just would ask your help on that and any thoughts you have on that starting with you, General Graham. General Graham. Representative Ryan, we are certainly tracking the aqueduct connection that the village is working to make, and subject to funding on the 219 program, we're prepared to assist them. Mr. Telle. Congressman, happy to visit with you at any point and learn more about this project and see how we can be of help to you. Mr. Ryan. Appreciate that. We would love to follow up with you on that and understand amidst all the priorities that you all have on your priorities list what we can be doing to make sure that this is seen as it is, because it is reaching an existential situation. That is the main question I have, and again, I just want to, as a former Army guy, it is good to have Army folks in this committee as well. Appreciate the service you are both doing for our Nation, and I yield back, Mr. Chair. Mr. Collins. Thank you. The gentleman yields back, and I now recognize Mr. Fong for 5 minutes for questions. Mr. Fong. Thank you, Mr. Chair. Thank you both for being here. To the Assistant Secretary, my condolences to you and your family on your loss. I wanted to also move on to thanking the President for his leadership on California water. We haven't had a President focus on our water policies in California in a very long time, and the fact that he signed two Executive orders, one on the first day he was inaugurated, certainly signifies the importance he takes to our needs in California. President Trump's Executive Order titled ``Emergency Measures To Provide Water Resources in California'' directs Federal agencies like the Army Corps to take emergency measures and to streamline policies constricting water infrastructure construction in California while maximizing water delivery. The Redbank and Fancher Creek Dams that service my district are authorized as single purpose flood control facilities. Army Corps studies will analyze modifying existing infrastructure like these that increase water storage that will directly be used and manage groundwater recharge in California. I wanted to ask both of you, maybe first to the Assistant Secretary, how does the Army Corps plan to streamline his policies to prioritize review and approval of water projects like Redbank and Fancher Creek which will meaningfully impact water supply in agricultural regions like my district? Mr. Telle. Congressman Fong, thank you for the question, and I would just agree with you wholeheartedly about President Trump's commitment to water supply in California. We are very fortunate to have a President who is so focused on water issues in your State and throughout the country, and I would also compliment the California congressional delegation, Congressman LaMalfa and Congressman Kiley on this committee, for your expertise on this issue that is very important to your State. As you have conveyed to me and your colleagues have conveyed to me, we can make the pie bigger in terms of water supply in California if we are willing to do what it takes to optimize the use of the reservoirs there to keep this precious resource available. That is in the form of water control manuals using forecast-informed reservoir operations. These are all activities that we are focused on throughout your State, and if we increase that water supply in California, we are going to be able to deliver on the needs of farmers in your State, the municipalities in your State, and when disaster strikes, we are going to have more water to be responsive to it. And so, I look forward to working with you and Members of the California delegation under President Trump's leadership to deliver on that hope. Mr. Fong. Thank you. Also, thank you for that, and I want to mention two other projects. As you know, for several years, my community has been working with the Corps to initiate a feasibility study to raise Pine Flat Dam in my district. We talked about that as well when you were generous enough to offer some time. This project has brought bipartisan support since it adds critical flood protection needed to prevent the kind of devastation we saw in the Central Valley during the flooding events of 2023. Look forward to working with you on how we can commence work on some of the requirements for feasibility determinations so that we can move through the process quicker. And then the Success Reservoir enlargement project provides, again, more significant flood protection for our communities and farms in my district. Once completed, this project will more than double flood protection creating over 28,000 acre-feet of new water storage. There is $15 million remaining to close out this major project, so, certainly look forward to the partnership to funding this project, complete the Lake Success project to ensure that this project becomes operational as quickly as possible. I do want to end my opportunity to chat with you both about the use of advanced forecasting technologies like ASO and FIRO that allows us to better map and predict snowpack and watershed levels. How does the Corps plan to incorporate a greater use of available technology to better manage watersheds, snowpack so that our existing infrastructure can better protect communities from floods while also increasing water supply levels? That goes to either one of you. Mr. Telle. Congressman Fong, you have identified a critical issue, which is to optimize the use of our existing infrastructure. We are able to use things like forecast- informed reservoir operations to update water control manuals that may not have been updated since the 1970s. We can use all of the sensing and data capabilities that we have developed in the interim to store more water, provide more water, take smarter risks when necessary without really spending a single dollar on new infrastructure. So, you have identified a critical area where we can do more and better, and I will defer to General Graham on any of the specifics if you would like to---- General Graham [interrupting]. I cannot really say much more than that. Secretary Telle. Bringing the maximum value we can out of all of the projects around the Central Valley is absolutely key, and so, we are delighted to see Lake Mendocino and its new water control manual coming online this month, and that is the first of the FIRO, forecast-informed reservoir operations, water control manuals that we will be able to put into operation, and we are continuing to work on the additional ones. Mr. Fong. Thank you. I have run out of time, but water is life for us in the Central Valley in California. We are the food production capital of our State, and I look forward to partnering with both of you. Thank you. I yield back. Mr. Collins. The gentleman yields back. I now recognize Mr. Pappas for 5 minutes for questions. Mr. Pappas. Thanks very much, Mr. Chairman, thanks to you and the ranking member for holding this session. I want to thank our witnesses, Assistant Secretary Telle and Lieutenant General Graham. We appreciate all your hard work, and I can attest to the significance of the Corps in terms of New Hampshire and projects that we have seen undertaken over the last several years. We are really grateful for your attention to a number of initiatives. I wanted to build on what the chairman was asking you about, Mr. Assistant Secretary, around recreation, an issue that is top of mind to a lot of folks in New Hampshire, where our communities are really rooted in access to the wilderness and the outdoors. As you know, the Army Corps has been subject to a hiring freeze imposed by the administration. It has impacted the New England District recreation areas. It has left recreation areas in New Hampshire unable to hire summer rangers at all who serve in essential roles and keep those areas open and safe and accessible for individuals and families to enjoy. Without summer rangers, recreation areas in New Hampshire where people boat, swim, fish, and hike experienced reduced hours, limited access to facilities, and significantly reduced services throughout this past summer. So, I share those concerns, and I would love to hear a little bit more about an action plan to address this, but I just want to add that it is not just the summer months. It is all year round in New Hampshire in terms of our outdoor recreation opportunities, and it is connected to our economy. The outdoor economy represents a major sector in New Hampshire, employs tens of thousands of people. We are among the top 10 States nationwide in terms of proportion of GDP that is generated based on outdoor recreation. So, whether it's activities in the summer, access to lakes and ponds in the winter for ice fishing, hiking, and hunting, this goes 365 days throughout the year, so I am wondering if you can expand a little bit more on access to outdoor recreation, how we can get more people out there to make sure that we are not compromising not only access, but economic opportunities, and I will just add that I think the notion that this could somehow be shifted to other agencies or to State and local taxpayers, that is not something that folks in New Hampshire I know would support. So, I would love to hear a little bit more about how we can improve this, and I think people at the local level have great urgency around wanting to see some action. Mr. Telle. Congressman, thank you for the question and thank you for astutely pointing out that the Corps of Engineers facilities do--many of them do attract visitors throughout the year. With regard to the workforce that supports the recreational activities of the Corps of Engineers, this is an area that the Trump administration identified very early on as a challenge and instituted a program to hire these folks as quickly as possible, and we have already made significant progress against that goal. We are tracking it every single day in cooperation with General Graham, and it is something that we intend to have fixed. We already addressed over the course of this summer heading into the winter months and into next summer. I am confident that we will have a workforce that meets the needs of the American public as it relates to using Corps of Engineers facilities for recreation. Mr. Pappas. Well, we are hoping we can continue to communicate with you on this. It is important, and where there are exemptions needed from the hiring freeze, I think we absolutely should be looking for maximum capabilities from the Corps to be able to fill these positions. Mr. Telle. Congressman, we are aggressively hiring today against these needs and look forward to working with you and giving you more information about that. Mr. Pappas. Thank you. Additional question for you, Mr. Assistant Secretary. A key priority of mine in the last WRDA was language encouraging the Secretary to coordinate with apprenticeship programs when conducting corrosion prevention activities as well as the use of industry recognized standards and best practices. This will enhance the quality and effectiveness of corrosion prevention measures through certified training programs, ensuring the integrity of our infrastructure over the long term, so I was pleased with its inclusion in the legislation. I am wondering if you can talk about any coordination with apprenticeship programs, whether it is on corrosion prevention or other things that will help support the needs of our infrastructure. Mr. Telle. Congressman, corrosion is an important issue when it comes to our Nation's water infrastructure. When water and metal and oxygen touch, corrosion occurs, and much of our infrastructure is far too old, and so, anything we can do to get against the corrosion challenge on our Nation's infrastructure, locks and dams, and other infrastructure related to the United States Army Corps of Engineers' mission is something we ought to take a close look at, and I congratulate you on your leadership in that area. Mr. Pappas. Thank you. There are apprenticeships out there that are the gold standard that ensure that workers are skilled and that they are using best practices, so I hope that the Corps can continue to benefit from those types of programs. With that, I yield back. Mr. Collins. Thank you. The gentleman yields back. I now recognize Mr. Mast for 5 minutes for questions. Mr. Mast. Thank you, Chairman. Appreciate it. Secretary, General, nice to see you both. You guys are a pretty new team. Working together, getting along well? Secretary, appreciate you coming in the other day. It was a great conversation. Appreciate your work on the issues. I know you bring a wealth of knowledge having been working for a number of Senators. Now you are getting your Ph.D. and everything, but I know you have had a lot of exposure to everything, so, I am glad to see you both in here. I just want to have a little conversation about something I frequently do, Lake Okeechobee. It is the biggest thing that affects me as it relates to the U.S. Army Corps of Engineers, and I would frame the conversation in this way. Corps of Engineers does not like to deal with issues of, quote, ``water quality,'' but water quality affects us all. You guys have to move waters of different levels of quality. You have to manage water standards in different parts for the outlets of Lake Okeechobee. The water quality standards for what goes south into the Everglades are not what the east and west coasts of Florida get to have in terms of eight parts per billion. Eight parts per billion is the standard that the EPA set for what is toxic algal blooms. Ten parts per billion for water going down to the Everglades, for phosphorous. We don't have those kinds of standards to the east and west, but we have a lot of toxic algal blooms on Lake Okeechobee. That affects your people. The water quality affects your people. I don't know, have either of you had to be on top of the Port Mayaca Lock and Dam with algal blooms measuring 100, 200, 300 parts per billion microcystin? Have you done that yet? Mr. Telle. I haven't had a chance to do that yet. Mr. Mast. General? General Graham. So, Congressman Mast, I think the last time I met you was out in the field with your son at Port Mayaca when there was an algal bloom going on. Mr. Mast. So, you know what that is like. General Graham. Absolutely. I think your son walked out of the car and said, ``Dad, this place stinks,'' and he was absolutely right. Mr. Mast. And so, the point is that quality, your people have to stand on that how many hours a day? Eight, ten hours a day breathing those things in. It is serious. And just as much as it is serious for your people in uniform out there working daily, weekly, monthly on top of that, it is the same level of seriousness for our people that have that discharge to them. So, the point of the conversation I just want to have for a couple minutes, you guys are a new team coming in. What do you feel like we can do to protect my people on the east coast that get that dumped on them when we don't receive any benefits? The people on the west coast that get them dumped on them, even though they want a minimum level of water flowing to them because they have a natural connection. We have an unnatural connection. And your people that have to sit on top of this and work every day, what can we do to work on this? Mr. Telle. Congressman Mast, thank you for being on top of this issue. You have helped me as I have gotten up to speed on this issue. I have been down to Lake Okeechobee already. You have been a tireless advocate for your constituents along the St. Lucie River. The Corps of Engineers under General Graham's leadership has already taken action to update the water control manual of Lake Okeechobee to ensure that we are not having unnecessary discharges into the St. Lucie River, the Caloosahatchee River. You have been at the forefront of making that happen. There is still more that we can do to ensure that we provide for the Everglades restoration project and we provide for flood control throughout central and south Florida without negatively affecting your constituents, and so, I look forward to working on this with you. Mr. Mast. You as well. Mr. Telle. You have been an incredible advocate for the interest of your constituents. Mr. Mast. Look forward to working with you also. General, anything to---- General Graham [interrupting]. One piece I would add, Congressman Mast. I know you have been a great support of this is research and development that we can do when the harmful algal blooms erupt, that we have a tool to combat that. South Florida Water Management District has some pretty good tools that we have used. We will continue that research and development. At the end of the day, the root cause of this is the nutrients that are causing this to begin with, and we will work hand in glove with the State of Florida to improve that. Mr. Mast. And the water quality standards that I started to speak about, those are related to nutrients. That is not even related to are we moving toxic pollutants like microcystin that the EPA says, hey, if you are a human being, don't come in contact with this at 8 parts per billion, much less 800 parts per billion, right? So, I hope there is a place that we can work together to rightsize that there are not different water quality standards for water that goes south than the water that comes to these epicenters of people across the State. It doesn't make sense. I am sure you could agree, General, it wouldn't make sense to have a water quality standard for the water that goes to one housing development, Normandy at Fort Bragg, then goes to a different housing development somewhere else on Fort Bragg. It wouldn't make any sense. That is basically what we have going on with Lake Okeechobee, and it is those inputs of those nutrients that allow our coastal estuaries that are otherwise Bahama blue to be turned into something that looks like your uniforms, which are great uniforms, but it is not how we want our water to look. So, with that, my time is about expired. I look forward to working with both of you. Mr. Collins. Thank you. The gentleman yields back. I now recognize Ms. Friedman for 5 minutes of questions. Ms. Friedman. Thank you very much. Mr. Telle, my condolences on your loss. I don't need to tell anyone here today how important the WRDA funded projects are. We have heard about a lot of them today, and I wanted to highlight the need to continue to invest in water resource projects that reduce flood and storm damage, support water supply and drought resiliency, and restore ecosystems by focusing on a very important project in my district. We have a project that was authorized under the most recent WRDA bill, the L.A. River restoration project, and if you are listening to this, you might think you don't know the L.A. River, but you do, because you saw ``Grease'' and you saw the cars racing in what may have looked like a giant drainage ditch, but that is actually the L.A. River, which in recent years has really captured the imagination of the public as we think about what that river could be to Los Angeles. In fact, I toured this project recently with Ranking Member Larsen, and he was amazed at what has already been accomplished and how many people midweek are using the bike paths that now go along a lot of the river and talking to him about the parks that are going to be created and the areas, some of which are fairly blighted around the L.A. River, but looking forward to a complete economic revitalization as we reclaim this amenity. As you know, this project is a major investment that requires close collaboration between the city of L.A. and the Corps, and the Corps has been working with L.A. for a number of years on the L.A. River. Now, it is my understanding that the L.A. River ecosystem restoration project will require a section 902 adjustment along with a Post-Authorization Change Report since project costs have naturally increased. Congressional authorization by our WRDA is needed to increase authorization of appropriations for this project which has been undergoing for a number of years. In order to increase authorization of appropriations, a complete PACR is needed, and it is my understanding that the current targeted date for completion of this PACR is July of 2026. My constituents are relying on this project being completed, and to be clear, this project does go through part of my district. And I am worried that any delay in completion of the PACR won't allow the committee to complete the review in time for WRDA in 2026, leaving our taxpayers to pick up the tab at a time when we are already overburdened because of the L.A. fires nearby in the county. So, I don't know which of you wants to answer this question, but my question is, what we can do to speed up completion of the PACR process to ensure that it is completed in time for the committee to consider ahead of next year's WRDA, and how can I be helpful in that process? Mr. Telle. Congresswoman, thank you for the question, and I will just say before I turn it over to General Graham, Los Angeles is one America's great cities, and it is going to be on the world stage soon. It is important that the Corps of Engineers do what it can to support the citizens of Los Angeles and the Greater Los Angeles area, including with the L.A. River, which is an important part of that ecosystem. So I look forward to working with you and learning more about this project and hopefully getting out to L.A. very soon. General Graham. General Graham. We are committed to deliver that PACR to this committee in time for WRDA 2026. The cutoff point I usually set for the districts is the end of May. Never know when the next WRDA might get put together, so, I am a little concerned that the district right now plans to finish that in July, and we are working with the district to see, one, to make sure that we maintain it on track to deliver it by July, but I would like to see it moved towards the end of May, and that, right now, is our goal. We are also working collaboratively with the County of Los Angeles Department of Public Works for the entire system. This committee has authorized some deauthorization or transfer of some of the features of the entire L.A. County Drainage District and there is no better partner we have than the L.A. County DPW and Mark Pestrella, so, we are absolutely committed to continue to work collaboratively with them to make sure that that system provides tremendous protection to your citizens. Ms. Friedman. Thank you. We have heard that there has been good coordination. I really appreciate that. And along with the L.A. River project, there are several bridges that are going to be built, because we have got parks like Griffith Park and Elysian Park where right now it is very hard for people on the other side of the river to access those amenities, and these are some park poor areas, and I know that they have been working closely with the Corps on making sure that they can expedite or move the approvals of those bridges through. But, Mr. Telle, I would love for you to come to Los Angeles. I would love to walk you through some of this project area and show you how it is going to take what is already a great city but really move it up to the next level, and this is a major piece of infrastructure for Los Angeles to help with flood control, but also bring a lot more recreation to Los Angeles, so, thank you. Mr. Telle. Thank you. Mr. Collins. Thank you. The gentlelady yields back, and I recognize Mr. Onder for 5 minutes for questions. Dr. Onder. Thank you, Mr. Chairman, and thank you to our witnesses today. Back home in my district in Missouri, I hear the same concerns time and again from farmers and river communities, local officials. They depend on reliable levees, timely dredging, and flood protection to keep their families, their lands, and their neighborhoods safe. Yet, too often, we see these projects bogged down by multiyear studies, by shifting regulatory definitions and ballooning costs, but the floodwaters don't wait for Washington's bureaucracy. A good example is the Lower Missouri River Basin flood risk and resiliency study. It was authorized under WRDA, yet the interim report wasn't expected until December 2023, and its final completion is not scheduled until March of 2027. This means the region won't experience tangible improvement until nearly 8 years after authorization. In the meantime, the rivers may overtop flawed levees and my constituents pay the price in anxiety, risk, and economic damage. That is why today's hearing is so important: translating WRDA mandates into timely action, minimizing bureaucratic drag, restoring discipline and accountability to protect local communities. Despite Congress' clear direction, bureaucracy continues to slow things down, and I would like to explore opportunities to make a difference here. Secretary Telle, the Lower Mississippi River Basin flood risk and resiliency study highlights how nearly 8 years can pass between authorization and real results. What specific reforms are you implementing to cut down on these study timelines and deliver protections to our communities faster? Mr. Telle. Congressman, thank you for the question. You are absolutely right. It is unacceptable that these projects take so long and cost so much. I think we have an opportunity under the leadership of Chairman Collins and President Trump to get after this program in a way that will help the entire country, and especially areas like yours that have multiple big rivers all coming together. In terms of specific reforms, it is important to me that the United States Army Corps of Engineers is an organization that from my office to the headquarters to the 9 divisions to the 39 districts, that we deliver policies and standards that you can count on, whether you are in the St. Louis District or the Kansas City District, and I think that that's something that General Graham and I have worked diligently on. Another one that I mentioned already is looking at the project-based budgeting and what that means in terms of the incentives it creates throughout the system. The United States Army Corps of Engineers is virtually the only agency within the Federal Government that budgets in this manner, and there are advantages to budgeting that way, but there are also potential perverse incentives in terms of delivering low cost and quickly. And so, I look forward to working with you and with Chairman Collins, Ranking Member Wilson to really explore how we can get serious about reducing schedule and cost on these projects. The American public can't wait for, like you said, for us here in Washington, and I think the benefit of harmony across the Corps of Engineers enterprise is perhaps we can reduce the wait times at the different levels of paperwork. And I know you agree with this, sir, which is that you expect the Corps of Engineers to build infrastructure, not build paperwork, and I am committed to helping work through that with General Graham's partnership. Dr. Onder. You have committed to reducing regulatory burdens and aligning with the Sackett decision. When will we see clear final definition of ``waters of the U.S.'' that removes uncertainty for landowners and farmers? Mr. Telle. Thank you, sir. As I mentioned earlier, we have already published interim guidance that is implementing that decision now, and one of the challenges is making sure that all of our districts all the way down the line understand that guidance and are implementing it, so if you hear of anybody who is not implementing the Sackett decision within your districts, please let us know. In the meantime, we are also expecting by the end of this year to publish a proposed rule that would provide permanent clarity in response to the Sackett decision and give much needed relief to Americans who are experiencing the regulatory burden of Washington. Dr. Onder. I appreciate it. Thank you. I yield back. Mr. Collins. Thank you. The gentleman yields back. I now recognize Mr. Figures for 5 minutes for questions. Mr. Figures. Thank you, Mr. Chairman. Thank you both for being here today and sitting through this grilling, as they call it, and Mr. Telle, I want to extend my condolences to you on your father. I lost my father, it will be 29 years ago in a couple days here, in 3 days. But I want to thank you for still being here and showing up despite that, because I know it is tough, man, so I appreciate that. I want to start by acknowledging that I have the proud honor of representing the area that will soon be the deepest port in the gulf from Panama as I understand it, from the Panama Canal all the way up to Charleston, South Carolina. That is the Port of Mobile. When they are done with the dredging here in a few weeks, we keep hearing the date get shifted and shifted, but nevertheless, they are fast approaching completion of that. And the Corps, I want to thank you guys for your cooperation in getting us to that point, and I also want to extend an invitation to both of you to come down to celebrate our new distinction, which will incidentally be on what would have been my father's 78th birthday on October 13th. If either of you are available, we would love to have you down in Mobile to celebrate that. It is a significant accomplishment for a lot of parties involved, and we are really looking forward to the impact that that's going to have in the future. That being said, 24-percent funding cuts makes it tough to ensure that we are doing what we need to do to keep that port in a position that is not like my colleague from Georgia was mentioning earlier and having issues with the regular maintenance dredging, and so, can you guys discuss what impact the budget proposal would have on your ability to be able to sufficiently perform the maintenance dredging that is necessary to keep the Port of Mobile open at its new depth? Mr. Telle. Congressman, thank you for your advocacy for that important project, and I hope I am not giving away too much about my schedule here, but I do plan to be in Mobile and Baldwin Counties on the 14th of October, so, we will see about the 13th. Mr. Figures. We don't worry about Baldwin County. That's [inaudible]. [Laughter.] Mr. Telle. Okay. Yes, sir. Look, General Graham and I are committed to ensure that we perform critical maintenance of our dams and our ports, critical ports like the Port of Mobile, with the resources contained within the President's budget request, and so, we are working hard to make sure that happens. As I have said multiple times during this hearing, our ability to compete in the 21st century is dependent on our ability to have port facilities that allow us to open up our country, our coastal areas, and our inland areas to the global commerce. And dredging and maintenance is part of that, and so, you have my commitment that we are going to do everything we can to maintain our ports, keep our channels dredged, and open America in important places like Mobile to the rest of the world. Mr. Figures. I appreciate that. I also encourage you to come down and visit it, because I am pretty sure we have the newest Army Corps of Engineers facility in the Nation, so, you should also take a look at that. And I have had the privilege to meet the newly installed Colonel Kelcey Shaw and have full confidence in his ability. Very impressive guy. He is an alumni of Tuskegee University, which is also in the district, and so, looking forward to working with him over the next several years. Beneficial use of the dredging material is a huge deal back home in Mobile. As you know, your predecessor issued a directive, I think, requiring 70 percent of dredging sediment to be used for beneficial use. This is something we want to ensure can continue to happen. These are sentiments that are echoed by my colleague over in the Senate, Senator Britt. This is a very important issue to make sure that we are exploring all beneficial use options for the sediment dredging material for wildlife reasons, for recreation reasons, and just general good housekeeping reasons, and so, do we still have that commitment from you guys to enforce that threshold and do everything you can to ensure that the sediment that is being dredged out of these ports is being prioritized for beneficial use? Mr. Telle. Congressman, I will say without commenting on the 70-percent threshold as I will need to look into that, but I will just say that when we can use dredge material for beneficial use, whether it is restoring a shoreline or restoring barrier islands, or renourishing beaches, that's a win-win for the taxpayers and for the ecosystem. And so, in general, I would just say that the use of beneficial use material as we call it within the Corps of Engineers is important, and you are correct that Senator Britt has been advocating to me the importance of ensuring that the dredge material from the Mobile Port channel is used in a way that is a benefit to Alabamians. Mr. Figures. Thank you. We look forward to seeing you guys on October 13th, and I yield back. Mr. Collins. Thank you. The gentleman yields back, and I recognize Mr. Patronis for 5 minutes for questions. Mr. Patronis. Gentlemen, good morning. Thank you for being here. My district is northwest Florida. Secretary, you know where that is. You know where the Gulf of America is. Even though I am the lowest ranking Member, I have been in Government a long time, and I have dealt with the Corps on a lot of issues, some of which are totally revolutionary, can't believe we are able to make some of these transformational permits in the case of a real significant out-of-the-box thinking project that exists in the State of Florida, and then sometimes I scratch my head about why in the hell is the Corps even looking into what I am asking you all to look into. And I am not saying this is something that you are going to fix today, but I am going to--I am a big believer in going through the chain of command. I am a rule follower. You know what? And so, now I am going to look past you. I am going to look at your staff, because I am not going to ask for the Secretary or the general's phone number in this public meeting, but I will be happy to give you mine, but I am looking at your staff behind and I am going to ask you in the next 30 days to come schedule an appointment with my office so we can go through some permits. I am not going to ask you for a single dollar. I am not going to ask you to spend a single bit of your resources that are so important to everything else you have heard today, but I am going to tell you that the most precious thing that we have in life is time. I would love to have more time with my family. I would love to have more time enjoying life. But when things get clogged up in your system, that is eliminating precious access to time and resources that, I'm sorry, I just can't tolerate. I am going to give you two examples of issues. I am not going to use names, we will talk about this when your team shows up. But I have got a land swap happening that has been waiting for years to take place. Every time a land swap takes place, we have to get a new appraisal. After we get a new appraisal, appraisals are perishable. They are only valuable for so long a period of time. This particular land swap has been approved at the district, in Atlanta, immediate headquarters, and DC headquarters, yet it cannot get approved and the appraisals continue to get neglected and the appraisals have to start all over again, so we will go into details of that when your staff shows up. The second, again, scratching my head. I don't know why I am even talking to you all about this. Okay? I have got a constituent who has been waiting more than a year to put in a floating dock at an existing marina. Why is this even an interest of the Corps of Engineers? It just scratches my head. I think one of the greatest things we have got is the Gulf of America, I want people to enjoy it, I want people to spend money and enjoy it with their family, I want those tourists to come down and enjoy northwest Florida, but why does the Corps even care about an 80-foot floating dock? It makes no sense. What are we going to have? Maybe two pylons in the water, maybe four pylons on an 80-foot, maybe six pylons. Okay? DEP has approved it, Florida Department of Environmental Protection has already approved it. They care about the sea grasses. They do all that. Why does the Corps care? Again, these are things that you all have got bigger fish to fry. Why are we even talking to you about this, and why couldn't it be off your desk already? So, I want to work on these things. Like I said, I want to praise you, I want to support you, I want to give you your resources, but also I want to get these problem children that are buried in somebody's desk, because I know you get overwhelmed with some of the types of things that shouldn't be there, just like an 80-foot floating dock, and I just want to make your life a little bit easier. I told people, I was back in Florida, I said, the Florida Department of Environmental Protection is the greatest freedom agency in the State of Florida. It can take your freedom away or it can give you freedom. And you all are in a very similar category. I had somebody the other day that I was talking to in Jacksonville and they were going through some permitting on some dredging. I said, do you want me to reach out to the Corps for you? No, no, no, we have got a great relationship with the Corps, they treat us great, we are very happy. Again, where praise is due, I am going to share it with you, and it was great hearing that. But then I hear other folks just like these here that make no sense whatsoever. And, again, I am not thinking this is somebody's personal agenda, but you know what? I have seen people at DEP that just--I think it is their mission in life just to make sure that nothing ever gets out of their office. And unfortunately, we are humans and sometimes we just have those agendas sometimes embedded in us. So, I don't really have a lot to ask you, other than thank you for your service. I look forward to working with you, and I hope to be an advocate for the good that you all do. Mr. Chairman, I yield. Mr. Collins. Thank you. The gentleman yields back. I now recognize Ms. Pou for 5 minutes for questions. Ms. Pou. Thank you. Thank you, Mr. Chairman. First, let me begin by saying that I absolutely want to thank Assistant Secretary Telle and Lieutenant General Graham for joining us today. Thank you so very much, gentlemen. Last week, I met with mayors from across my district. The issue I heard over and over again was concern with the water management, so I wanted to just address something. The U.S. Army Corps of Engineers has been a lifeline for our district which faces repeated severe flooding. I am grateful to the Army Corps for recently meeting with our local officials in Clifton to discuss a critical mitigation project study to address the chronic flooding from the Third River. I want to work with each and every one of you, but I want to work with you to ensure that this project gets the resources that it needs under the continuing authorities program to advance to the next phase. I also look forward to reviewing the results of the New York Harbor and tributaries coastal storm risk management study to better prevent devastating losses from hurricanes. Information like this is sorely needed to support areas like my district that are at risk from superstorms. In our district, the Lower Saddle River Basin has faced repeated flooding for decades impacting at least eight cities and towns, including Lodi, Garfield, and in response, Congress authorized the Lower Saddle River flood protection project, ladies and gentlemen, back in 1986. Now, that is almost 40 years, 39 plus, literally 40 years ago. However, the basin contains known contaminated sites, areas with heavy pollution. The presence of these sites means that if the Army Corps begins construction, they risk the legal and financial consequences as well as decades of bureaucratic inaction and stalled progress. So to the both of you, please help me to understand, and I understand that the Army Corps has been involved with contamination radiation at other projects. How does that presence of that contamination impact the Corps' ability to complete necessary work at this particular site? Mr. Telle. Congresswoman, thank you for bringing these issues to our attention. One of the things that I didn't fully appreciate until I was confirmed for this role was the work that General Graham's team does falls into two categories that you are talking about. If it's a former defense site, it falls under the FUDS program, which is under the military program side of General Graham's work, and if it's a former Department of Energy site, it falls under the FUSRAP program, which is under the Civil Works portion of General Graham's portfolio, and so, I will defer to him to make sure we fully understand in the case of your area which it is. Ms. Pou. Lieutenant General, let me just ask, though, as you are thinking about answering the question, I specifically would like to have you speak with the contaminated areas of the Lower Saddle River and what steps are needed to get that project off the ground. Since we have been literally waiting 40 years, I don't want to have to wait another 40 years. General Graham. Representative Pou, thank you again for that question, and it is a big challenge on many of our waterways. They were used as open sewers and just disposal areas in the past, and we do a lot of cleanup work as the Assistant Secretary mentioned. We also do some cleanup work under the Environmental Protection Agency. I think probably in this case, and we will check on the specifics, it is we are working to find out who put that contamination in there and hold them responsible. Understand that that is usually where this gets stuck is finding that out. And then where that is not feasible, then it will go into the EPA program, and oftentimes they will hire us. They will bring us in to then do the actual engineering and cleanup work. And we will get back with you on the exact status of this particular issue, and we will collaboratively work with you to see if we can get a path forward. WRDA 1986 was a long time ago. Ms. Pou. Thank you. Thank you, Mr. Chairman. I know my time is up, so I really appreciate it. I yield back. Thank you, gentlemen. Mr. Collins. Thank you. The gentlelady yields back. I now recognize Mr. Hurd for 5 minutes for questions. Mr. Hurd of Colorado. Thank you, Mr. Chairman. Gentlemen, good morning. Thanks for being here. I represent Colorado's Third District, which is--Colorado's a headwater State. We are the only State in the continental U.S. where all the water flows out. And the Colorado River Basin is an important issue not only for the constituents that I represent, but also for the 40 million-plus citizens who live in the Colorado River Basin and our down basin cousins as well. This year has been a very difficult year in Colorado when it comes to snowpack and moisture, and I am concerned what that means for us in Colorado as well as our fellow Colorado River Basin States. I understand that section 208 of WRDA directs the Secretary of the Army to assess potential applications of forecast-informed reservoir operations in the Colorado River Basin, and provided there are sufficient resources to do so, the Secretary can facilitate smarter water storage and release programs. Mr. Telle and General Graham, can you speak about the implementation of this provision, potential implementation of this provision, and have there been any lessons learned from forecast-informed reservoir operations in the past in terms of how we can be better prepared and more resilient when it comes to drought related challenges? Mr. Telle. Congressman, thank you for the question, and you and other of your colleagues have pointed out the importance of forecast-informed reservoir operations and other technology enabled methods to make the best use of scarce water resources. The Colorado River winds up being the source of water for a great portion of the Southwestern United States, and I think the disputes between the States over the Colorado River water supply are historic and challenging, and so that speaks to the importance of using every tool in our toolkit to better optimize the way that we manage the system, and General Graham is on top of that, and I would defer to him in terms of implementation of section 208 as it relates to this specific basin. General Graham. Representative Hurd, taking the lessons we are learning right now on forecast-informed reservoir operations, putting those into practice with water control manuals out in California and Lake Mendocino, we certainly want to continue to deploy that technology throughout the country. You say, well, maybe that is only for California; we can see the atmospheric rivers coming. But I talked to some of the scientists and engineers before they even were talking--places like New Jersey might be capable of it. That, as the Assistant Secretary has said, his guidance is to make sure wringing every ounce of value we can from these facilities. We just operate them differently. We don't have to build anything new. So, our commitment to you is to take a look at all of the watersheds, the headwaters of the Rio Grande, the Arkansas River and the Colorado to make sure that if this technology or this--yes, I will call it a technology, it is a different way of looking at managing water--is applicable here, we absolutely want to apply it. Mr. Hurd of Colorado. General, can you think of any additional resources or authority that would help accelerated option of forecast-informed reservoir operations? General Graham. I am sorry, I missed the question. Mr. Hurd of Colorado. Can you think of any additional resources or authorities that would help accelerated option of the forecast-informed reservoir operations? Can we do it better? How can we do it better? General Graham. Scaling up from we are, kind of--if you--as we branch out from getting it started in California, we want to continue to train our staff and to bring in additional staff, so, I think it will start to expand out our capabilities. We are also working not only with our researchers at our Engineer Research and Development Center, but also to bring in private- sector organizations, colleges, and universities so that we can expand this capacity. Mr. Hurd of Colorado. Thank you. Were you going to say something, Mr. Telle? Mr. Telle. Sir, I was just going to mention that one of the ways that we can achieve the scale that General Graham references and that you are seeking is by making sure that we are taking district employees who have expertise and experience in these new methods of controlling water reserves and making them available to other districts and regions throughout the country, potentially making sure that we take advantage of our expertise across the country and potentially creating centers of excellence, which is something that General Graham and his team have done a really good job of to eliminate duplication within the districts and focus expertise in one or two areas in the country, so I would just say as forecast-informed reservoir operations becomes more and more prevalent, we look forward to working with you on helping stand up that capability. Mr. Hurd of Colorado. Thank you very much, gentlemen. I see my time is almost expired. Mr. Chairman, I yield the remainder of my time back. Mr. Collins. Thank you. The gentleman yields back. I now recognize Ms. Gillen for 5 minutes for questions. Ms. Gillen. Thank you, Mr. Chairman. Thank you, gentlemen, for taking the time to appear before us today, and thank you for your service to our country. I represent New York's Fourth Congressional District, which is contained entirely on the South Shore of Nassau County on Long Island. We are the home to many coastal communities and many beautiful beaches. I, in my prior role in local government, had the privilege of working with the Army Corps to ameliorate some of the effects that were still lingering from Superstorm Sandy, which was devastating to my district, and other hurricanes that happened after that and really worked productively with you, so, I thank you for that. So, my district contains two Federal navigation channels, the East Rockaway Inlet and the Jones Beach Inlet, and due to shoaling, the depths of the navigable channel in these waterways are often reduced, which poses a real threat to safety, especially during rough weather. I have heard from many in our maritime trades and recreational boaters as well about the need to regularly maintain and dredge these two inlets to keep boaters safe. So, I guess, Lieutenant General Graham, could the Army Corps, and perhaps your staff can follow up with me, provide my office with an update on plans to conduct dredging at both East Rockaway and the Jones Beach Inlet? East Rockaway was last dredged in 2022, and Jones was last dredged in 2023. Thank you. And I am also asking if Congress can do something to help New York reduce the delays and increase the frequency of maintenance dredging on inlets such as this and perhaps look at ways, particularly with respect to the East Rockaway and the Jones Beach Inlet. If we could look at ways where we might be able to do some studies, perhaps working with our local governments on alternate locations to place some of the dredging materials so this problem doesn't keep occurring every year. Do you think that is something that we could look at together? General Graham. Representative, absolutely. Ms. Gillen. Excellent. Thank you. So, again, I mentioned working together with the Army Corps on addressing erosion after Superstorm Sandy and the beautiful beaches that serve our community are not only a great source of recreation, they are a great source of natural beauty. They're a really important resource for my district. But erosion remains a continuous problem with these beaches having to rebuild our dunes, having to restore our shoreline. So, there is new technology available, gentlemen. There are reusable plastic grids, which are also known as cliff stabilizers, and they can be driven into sand to protect against beach--dune, rather, erosion. So, Assistant Secretary Telle, would you and the Army Corps be willing to work with my office and the committee to explore potential applications of this technology to prevent future coastal erosion and also reduce the burden that you might have to come back and replenish those beaches? Mr. Telle. Congresswoman, thank you, and yes, there are technologies out there that help reduce beach erosion. Some of them are already deployed in different parts of our country. General Graham recently mentioned the Engineer Research and Development Center, which is the U.S. Army Corps of Engineers R&D component, and we would be happy to put you in touch with the appropriate folks there to see what this technology might be able to provide to the Nation in terms of reducing beach erosion. Ms. Gillen. Excellent. Thank you. Anything else, Lieutenant General? General Graham. We are always looking, as the Assistant Secretary said, to innovate as a tremendous amount of funds, but the amount of funds we have for the coastal storm risk management system is certainly insufficient to deal with the needs that are out there, so stretching every dollar, doing more with this is certainly our commitment to you, and so, if there are new technologies, always happy to spend some time up on Long Island. Ms. Gillen. Excellent. Thank you. We welcome you anytime to come visit, and my office will follow up with you about the two points we discussed. Thank you, gentlemen. Mr. Collins. Thank you. The gentlelady yields back. I now recognize Mr. Burlison for 5 minutes to ask questions. Mr. Burlison. Thank you, Secretary Telle. Thank you, General Graham, for being here today. I really appreciate your service to our country. And I am sorry to hear about the loss of your father. I am sure he was very proud to see you become Secretary. And I want to say thank you for coming to my office last week and visiting. I greatly appreciated that meeting, and it gave me hope that we will be able to resolve some issues together. As you know, Table Rock Lake, which is located in my district, is more than just a body of water. It is a cherished landmark of southwest Missouri, and it is really a crown jewel for the whole State. Some property owners, through no fault of their own, as we discussed, have structural encroachments, much of which happened when surveys were confused, or plot lines were confused. Many of these individuals didn't build the structure, they just bought a home and--their retirement dream home, right, only to find out that there is an encroachment that requires them to remove their septic tank, or some structure, or sometimes a retaining wall that is holding back dirt from flooding their home. And so, I want to just kind of get an update from you after that meeting, any followup that you have. Mr. Telle. Congressman Burlison, thank you for being an advocate for your constituents on this issue. It is one that my office and General Graham's operation are tracking very closely. We let you know last week that we had paused all enforcement actions on residents around Table Rock Lake, which, as I conveyed to you last week, I understand personally the lake culture that exists throughout much of middle America, including places like your district. You and I talked about visiting southwest Missouri, which I intend to do, and the Little Rock District as well. And so, what I will say to those constituents of yours who you have advocated for around Table Rock Lake is that we are working every single day to deliver a commonsense and fair outcome to this solution. There is no place for the Government to inappropriately infringe on individual property rights, but there is a flood control mission there. And so, we are going to have to balance the flood control mission against the property issues. But I see no reason that we shouldn't be able to solve this in a fair and commonsense way that produces a good outcome for your constituents. Mr. Burlison. Thank you. After our meeting, a couple of days later, I got a call from my Aunt Bonnie who lives on Table Rock Lake, and she said, the Corps has gone crazy; they are telling us that we have to remove our flowerpots off of our docks, and that they are not allowing pizza to be delivered. I didn't realize pizza could be delivered by boat on Table Rock Lake, but that's pretty awesome. And so, I get those kinds of phone calls all the time. And so, one has to scratch their head and wonder, Don't they have something better to be focused on than the flowerpots that my Aunt Bonnie has on her docks? Right? Mr. Telle. Congressman, I hope that that's not true. If it is, I know General Graham and I will look into it with the Little Rock District and see what we can do to make sure that we are being reasonable in enforcing our mission of flood control in that area. Mr. Burlison. Thank you. And I want you guys to mark on your calendar November the 9th. Each year, we have a veterans fishing charity event, we provide free fishing guides to area veterans. It is one of the most beautiful, patriotic American things you could ever see, and on the most beautiful lake in the country, and I would love for you both to attend November 9th if you could make that available. Mr. Telle. Thank you, Congressman. Mr. Burlison. And then I have a last question, General Graham, and this is a strange question, I know. But in an interview with Tucker Carlson, former Assistant Secretary of Housing and Urban Development Catherine Austin Fitts reported that there were secret underground military bases and bunkers that were built. She said that the United States Government has diverted $21 trillion to build a network of underground military bases, a vast--almost like a city-type structure with transportation in between. Are you aware of that claim that she made, and is there any validity to it? You can't comment? General Graham. Congressman, I don't have any knowledge of any of that. Mr. Burlison. Okay. All right. Thank you. I yield back. Mr. Collins. The gentleman yields back. I now recognize the gentlelady, Ms. Sykes, for 5 minutes for questions. Mrs. Sykes. Thank you, Mr. Chairman. Thank you, gentlemen, for being here. I have quite a bit to get through, but I also want to join my colleagues in expressing my condolences, and thank you for being here to share. Water is certainly a very important topic all across this country, and my district is no different. So I want to direct your attention to Ohio's 13th Congressional District, particularly the city of Massillon. The Corps' work has been benefiting a lot of my communities, but Massillon, in particular, needs and wants some help from the Corps. Last term, the Corps wrapped up a $22 million levee safety investment at the dam there that will help keep our community safe from flooding for years to come, so thank you for that. When we discovered that the Corps couldn't help us fund a sluice gate replacement for the dam, we were a little concerned. Part of this was because we were told you a need contract with the city and the Corps with the operations and maintenance funding, but it was my understanding that WRDA in 2022 gave you the authority to do this. We used as one of our CPF funding projects, my first term, this project to help the city cover this gap, but it was rejected. And the last time we had a hearing in this committee in 2023, I asked about guidance related to this new authority in section 8152. As of today, my office has since received this guidance, so we just got this today. So I know that was not your administration, but now we have it. But, however, it doesn't appear on the Corps website, and the individuals in my community were not communicated with. So Secretary Telle, while we work with Massillon to work on this rehabilitation, could you share how the Corps intends to share new implementation guidance with regional offices and relevant project partners? Mr. Telle. Congresswoman Sykes, thank you for the question. We take very seriously the Water Resources Development Act enacted by Congress and signed by the President and following that law. The approximately 180 provisions contained in the 2024 WRDA, just to give you an idea of the process that we go through as we implement---- Mrs. Sykes [interrupting]. Mr. Secretary, this is from 2022, not---- Mr. Telle [interrupting]. I'm sorry. I'm sorry. Apologies for that. In general, when we receive WRDAs, the way that we implement them is, some of the provisions are simple enough that they can be implemented right away and they sort of speak for themselves. Others of them are very complex, and as you mentioned, require implementation guidance. It is a minority of the provisions that require that type of guidance, but that type of guidance means that we have to get into much more detailed level of specificity in how we are going to carry out the laws that Congress passes and that---- Mrs. Sykes [interrupting]. I hate to interrupt you, but I have a couple more, but can I just count on your support to work with the city of Massillon to figure this out? We are now 3 years into this, and they could use that help. There are over 22 gates they need to deal with. Mr. Telle. Absolutely. Mrs. Sykes. And we have do two at a time. Thank you so much. And since you were talking about WRDA, I think many of my colleagues were disappointed with the appropriation of WRDA for the 2024 that you just referenced. We have significant authorities, large authorities to deal with so many projects in our area across the district from Akron, Canton, New Franklin, Barberton, Fairlawn and more, but what do you do when you are not appropriated the money, but these projects still need to be done? I know you don't appropriate funds, that is not your role, that is ours, but what do you do with the authorities that are not funded? Mr. Telle. Congresswoman, we keep very close track of all projects that have been authorized by Congress, all projects that could be authorized by Congress, and all projects for which appropriations have been received from Congress. We keep very close track of all of that. As I mentioned earlier in this hearing, there are some $78 billion worth of projects that have been authorized, but we haven't received appropriations. There are some $44 billion worth of projects that we have received appropriations for, but that funding has not been expended. And all of this is to say, the demand for Corps of Engineers' services is greater than the supply. And if we are going to get after the challenges that exist in your State, and exist throughout the country, this is a massive undertaking, we have got to be more efficient and smarter. It is not just about more resources. We have to deliver more with the resources that we have if we are ever going to get at this challenge. And General Graham and I are working together every day to try to ensure that that happens. Mrs. Sykes. Thank you. I appreciate you talking about efficiency and working smarter. I do want to thank you, although not funded, you have been working with the city of Cuyahoga Falls on giving some technical assistance in removing the Gorge Dam, which will be incredible. I actually texted the mayor because he had some interesting comments, and he said that the removal of those dams opened up about 1 to 2 miles of challenging white water for the experienced kayaker, and then when it is removed, it will open up 2 to 2\1/2\ miles of white water, which is not available anywhere east of the Mississippi. Going back to your conversation on efficiency, last month, the Secret Service directed the Army Corps to change the outflow of Ohio's Caeser Creek Lake to accommodate a kayaking trip for the Vice President, JD Vance. In terms of efficiency, it seems like this was probably not an efficient use of resources. So I do want to ask you, how much did this cost, and if you are concerned about efficiency, please explain how this action contributed towards the safety and efficiency of the Army Corps to have an escapade, if you will, kayaking for the Vice President. Mr. Telle. Ma'am, thank you for the question. The water level in the lower Miami River was requested to be increased by the Secret Service who was on a mission to protect the Vice President. Within the past year, or within--in 2024, we experienced two attempts on the President's life. When the State of Ohio contacted the Louisville District and asked them to raise the water level in that tributary to accommodate the Secret Service's patrol boats, they did so to ensure that the Vice President wasn't under threat. And none of the operations to increase the level of that river did anything to affect--it was all within the water control manual, and none of it did anything to affect the operations of that river. All those downstream of it were notified promptly, and it was a successful use of our water resources to ensure that we protect a Secret Service protectee. Mrs. Sykes. Thank you, sir. And I am not sure about the time, because I have seen a lot of different numbers here, Mr. Chair, but I appreciate your answer for that. It is not satisfactory, in my estimation. And certainly, we do want to keep the Vice President safe, as well as all of our elected officials---- Mr. Collins [interrupting]. The gentlelady's time is---- Mrs. Sykes [continuing]. But this is not something that is made eligible for everyone, and I just did not---- Mr. Collins [interrupting]. The Chair---- Mrs. Sykes [interrupting]. Thank you, Mr. Chair. Mr. Collins. Thank you. The Chair now recognizes Mr. Babin for 5 minutes for questions. Dr. Babin. Thank you, Mr. Chairman, very much. I want to thank Lieutenant General Graham and Assistant Secretary Telle for being here today. It is good to see both of you. As you know, our district in Texas has several critical projects underway along the Texas coast, including the Cedar Bayou channel improvement, the Houston Ship Channel expansion, and the Ike Dike. These projects are essential to keeping America moving forward and strengthening our economy, and the Gulf of America serves as a central hub for energy, trade, and commerce driving growth for not only our region, but for the entire Nation. And Mr. Telle, we discussed these projects in our meeting last week. Thank you so very much for being there. I really appreciate your cooperation with me and my office in completing them. Especially during hurricane season, which we are now in, and preparedness and timely action are more important than ever before. Will you direct your team to provide my staff with status updates on these projects and the other Corps projects in our district? Mr. Telle. Congressman Babin, the answer is yes. This is one of the most complex series of projects in the United States of America right now. It is a large system of systems in an area that is vulnerable to natural disaster, as you know very well. Dr. Babin. Yes, sir. Mr. Telle. So it is important that we keep on track and that we keep you updated. Dr. Babin. Absolutely. I have a couple more questions for you. Building on your plans to revamp the Civil Works division, how do you plan to streamline communication between USACE's headquarters and the individual districts to make sure that Members of Congress and local stakeholders are kept up to date on project developments? Mr. Telle. Congressman, we are very fortunate. The United States Army Corps of Engineers has 39 districts across our country, and those 39 districts generally have positive relationships with the locally elected officials and Members of Congress. What we could use some work on is making sure that the communication from the district level, to the division level, to General Graham's level, to my level and down, up and down that chain is more efficient and is more responsive to the needs of the stakeholders like you. So we are going to work together on that. Dr. Babin. Absolutely. I thank you both very much. And one more question, Mr. Telle, under its flood control and coastal emergencies authority, or FCCE, the Corps provides much needed post-disaster assistance to impacted communities, supports recoveries, and requires infrastructure that the Corps is responsible for maintaining. Has the Corps conducted any analysis of what resources and authorities are needed to respond to future disasters? Mr. Telle. Congressman, thank you for the question, and thank you for recognizing our organization's contribution to disaster response here in the United States. We are part of that disaster response framework, and we activate, primarily on debris removal, but other activities when called upon by the inner agency. And I will just say how proud--I would like to express how proud I am to be affiliated with this organization which was one of the first and most aggressive organizations when Hurricane Helene devastated western North Carolina, east Tennessee, and other parts of Appalachia, recently with the Los Angeles wildfires, and with the Juneau glacial outburst flooding. These are places that in many cases the Corps of Engineers doesn't get the credit that it deserves, but our U.S. Army is on the ground helping Americans every single day as disasters approach, and I am very proud of that. Dr. Babin. Amen. Thank you so very much. I appreciate and am proud of USACE and both of your service to our country. One last one. Do you believe, Mr. Telle, that the Corps' current FCCE authorities are sufficient, and if not, please explain. Mr. Telle. Congressman Babin, thank you for that question. I will get back to you if there are any authorities that I feel like we don't have, but currently, our FCCE authorities do allow us to do the minimal things we need to do to prepare and get in place and provide mitigation against looming disasters. In cases where FCCE is not sufficient, we have a very well- oiled relationship with the inner agency that allows us to activate and provide the United States Army Corps of Engineers expertise and human capital to respond to disasters using funding and authorities derived from other agencies. Dr. Babin. Absolutely. Well, thank you, and that will conclude my questioning. I yield back, Mr. Chairman. Mr. Collins. Thank you. The gentleman yields back. I now recognize Mr. Stanton for 5 minutes for questions. Mr. Stanton. Thank you very much, Mr. Chairman, for holding this hearing on the Water Resources Development Act, WRDA, and for the Army Corps and Civil Works for coming to testify today. And I was informed, Assistant Secretary Telle, about the passing of your father last week. I want to pass on my sympathies, and thank you for being here, it has got to be very tough. A major component of recent WRDA bills has been authorization for environmental infrastructure assistance, the EI program, including in my State of Arizona. Section 595 funds for Arizona were originally put in the statute in 2020. In last year's WRDA of 2024, this very committee increased authorizing by $50 million, up to $250 million total. That is more money going back into local communities to meet their infrastructure needs and protect water supplies. In Arizona, nearly $50 million of EI funds have been delivered to projects to help our communities and Tribal nations use wastewater more efficiently, recharge area aquifers, and improve water delivery and conservation through new wells and pipelines. We anticipate more projects to be funded in 2026. Just this week, we will be celebrating the first groundbreaking in Arizona with the Pascua Yaqui Tribe's project. This key milestone will bring in nonpotable water for irrigation of landscaping, parks, and fields, and leave potable water for use by Tribal members in the future. But there is more work to be done. Building resilient water infrastructure is paramount in Arizona. It is no exaggeration to say that the future of Arizona and the entire American Southwest depends on how we respond to the historic drought in the Colorado River Basin. Arizona's communities are doing their part to conserve water, but we are going to need the Federal Government to do more to step in. Arizona will have more than $15 billion in drinking water and wastewater infrastructure needs over the next two decades according to the Arizona Society of Civil Engineers. This is any range of projects, including Goodyear's soil aquifer treatment site to increase recharge capacity, or Santa Cruz County's reconstruction of the Nogales Wash line channel. Right now, there is $9 million additional environmental infrastructure funding for projects that would be chosen by the administration in the energy and water bill that past the House. Pending that we keep some sort of funding upon passage of a Government funding bill, Lieutenant General Graham, my question is this, How will the Army Corps prioritize these environmental infrastructure dollars? General Graham. Representative Stanton, thank you. First off, I think the L.A. District has vastly improved its coordination with your constituents, with your office, and so, I would be glad to get your thoughts on that, but my report---- Mr. Stanton [interrupting]. That is correct. General Graham. Okay. So, I am delighted that we are on the same sheet there. Thank you for bringing that to our attention. The district is committed to delivering for the State, and we will continue to make our best technical recommendation on these, as you laid out, very valuable projects. Mr. Stanton. Infrastructure takes time, as we all know, and there are ways to move the needle faster. Recently, the city of Flagstaff was not able to wait for EI money that was allocated through the Corps' IIJA work plan in 2022 due to the length of time to complete the environmental review for a simple flood mitigation project. As a result, the city will now construct the project with its own funding, obviously taking away from other projects that they could do in that important city. We also heard from the city of Buckeye west of Phoenix who received $2.25 million to update the wastewater treatment process at its central wastewater reclamation facility experienced a delay due to an environmental assessment. Moreover, when these EI projects broadly happen in an existing facility, it would move things along faster if CE is allowed. So Lieutenant General Graham, my final question is this, What is the Army Corps doing to expand the use of CE on EI projects, categorical exclusion, obviously, to get them under construction more quickly, and are there other ways to streamline the process to get the water infrastructure projects built faster? General Graham. I think this is certainly where President Trump has asked us to go, which is to take a look at the environmental rules, to continue to streamline those, and if there are categorical exclusions, to use those. Like in this instance, as we are relooking at the NEPA rules, we are working within the Department of Defense, and they have more categorical exclusions, so I think that would be an advantage of the environmental infrastructure program. Mr. Stanton. Okay. Assistant Secretary, anything to add? Mr. Telle. No, the general covered it, which is there have been actions taken, significant actions to date during the Trump administration to reduce the burden of Federal regulations without compromising our environmental quality. And so, nationwide permits under section 404 of the Clean Water Act is another one that we have talked about here, something that comes due in March, and we are committed to renewing those as they are an important tool that actually provides for some 50,000 annual 404 permits, which is over half. And so, that is a critical tool that provides transparency to the public and enables fast action when a member of the public seeks to take action. Mr. Stanton. Thank you very much. I look forward to working with you on that, and I yield back. Mr. Collins. Thank you. The gentleman yields. I now recognize Ms. King-Hinds for 5 minutes for questions. Ms. King-Hinds. Thank you very much, Mr. Chairman, for allowing me to sit in today, and thank you very much, Assistant Secretary Telle and General Graham, for being very gracious with your time today. So, I represent the Northern Mariana Islands, it is a chain of islands, and each of the islands has very different challenges. And I want to start, and I don't really have any questions, I just wanted to be able to have a conversation with you this morning to elevate some of the concerns with regard to the challenges that we are having. So I am going to start off with the island of Saipan, which is our capital island; our biggest challenge is shoreline erosion. So recently, we had a tropical storm sometime in July that exacerbated the issue. The wave action was so bad that it unearthed unexploded ordnance on the shoreline, which consisted of landmines, hand grenades, and just different types of artillery. And this 4,000-foot-stretch beach sits adjacent to a publicly owned--actually, to the American Memorial Park, and we are working to fix the issue, but obviously, permitting and technical support are very much needed from the Army Corps. And in recent conversations, one of the challenges that has been raised is the request for technical support from the Corps has been denied, so I am looking for the opportunity to be able to collaborate with you to figure out how to provide that assistance to our community. In addition, we also continue to face challenges with sediment removal in our primary marina where our boaters dock. Dredging there is very urgently needed, but the issue is delayed in permitting. We have been working with everybody, to include the Seabees, to figure out how to help and expedite that process, but the issue really is permitting, and getting the technical guidance from the Army Corps is an issue. Another issue that I want to raise, a couple of years ago-- actually, more than 10 years ago, we paid the Army Corps to do a study to figure out, basically, if the islands of Tinian and Rota could be eligible for the safe and subsistence--I think it is the remote and subsistence--section 206, remote and subsistence harbors funding through WRDA. We spent a couple million on that study only to find out that we weren't eligible because of Army Corps interpretation of specific language with regards to eligibility requirements. And I want to be able to work with you to be able to figure out how do we get, especially the island of Rota, qualified. So, as we all know, having viable ports is very critical to having an economy. Fortunately, for the island of Tinian, we do have a lot of Department of Defense activities happening there, and so, DoD is working to improve the harbor and the breakwater there on the island of Tinian. But for the island of Rota, funding is very--it is very challenging, and it doesn't have the same activities there. And so, I am looking forward to being able to work with you. I just wanted to be here to elevate those issues. We will be following up with a letter shortly here kind of outlining what I just discussed. And I also want to take this opportunity to invite the two of you to the Marianas so that you can see exactly what it is that I am talking about. Thank you very much. General Graham. Ma'am, you absolutely have our commitment to work with you on those issues. Many of those I am tracking right now. The entire region is tremendously important certainly, as you mentioned, to the Department of Defense, and to the Nation as a whole. I am happy to take our general in the Pacific and send him out to meet with you as soon as possible. And then if possible, I would like to also have the opportunity to meet you out there. I mean, that is the importance of the Territory. Ms. King-Hinds. Yes. I mean, there is no better way than just laying eyes on it, right? So, looking forward to that happening. Thank you so much. General Graham. Since you threw the gauntlet down on what the Seabees were doing, we are going to have to show up. Ms. King-Hinds. Yes, for sure. I yield my time. Mr. Collins. Thank you. The gentlelady yields. I now recognize Mr. LaMalfa for 5 minutes for questions. Mr. LaMalfa. Thank you, Mr. Chair. And thank you, panelists, for being here. And sorry I am last second at the meeting here. Three committees at the same time doesn't help you do a great job sometimes, so, anyway. Assistant Secretary Telle, my understanding is mourning in your family there, so God bless you. Our hearts are with you, sir. Thank you. Thank you for soldiering through today. It is a business here. I appreciate the opportunity to speak with you a little bit earlier. In northern California where I represent, it is the Sacramento District office primarily the one overseeing the operations in my district here, so a question for both Assistant Secretary Telle and Lieutenant General Graham. In your roles, what could we do to help with the staffing situation in the Sacramento District that seems to just put us so far behind on projects, because we have important things we are trying to get done that has to do with water, water supply and like that? What could we touch on to have the staff situation be able to work, move people around that maybe are less occupied and into a position where they can help move pretty important water projects and water-related issues? Mr. Telle. Congressman LaMalfa, thank you for visiting with me last week, and thank you for the expertise you bring to the complicated conversation that is California water. I would just say that one of the things that General Graham and I are working on every day is to make sure we are optimizing the workforce across the districts. And we have done a lot of discussion here today about forecast-informed reservoir operations, which I know is important to you as it relates to the Shasta Dam, which is really the headwaters, you might say, for all of California's water, and important to the agricultural interests in your district. And so, I would say that General Graham and I are committed to try to deliver expertise from across the enterprise to districts that are busy, from districts that may be less busy and that have expertise for districts that may not. And in the case of the Sacramento District, I look forward to working with General Graham and with you to see what we may do to accelerate the update of some of the water control manuals in your district. As you discussed here today, this is a low-cost way to utilize existing infrastructure and optimize water supply for the variety of purposes it is needed in places like California. Mr. LaMalfa. Thank you. Lieutenant General. General Graham. Representative LaMalfa, absolutely, bringing all of the possible value we can out of those facilities, and ones that we work in collaboration with, like the aforementioned Lake Shasta with Bureau of Reclamation in Oroville with the State of California. Absolutely. So, delighted to see Lake Mendocino's water control manual go into operation, and our ability to continue to take a look at those facilities, get the assessments done on whether or not forecast-informed reservoir operations is applicable here, and then move that rapidly into an update to the water control manual. That is our pledge to you is to do that and optimize in an efficient way. Mr. LaMalfa. Given the size of Lake Shasta being 4\1/2\ million acre-feet and the largest project in the States in Federal purview there, and then the possibility of a dam raise there of another 600,000 acre-feet combined with this work on the manuals, the FIRO, the forecast-informed reservoir operations, would be--certainly make a lot of sense to me instead of older manuals that--because I believe, as I was watching water flooding out Glenn County from releases in February or March this year, that with FIRO, just with that forecast ability to see what the weather is going to be for a few weeks at a time, perhaps offshore fronts and such, that we could have probably conserved a couple hundred thousand more acre-feet of water by adjusting that to the timeline for conservation. So, we have that opportunity, again, we have the raise itself that we need to be sure we can engineer, move that along. And as we talked about, too, the assessment of the Black Butte Lake there in Glenn County, which needs to finish a review on dam safety, but, also, incorporate it, hopefully at the same time, this is what we got an amendment built into legislation here recently on both those items, the FIRO and Black Butte, installing gates there that could raise the capacity safely just by having the ability to regulate the spillway there. Those are two very important projects tied in with two other study aspects, really four things simultaneously we need to get done, and at pretty low cost, really, and enhanced water supplies. So, we have seen in the west side of the valley there in the year 2022 the devastation by water supply, 250,000 acres of rice just left out. And drought is drought, but if we manage water and stretch it farther into upcoming years, then we will get a lot more yield. So, with that, thank you, Mr. Chairman. I yield back. Mr. Collins. Thank you. The gentleman yields back. I now recognize the chairman of the Subcommittee on Coast Guard and Maritime Transportation, Mr. Ezell, for 5 minutes of questions. Mr. Ezell. Thank you, Mr. Chairman. And thank you guys for both being here today. Congratulations on your new job. I look forward to working with both of you in the future. And condolences to you about your father. Since I have been in the Congress, it hasn't been too many weeks that have gone by that I hadn't had some kind of call about the Army Corps of Engineers. It was kind of like when I was sheriff, some deputy was always doing something that he wasn't supposed to. But I do get quite a few calls, various complaints. But, I know that some of the main issues that we have dealt with and worked tirelessly to address, the Bonnet Carre spillway issue on the Mississippi River. I am sure both of you are aware that the Mississippi River and its infrastructure are outdated in comparison to some of the technology that is available today. Levees, chemicals, runoff, drainage issues, outdated processes and more, plague our management of the Mississippi resulting in a dead zone nearly the size of Connecticut out there in the Gulf of America. We have to get together to find a solution that works for both Mississippi and Louisiana. That is just something we have got to do. And I look forward to working with both of you and the opportunity in speaking with you and getting this thing done. But General Graham, I have got a vital port in my district that is currently undergoing a dredging process. Given the time that has already elapsed, I am hopeful that it will soon transition from a study to actually moving some mud. Can you provide me with an update on the dredge capacity report required by section 8205 of WRDA 2022? When do you expect it to be available for public comment? It has almost been 3 years. General Graham. Thank you for that question. And that report is under administration review. Mr. Ezell. Okay. And I want to, General, ask you about beneficial reuse, which is--and I heard somebody say something about that earlier, implemented in the 2016 WRDA section 1122, and, again, in WRDA 2022. It has been 10 years since the pilot program was first implemented, when do you expect the pilot program to be ready for use? Mr. Telle. Congressman, I will defer to General Graham on the timeline there. But as you say, beneficial use material, dredge material has been, especially in your district where the barrier islands were restored, or partially restored post- Hurricane Katrina. And I would just like to recognize the 20th anniversary of that event, which your citizens in your district did a tremendous job persevering through and rebuilding, so, congratulations to you and to them. But the beneficial use program is important to preventing future storms. General Graham. It absolutely is. And looking at, just like its name implies, is that dredge material isn't a waste byproduct. It is actually a commodity we want to maximize. So, we will get back with your office on the exact status of those pilots. Mr. Ezell. Can you give me any idea about what is holding this thing up? General Graham. We will get back to your staff with that. Mr. Ezell. I get it. General Graham, there are roughly 18 strategic seaports in the United States that work with DoD for preparedness and general transportation of equipment. The result is numerous acres set aside that ports cannot use. The extensive labor and cost associated with these agreements ensure that the country's military can deploy at a rapid pace if needed. General, do you think ports that have these obligations should see this obligation incorporated into the benefit-to- cost ratio in some way? General Graham. Congressman, I have not come across that ask before, but I will certainly go back to the staff and take a look at that. Mr. Ezell. Okay. Mr. Telle. Congressman, I would just say is we calculate the benefits of a project, General Graham and I are stretching to make sure we are being holistic in that calculation to account for monetary and nonmonetary benefits. And I know the Port of Gulfport in your district is a major mobilization point for Camp Shelby, and the Army National Guard has that designation, and it is something that we will try to take into account as we look into that project. Mr. Ezell. Very good. I am proud to have somebody from Mississippi with some ties to the Army Corps here with us. Thank you, sir. Given your career up to this point, I am sure that you are aware of the issues we face down on the gulf coast. Mr. Secretary, can you give me some of the priorities of the Army Corps of Engineers, and how can WRDA be a resource to you? Mr. Telle. Congressman, thank you for the question. And I will just say, I don't have much free time, but what free time I do have I generally spend it in your district, so---- Mr. Ezell [interrupting]. Thank you. Mr. Telle. Thank you. There is a lot that can--this applies to the entire coast of the Gulf of America, which is such as important part of our country, Mississippi is no exception to that, it is a wonderful place, and I think one of the things that I hear when I visited your district is the importance of the operations on the Mississippi River that you referenced. And I would just commend our New Orleans District, during the spring floods this year of the Mississippi River, for really holding off on opening the Bonnet Carre spillway. They had a very precise understanding of when that would be needed, and fortunately in this year's flood, it was not needed. And they are going to take that thing right up to the limit to preserve the quality of the water in the Mississippi Sound. And so, I would just like to commend the New Orleans District, the commander down there. Mr. Ezell. Thank you, Mr. Chairman. I yield back. Mr. Collins. Thank you. The gentleman yields back. I now recognize the chairman of the Subcommittee on Highways and Transit, Mr. Rouzer, for 5 minutes. Mr. Rouzer. Thank you, Mr. Chairman. Mr. Secretary, so sorry to hear of your loss. Certainly going to be in our thoughts and prayers. This is to both of you, but probably more predominantly General Graham. You are aware, I am sure, of the Surf City, North Carolina, coastal storm risk management project which has advanced through key milestones with a committed non-Federal sponsor. A signed Chief's Report has been issued, but I understand there are some outstanding technicalities that must be resolved in the Chief's Report package. How quickly can that be resolved, can that be accomplished? General Graham. It was great to get down there and meet with that team. I got a Ph.D. dissertation on turtles from the team down there, and they are phenomenal non-Federal sponsors. That study went through, or that project went through some challenges with, I believe it was North Topsail pulling out, but we are committed, signed that one immediately. The technical challenges that we are working through, I don't expect them to take long, and we will get it so that it will be over here ready to go. Mr. Rouzer. Okay. When you say ``don't take long,'' is that a month, is that 2 months or---- General Graham [interrupting]. Sir, I will get back with you with an exact timeline. Mr. Rouzer. Okay. That would be wonderful. So, you don't see any problems pertaining to the project thereafter? General Graham. No critical flaws have been brought to my attention. Mr. Rouzer. Very good. The North Carolina Ports Authority completed a section 203 study for the Wilmington Harbor channel improvement project, which was contingently authorized in WRDA 2020. It took nearly 2 years to reach a cost-share agreement for the project. Is there a good reason for that? It just seems like this has dragged on a little too long. Mr. Telle. Congressman, I will defer to General Graham on the specifics of that project, but you raise a really important question here, which is the length of time these projects take. And you also referenced cost-share agreements. Because the cost-share agreements with Corps' projects have robust non- Federal sponsor commitments, and they often deal with real estate acquisition, which is complicated, especially in coastal communities and riverine communities, getting an agreement between the Federal Government and a non-Federal sponsor can take a significant amount of time. And we need to work with this committee to address that timeline. Quite often, the non-Federal sponsor can be a better acquirer of real estate than the Federal Government, and so, that is one key way in these project partnership agreements that we can deliver better results for the taxpayer. Mr. Rouzer. Well, this is deepening of that harbor. Obviously ports are critically important to the economy, and in North Carolina, we have two that service the economy in exceptional ways. And improvements of those ports are necessary. And the whole purpose of this, of the program was to expedite, not to slow anything down, and to have good non- Federal partners that could take the lead, and not only share in the cost, but help to move things along. It just doesn't seem to have worked out that way. Mr. Telle. We look forward to working with you to get this right. I agree with you, this is critically important, and we have to get it done. Mr. Rouzer. One other item I want to mention before my time runs out. We have a lot of beautiful beaches in North Carolina, as you know. A number of them are federally authorized, and it is important, that continual renourishment cycle is important in terms of protecting the infrastructure property. The money that is invested upfront saves the taxpayer a whole lot of money on the back end once a storm comes through. You can go to the beaches that aren't well renourished and see the damage that's done, and it's lasting and forever. And then you can go to the ones that have a good renourishment program, and you would never know a storm ever came through there, in large part because so much of that property was protected from the storm, and the infrastructure as well. So, it saves the taxpayer money on multiple fronts, National Flood Insurance Program, insurance costs, you name it. And so, I just want to reiterate the importance, and underscore the importance of beach renourishment. I assume the administration and the Corps specifically is still very much committed to that process. Mr. Telle. Congressman, you are correct, in many coastal communities, beach renourishment is the best way to prevent storm surge flooding and other types of flooding, and that is true in your State, and it is true in many others. Mr. Rouzer. Thank you very much. With that, I yield back. Thank you, Mr. Chairman. Mr. Collins. Thank you. The gentleman yields back. I now recognize Mr. Bresnahan for 5 minutes for questioning. Mr. Bresnahan. Thank you, Mr. Chairman. My district is northeastern Pennsylvania, which is no stranger to flooding and natural disasters. Over time, the Wyoming Valley has seen more frequent and more severe flooding and storm events. Yesterday was the 14th anniversary of the 2011 floods, which nearly broke the Wilkes-Barre levee. During the storm, the Susquehanna River hit a record of 42.66 feet against a levee that is designed for 41 feet of water. Families in West Pittston, Plains, West Nanticoke, Shickshinny, and Edwardsville either lost their homes or spent thousands rebuilding, including my own grandparents' home that is on the Susquehanna River banks. Couple this with Hurricane Agnes in 1972, and the September 2023 floods, and you can see why flood mitigation efforts are so important to my district. They are literally life-saving measures. My district has the second lowest median income in Pennsylvania with a median household income of $61,140, and my constituents cannot afford to keep rebuilding year after year, and we don't have the tax base to build our own levees without Federal support. Since 1996, the Luzerne County Flood Protection Authority has been working with the Army Corps on mitigation efforts which cover 5 counties and 52 municipalities over a 16-mile span, including Pennsylvania's Ninth Congressional District, which is represented by my colleague, Congressman Dan Meuser. Unfortunately, these efforts have stalled on the project, and it has been drawn out since 2009. With each passing year, project costs increase, and with each year without mitigation efforts moving forward, my constituents live and properties are at risk. The cancellation of FEMA's BRIC program has cost my district at least $22 million for property buyouts and levee projects. So, here is the catch-22. The Army Corps has said that for local authorities to be reimbursed, it can only be for a fully functioning project. The Army Corps conditionally approved the Luzerne County Flood Protection Authority mitigation projects with the stipulation they be design-only phase. So, now these projects are tied up in design-only phase since BRIC funding was canceled. So, we can't complete a fully functioning project since BRIC funding was canceled. So, what my district needs from the Army Corps is to review the requirement change for design-only projects to be advanced so our local flood authority can be reimbursed, and for the Army Corps to move this project off the back burner and to the top of the priority list. So, perhaps maybe that was just a long-winded way of saying we need help. And perhaps over the next few weeks, you can commit to coming out to northeastern Pennsylvania to visit and meet with our local flood authority to discuss a plan, which was first developed in 1996. Is that something that we can perhaps work together on? Mr. Telle. Congressman, I would enjoy visiting your district, and I am happy to do that. And I know we have a native Pennsylvanian here next to me who may have the ability to do that as well. General Graham. This is what we are built for, and we will look with the Baltimore District to see what the challenges are up in Luzerne County, the management working in conjunction with the Potomac River Authority is really--I'm sorry---- Mr. Bresnahan [interrupting]. Susquehanna. General Graham. Susquehanna--is really important. So, absolutely agree to meet with you and your team. Mr. Bresnahan. I think it's a very notable moment when you smell flood mud for the first time. It was in 2011, I was actually helping my grandparents and other neighbors sandbag and when--actually, we were flooded from the rear through the sewer systems, first, before the actual river toppled over its banks. And everybody--1972 was slightly before my time, but everyone remembers Hurricane Agnes and how close in 2011 we actually came to disaster, again. I mean, we were within centimeters with a levee that, really, we got very lucky on many different fronts. So, I look forward to having you come up to visit Pennsylvania's Eighth Congressional District, to walk the banks of the Susquehanna, and hopefully be able to move this ball forward and come up with a finite solution so our friends and family and neighbors can sleep well at night. So, thank you. Mr. Telle. Thank you. Mr. Collins. Thank you. The gentleman yields back. Are there any further questions from any members of the subcommittee who have not been recognized? Seeing none. Before we conclude, I just, also, Secretary, I want to extend my condolences. I am sorry for your loss. And you don't know how much it means for you to show up today. Thank you very much. General Graham, good to see you, again. Thanks for your time today. It went a little bit over, but I appreciate you all coming. And, you know, it is hard for this old Georgia Bulldog to put good praise and Alabama in the same sentence, but I want to try to make an effort myself to get down on the 13th of October to Mobile as that pilot project that Congressman Figures was talking about came in under budget and ahead of schedule, and I think that could be a good example going forward of how we could improve efficiency and productivity within the Army Corps' projects. So, thank you for being here. And with that, this subcommittee stands adjourned. [Whereupon, at 12:48 p.m., the subcommittee was adjourned.] Appendix ---------- Questions to Hon. Adam R. Telle, Assistant Secretary of the Army for Civil Works, Department of the Army, from Hon. Mike Collins Question 1. The Jacksonville District of the Army Corps is stretched to its limit on resources. The district cannot keep up with permitting and enforcement. The State of Florida acquired the authority to administer Clean Water Act Section 404 wetlands permits, but that authority was revoked by a Federal court and returned to Jacksonville. If that permitting authority were returned to the State, would that free up the Army Corps to work on projects that are important for the safety and economic security of our local communities? Answer. Yes, returning certain Clean Water Act Section 404 permitting authorities to the State of Florida would reduce the Jacksonville District's regulatory workload. Question 2.a. Since your confirmation, what more have you been able to learn about the Corps' winter release plan at Gavins Point Dam and whether updates to the Missouri River Mainstem Reservoir System Master Water Control Manual are warranted? Question 2.b. What operational adjustments can the Corps take at the Gavins Point Dam, consistent with existing legal authorities, authorized project purposes, and seasonal water conditions to support the Nation's energy supply consistent with Section 4 of the President's Executive Order ``Declaring a National Energy Emergency''? Answer to questions 2.a. & 2.b. The Corps monitors weather and river conditions within the basin, including the reach below Gavins Point Dam. When the weather forecast indicates an increased possibility of rapid ice formation, releases can, and have historically been, increased slightly to mitigate some of the effects of ice formation. Large or rapid increases in releases increase the risk of ice jams, which represents an even greater risk for water intakes in the lower river. Question 3. The Corps' Cold Regions Research and Engineering Laboratory can support monitoring, modeling, and information-sharing efforts to better understand the conditions that lead to ice jam formation and their impacts on public infrastructure. To expand collaboration with affected communities and infrastructure owners and identify practical mitigation measures and improve preparedness for ice-related events, would you be willing to both meet with stakeholders and visit these communities along the Missouri River to better understand the potential consequences of reduced winter release levels from Gavins Point Dam? Answer. Yes, I am willing to meet with stakeholders. In addition, Northwestern Division will be hosting in-person and virtual water management meetings in the Missouri River Basin this fall. In addition, Northwestern Division plans to host in-person and virtual water management meeting in the Missouri River Basin this fall. The meeting times and venues are on the Missouri River Water Management website. These meetings are an opportunity for stakeholders to discuss their concerns with planned releases. Questions to Hon. Adam R. Telle, Assistant Secretary of the Army for Civil Works, Department of the Army, from Hon. Brian Babin Question 1. The Galveston District awarded its $7 billion Horizontal Construction Multiple Award Task Order Contract (MATOC) in April to 15 firms. Beyond the initial seed project award of $400M (which was the only project included in the MATOC solicitation), subcontractors and the awardees themselves have had little to no information on the work forecasted to be issued as task orders under the MATOC. Can USACE commit to providing more information to the construction industry on funding availability and timing of upcoming task orders under this MATOC? Answer. As the Corps identifies work that would be suitable for this MATOC, it will inform the firms qualified as bidders of the proposed work. Question 2. Given the significant backlog of required mitigation across the Corps' portfolio, can USACE commit to ensuring that mitigation measures are implemented prior to or concurrently with construction on new civil works projects, rather than years after project completion? What specific steps is the Corps taking to integrate mitigation into project delivery schedules to avoid further compounding the backlog? Answer. The Corps works to ensure that implementation of mitigation features of water resources projects occurs prior to, or concurrently with, construction activities as required by section 906 of WRDA 1986, as amended. Project implementation and the estimated costs for construction, including any required mitigation, are specified in the feasibility report. Mitigation features are tracked across all construction projects and reported annually to Congress, which supports accountability for mitigation work. Questions to Hon. Adam R. Telle, Assistant Secretary of the Army for Civil Works, Department of the Army, from Hon. Rick Larsen Question 1. What is the status of implementation for the amendments to the continuing authority for aquatic ecosystem restoration projects (enacted by section 206 of WRDA 1996), especially as they related to cost share for projects for habitat or passage of anadromous fish (see section 1107(e) of WRDA 2024)? Question 1.a. The Corps has informed me that it is actively working implementation guidance for this section of WRDA 2024. This new guidance will address the revised cost share as well as language tied to drought resilience and the federal per project limits. The Corps says a draft of this implementation guidance should be ready for ASA(CW) review by the end of September. When will your review of this implementation guidance be complete, so these changes may go into effect as soon as possible? Answer to questions 1 & 1.a. Implementation guidance is being drafted. Question 1.b. How will interested non-federal interests identify their desire to utilize this new cost share for aquatic ecosystem restoration projects for habitat or passage for anadromous fish? Answer. The non-federal sponsor will not need to request to use the new cost share percentage. The Implementation Guidance will define how projects qualify. Question 2. What is the status of implementation for the amendments to the tribal partnership program (TPP) (enacted by section 203 of WRDA 2000), especially the pilot program for water-related planning activities or activities relating to the study, design, and construction of water resources development projects in proximity to a river system or other aquatic habitat within the State of Washington with respect to which an Indian Tribe, an inter-tribal consortium, or a Tribal organization has Tribal treaty rights (see section 1140 of WRDA 2024)? Answer. We are incorporating the changes from Section 1140 of WRDA 2024 into existing guidance on the Tribal Partnership Program and determining if additional guidance is needed. Question 2.a. The intent of this change was to allow Tribal partners to utilize the TPP authority for project-related activities on lands within Washington State that are not otherwise ``located primarily within Indian country,'' provided those lands are located ``in proximity to a river system or other aquatic habitat within the State of Washington with respect to which an Indian Tribe, an inter- tribal consortium, or a Tribal organization has Tribal treaty rights.'' The Corps has informed me that utilization of this new pilot program would proceed according to the standing TPP laws/guidance. Does the ASA (CW) office concur with this understanding? Answer. Yes. Question 2.b. How will the Corps determine whether projects meet the revised scope of section 203(e)(2)(C) of the WRDA 2000 (33 U.S.C. 2269)? Answer. Prospective new start feasibility studies will be evaluated case-by-case to ensure they meet the two criteria in section 203(e)(2)(C): (1) Proximity to river system or aquatic habitat within exterior bounds of Washington State, and (2) the NFS is a Tribe/Tribal organization with treaty rights applicable to the river system or aquatic habitat where the proposed project occurs. Question 2.c. How will the Corps provide outreach to potentially eligible Tribal consortiums, commissions, and communities in the State of Washington to make sure they are aware of this new authority? Answer. The district's Tribal Liaisons continue to share updates to the Tribal Partnership Program with Tribal leadership and staff, Tribal consortiums and other organizations with Tribal treaty rights in Washington State. The regional leadership also leverages routine leadership engagements at events such as the Affiliated Tribes of the Northwest Indians and other meetings between eligible federally recognized Tribes. These include engagements with organizations such as the Columbia River Intertribal Fish Commission and the Northwest Indian Fish Commission. Question 2.d. How will interested Tribal communities identify their desire to utilize this new authority for eligible TPP projects? Answer. Interested Tribal Nations or Tribal organizations should contact their local Corps district or division office and provide a letter of interest for initiating a feasibility study under new provisions of the Tribal Partnership Program. Question 3. In February, I joined with Subcommittee Ranking Member Wilson (FL) in a letter to the Corps and the Office of the Assistant Secretary of the Army (Civil Works) outlining several priority provisions within WRDA 2024 that we urge for immediate implementation. Can you provide a detailed account of each provision outlined in that letter (attached), including whether implementation guidance will be required to implement each provision, and if so, when this guidance will be completed? Letter referenced by Hon. Larsen in question 3 above: __________ Committee on Transportation and Infrastructure, U.S. House of Representatives, Washington, DC 20515, February 4, 2025. Robyn Colosimo, P.E., Senior Official Performing the Duties of the Assistant Secretary of the Army for Civil Works, Department of the Army, 108 Army Pentagon, Washington, DC 20310-0108. Lieutenant General William H. Graham, Jr., Chief of Engineers and Commanding General, U.S. Army Corps of Engineers, 441 G Street NW, Attn: CECS-C, Washington, DC 20314. Dear Ms. Colosimo and Lieutenant General Graham: As you proceed with implementation of the Water Resources Development Act (WRDA) of 2024, we write to highlight several priority provisions on which we urge immediate implementation. Swift action on these items will advance the work of the U.S. Army Corps of Engineers (Corps) to improve our nation's water resources, maintain our global economic competitiveness, and speed up project delivery timelines for communities nationwide. WRDA 2024 was enacted into law on January 4, 2025, as Division A of the Thomas R. Carper Water Resource Development Act of 2024 (Pub. L. 118-272). WRDA 2024 is the sixth biennial and bipartisan WRDA in a row and maintains the tradition of the Transportation and Infrastructure Committee to create jobs and improve the efficiency and effectiveness of the nation's ports, harbors and inland waterways. Attached is a list of provisions that address priorities identified by Members of the Committee on Transportation and Infrastructure that were enacted in this legislation. These priorities include confronting the challenges of extreme weather and violent storms; addressing the water supply, water conservation, and drought resiliency needs of the nation; enhancing project delivery; and supporting critical Corps' responsibilities for dredging and maintenance at our ports, harbors, and inland waterways. As Members of the House Committee and Subcommittee charged with Congressional oversight responsibility for the Corps, we urge you to prioritize your implementation efforts on these areas, including, where necessary, federal financing of these critical provisions. Similarly, we urge this administration's continued support for sufficient budgetary resources necessary for efficient and expeditious implementation of all authorized water resources development projects contained in this, or previous, WRDA bills. Finally, Section 1102 of the bill requires the development of a plan to implement each provision in the bill, as well as provisions of prior WRDA bills. We look forward to the transmittal of this plan as required, as well as required updates on implementation status, project timelines, and updates on provisions from previous WRDA bills that still await full implementation. Efficient and timely implementation of these legally-required authorities is essential to meeting the water resources challenges facing our local communities. Thank you for your attention to addressing the water resource needs of this nation. Sincerely, Rick Larsen, Ranking Member, Committee on Transportation and Infrastructure. Frederica S. Wilson, Ranking Member, Subcommittee on Water Resources and Environment. Attachment Attachment Maintaining Our Economic Edge: WRDA 2024 builds upon the Corps' critical responsibilities for constructing and maintaining our ports, harbors and inland waterways. This work is critical to supporting our economy, our businesses and industry, and alleviating supply chain issues. WRDA 2024 included several provisions to ensure this core mission work is as successful as possible. Sec. 1117, entitled Harbor Deepening, modifies the depth at which Federal ports and harbors projects can receive Federal assistance for construction and operation and maintenance. This provision will ensure our ports to be prepared to receive post-Panamax- sized ships and keep our supply chains strong. Sec. 1126, entitled Inland Waterway Projects, adjusts the share of costs derived from the Inland Waterways Trust Fund for navigation projects on the inland waterways. This shift will support the upgrades and modernization needed at our waterway connections to support domestic goods movement and exportation. Sec. 1129, entitled Emerging Harbors, requires the Secretary to issue guidance and to develop a mechanism to accept funds from a non-Federal interest for the purpose of maintenance dredging. When this program is fully implemented, it will support local economies while ensuring smart and efficient use of federal resources. Sec. 1130, entitled Maximization of Beneficial Use, encourages additional beneficial reuse of dredged materials through several means, reducing federal costs for projects, allowing critical reuse of clean dredged material for complementary projects, and creating cost-savings for the Corps and its partners. Sec. 1136, entitled Federal Breakwaters and Jetties, further clarifies the scope of navigation repair and replacement work that falls within the scope of operation and maintenance activities at federal harbors. Sec. 1147, entitled Remote and Subsistence Harbors, promotes projects that support remote and subsistence harbors. These harbors support national defense locations and support global commerce and imports critical to the contiguous United States. Sec. 1206, entitled Annual Report on Harbor Maintenance Needs and Trust Fund Expenditures, provides greater transparency on the legally-required distribution of operation and maintenance funds from the Harbor Maintenance Trust Fund to our harbors. Sec. 1356, entitled Additional Projects for Underserved Community Harbors, directs the Corps to assist to underserved community harbor projects, supporting local economies while ensuring smart and efficient use of federal resources. Sec. 1364, entitled Maintenance of Navigation Channels, encourages the utilization of additional private sector resources for the construction of coastal navigation projects, boosting the nation's our capacity for the movement of goods and support our global competitiveness. Job Creation and Supporting Local Economies: WRDA 2024 created and modifies several Corps authorities aimed at benefiting local economies and boosting job creation and training. Economic development in small communities is critical to supporting our national economy and ensuring American prosperity. Sec. 1105, entitled Review Process, directs the Secretary to provide clear guidance and technical assistance for modifications of Corps-built structures by non-Federal entities. Local efforts to maintain or modify their infrastructure can bring jobs and critical investment to communities; this provision will allow better facilitation of that process. Sec. 1115, entitled Support of the Army Civil Works Mission, directs the Corps to partner with designated, local educational institutions on shared research goals that will support future water resources development projects. Sec. 1121, entitled Databases of Corps Recreational Sites, directs the Secretary to regularly update publicly available databases with information about Corps recreational sites, many of which are critical to local economies. Sec. 1135, entitled Corrosion Prevention, requires coordination with apprenticeship programs and implementing national standard best practices when conducting corrosion prevention activities, providing a stronger workforce and smarter construction decisions. Sec. 1149, entitled Remote Operations at Corps Dams, prevents the use of remote operation activities at Corps navigational lock and dam sites and hydroelectric dams that result in job displacement or that have not addressed cyber and physical security vulnerabilities. Sec. 1153, entitled Challenge Cost-Sharing Program for Management of Recreation Facilities, authorizes a private non-profit entity to partner with the Corps on the operation and management of a Corps' recreation facility, supporting greater use of local expertise, and increasing cohesion between local businesses and the Corps. Sec. 1154, entitled Retention of Recreation Fees, authorizes Corps' recreation facilities to retain additional recreation fees collected at that site. This will ensure that users of recreation facilities reap the benefits of their payments, ensuring local support and providing funding for the sites by local use, not top-down decisions. Title III of the bill includes several provisions which direct the Corps to divest certain federal assets through conveyances, deauthorizations, and land transfers. Their immediate implementation and finalization are strongly in the federal interest, as these provisions generally transfer financial responsibility from the Corps to local government, while boosting local economies and supporting local control. Addressing Water Supply and Water Conservation Needs: WRDA 2024 includes several provisions augmenting the Corps' authority to address the water supply and water conservation needs of the nation, especially in those regions of the country experiencing periods of prolonged drought. Swift implementation and robust funding of these provisions will ensure local communities are adequately prepared to sustain their economies and their quality of life, and to address the public health and safety threats posed by water scarcity. Section 1161, entitled Declaration of Policy, establishes national policy for the Corps to maximize opportunities to utilize the water supply-related authorities of the Corps, and to give full consideration of water supply projects, water conservation measures, and drought resiliency measures at, or in operating, water resource projects. Immediate implementation of this section is critical to allow non-Federal interests to undertake water supply conservation measures to augment local water supplies and to reduce future drought risk. Section 1162, entitled Forecast-Informed Reservoir Operations, directs the Corps to further encourage the use of forecast- informed reservoir operations and related technologies to ensure smart local water management decision-making and provide significant federal and local cost savings, including for disaster prevention. Section 1163, entitled Updates to Certain Water Control Manuals, directs the Secretary to prioritize the update of water control manuals that incorporate the use of forecast informed reservoir operations. Swift implementation of this provision is likely to result in significant, long-term cost savings while also decreasing threats to human health and safety. Section 1164, entitled Emergency Drought Operations Pilot Program, establishes a pilot program for emergency drought operations in certain states, which provides the Corps with increased flexibility to maximize critical local water supplies and better prepare for drought emergencies. Addressing the Unique Needs of Communities: WRDA 2024 contains several provisions to address the specific and unique needs of various communities nationwide. Full implementation and robust funding of these provisions is critical to addressing legacy challenges faced in communities seeking to partner with the Corps to address local water resources challenges. Sec. 1101, entitled Outreach and Access, directs the Corps to better assist locals in accessing federal resources and expertise related to water resources development projects, boosting infrastructure investment and protecting more communities. Sec. 1103, entitled Vertical Integration and Acceleration of Studies, allows greater flexibility in the development of feasibilities studies. This provision removes unnecessary bureaucratic restrictions while ensuring projects of higher quality or broader benefits. Sec. 1104, entitled Minimum Real Estate Interest, provides more flexibility for the Corps to handle easement and access issues. Implementing this additional flexibility will allow the Corps to meet the needs of our communities and the abilities of non-federal partners to deliver any land requirements. Sec. 1107(e), entitled Aquatic Ecosystem Restoration, enhances initiatives for aquatic ecosystem restoration. Implementation of this program will provide benefits to local and Tribal economies. Sec. 1124, entitled Removal of Abandoned Vessels, authorizes the Corps to remove abandoned and derelict vessels that do not impede navigation. Sec. 1132, entitled Improvements to National Dam Safety Program, makes several amendments to the National Dam Safety Program Act. Implementing these changes will help communities to address local needs in training, staffing needs, emergency planning, and dam inspection and monitoring activities. This provision will help smaller communities have access to the program for their repair needs. Sec. 1134, entitled Harmful Algal Bloom Demonstration Program, directs the Secretary to prioritize program activities that reduce nutrient pollution, utilize natural and nature-based approaches, protect wetlands, develop technologies for detecting harmful algal blooms, and combine removal with beneficial uses. Harmful algal blooms devastate local tourism and recreation economies and threaten local water resource needs, including drinking water supplies. Sec. 1139, entitled Ability to Pay, clarifies the Secretary's authority to assess the ability of non-Federal interests to cost-share projects and requires the Secretary to report to Congress on these determinations. Implementing this provision will provide greater flexibility to the Corps and to local communities as they work to address their water resource challenges. Sec. 1140, entitled Tribal Partnership Program, expands the ability of the Corps to partner with Indian Tribes to address local water resources challenges. Sec. 1152, entitled Columbia River Basin, provides authorization for interim pre-planned flood storage to minimize the flood risk in the Columbia River Basin during continued renegotiation of the Columbia River Treaty with Canada. Sec. 1237, entitled Examination of Reduction of Microplastics, proscribes additional Corps authority to reduce the release of microplastics into the environment. Sec. 1303(h), entitled Pilot Programs on the Formulation of Corps of Engineers Projects in Rural Communities and Economically Disadvantaged Communities, extends a pilot program for certain communities that allows a higher federal cost share for such communities. Sec. 1305, entitled Environmental Infrastructure Pilot Program, establishes a pilot program for environmental infrastructure projects meeting certain requirements. This investment supports healthy communities, while creating local jobs and boosting economic growth in small, rural, and economically disadvantaged localities. Sec. 1361, entitled Expenses for Control of Aquatic Plant Growths and Invasive Species, allows greater investment in watercraft inspection and decontamination stations, preventing the spread of aquatic invasive species that can eviscerate local businesses and recreational economies. Project Delivery and Acceleration: WRDA 2024 includes several provisions that intend to deliver more projects for communities with improved project delivery timelines. These provisions provide alternative routes to water resources development projects while still ensuring Corps' expertise and engineering quality. Sec. 1107, entitled Continuing Authority Programs, makes several changes to existing Corps' continuing authority programs (CAPs), allowing more communities to reap the benefits of these small- scale project authorities and address simple water resources issues quickly. Sec. 1108, entitled Stormwater Management Projects, authorizes the Corps to partner with communities to address local stormwater challenges. This provision will deliver expedited stormwater projects for communities, while also providing them with cost savings in water supply and availability. Sec. 1109, entitled Study of Water Resources Development Projects by Non-Federal Interests, provides non-federal entities with additional authority to assist the Corps in delivering water resources development projects, potentially saving federal dollars and improving the speed of project delivery. Sec. 1142, entitled Federal Interest Determinations, clarifies the existing federal interest determinations authority for feasibility studies. Integrating this provision provides better transparency and smarter federal investment in potential projects. __________ Answer. Completed implementation guidance is posted to our public website. Not all provisions required implementation guidance; most provisions can be implemented as written in WRDA 2024. Some Engineering Regulations or other guidance documents are also undergoing revisions. In addition, some provisions will require appropriations prior to OASA(CW) and the Corps taking any action. Question 4. Assistant Secretary Telle, according to information provided by the Corps prior to the hearing, 3,016 USACE employees have signed deferred resignation program (DRP) agreements, (excluding Army Fellows assigned to USACE). Of these, approximately 1,048 have utilized the Office of Personnel Management DRP, and 1,968 have utilized the Department of Defense DRP. During the Q&A period, you responded to a question by saying that Corps is ``aggressively'' hiring people to address Corps' responsibilities. However, according to a news report on the hearing,\1\ Army Corps spokesperson Gene Pawlik said in an email that the agency is still under a hiring freeze and that the agency has only hired staff ``on a very limited basis,'' in accordance with allowable exemptions. --------------------------------------------------------------------------- \1\ See https://subscriber.politicopro.com/article/eenews/2025/09/ 11/army-corps-chief-defends-vance-boating-trip-budget-cuts-00556554 --------------------------------------------------------------------------- Question 4.a. Mr. Telle, is the Corps still under a hiring freeze? Answer. Yes, the Corps is following Department of the Army Civilian Hiring Freeze guidance issued by the Secretary of the Army on August 14, 2025. Question 4.b. What are the ``allowable exemptions'' from this hiring freeze, and where, specifically, has the Corps utilized these exemptions for hiring new personnel to perform Corps' responsibilities? Answer. The Corps has requested and received approximately 1470 exemptions, which were evaluated based on immediate compelling resource needs, criticality of the function to the Army's core mission, and the command's achievement of their FY 2026 reduction objectives. The Corps is aggressively hiring for these positions, consistent with the exemption. Question 4.c. Having lost 3,000 employees, including their institutional knowledge and subject-matter expertise, how will the Corps ensure that it will meet your stated goal of optimizing the quality, speed, and cost of implementing the Corps' civil works missions and responsibilities? Answer. The Corps is committed to recruiting and retaining top talent and is optimizing our workforce to safely deliver quality projects on time and within budget. The Corps will continue to leverage technical training and leader development programs to build the next generation of leaders who understand the business imperatives of quality, speed, and cost. Question to Hon. Adam R. Telle, Assistant Secretary of the Army for Civil Works, Department of the Army, from Hon. Frederica S. Wilson Question 1. Assistant Secretary Telle, a recent report valued the Everglades as a $1 trillion asset generating $31 billion annually. The centerpiece of restoration, the Everglades Agricultural Area (EAA) Reservoir, will send more clean water south and replenish the drinking water aquifer for my district and South Florida. With a new agreement accelerating completion to 2029, ahead of the original 2034 timeline, can you speak to the administration's commitment to meeting this deadline? Answer. My office and the Corps are committed to the Administration's goal of accelerating completion of the EAA Reservoir. Questions to Hon. Adam R. Telle, Assistant Secretary of the Army for Civil Works, Department of the Army, from Hon. Hillary J. Scholten Question 1. I have the great fortune of representing Grand Haven, Michigan, and its workhorse harbor, which supports over 450 jobs. This past summer, Grand Haven's Inner Harbor was due for dredging to ensure its navigability. However, the project's timeline became uncertain due to new state sediment testing requirements. This delay would have been devastating for West Michigan, as this harbor generates over $88 million annually in economic impact and moves critical transportation and agriculture materials into the state. So, I got to work, convening with the Army Corps and the Michigan Department of Environment, Great Lakes, and Energy. After 8 months of advocacy, we finally struck a compromise to dredge Grand Haven's harbor this year in a way that both ensures the harbor's navigability for the good of our economy and protects West Michigan's public and environmental health from the very real threat of PFAS. This underscores how powerful local, state, and federal collaboration can be to truly serve the unique needs of a given community. Assistant Secretary Telle--how can Congress encourage closer collaboration with local and state regulators to prevent project delays and encourage thoughtful permitting decisions? Answer. The Corps always seeks to cooperate closely with state and local regulators to ensure the efficient implementation of civil works projects. In this case, the State's expectation in the case of Grand Haven was that the Corps would comply with new state PFAS sampling guidance immediately, which the Corps had not accounted for. However, the Corps discussed the sampling requirements with senior state officials soon after learning of the inability to obtain a new Section 401 water quality certification for Grand Haven unless PFAS testing was conducted. Question 2. In West Michigan, there is no natural resource more precious to our economy and culture than the Great Lakes. Earlier this year, under the guise of a national emergency executive order, the President directed the Corps to fast-track projects--including by circumventing Clean Water Act protections--if they were deemed to boost our nation's energy supply. Let me be clear: I'm ready to work with my colleagues and the Administration to enact real permitting reform that both expedites decisions and safeguards our waters. However, declaring a national emergency is not the right approach, particularly when some of the ``energy'' projects moving under this executive order include housing developments and museum projects. Assistant Secretary--can you please shed some light on how the Corps is determining which projects are eligible to bypass the Clean Water Act protections, as well as how the Corps is factoring in these projects' associated impacts to our water and wetlands? Answer. Based on direction in EO 14156 ``Declaring an Energy Emergency'', the Corps established Emergency Permitting Procedures for activities associated with energy production including exploration, refining, production and transmission. These projects do not bypass any required review. However, reviews are completed in a manner that supports expedited decisions. Question 3. Michigan's Third Congressional District is home to two small harbors in Grand Haven, as I previously mentioned, as well as in Muskegon. Federal dollars are absolutely critical to maintaining the ports that keep our supply chains up and running smoothly. Particularly at a time when we're working to ramp up domestic production, we need our harbors to be efficient and reliable. That's why I'm concerned that the Army Corps' FY26 budget request does not include a WRDA24 requirement to spend 100 percent of the Harbor Maintenance Trust Fund's collections. Assistant Secretary--since your FY26 budgets does not reflect Congress's call to invest over $1 billion in federal dollars to keep our harbors running, how is the Corps working to prevent harbor closures on light-loading, both of which would increase the cost of imports and exports, ultimately hurting everyday consumers? Answer. The Corps continues to operate and maintain Federal navigation channels and related infrastructure across the Nation. The Corps budget is performance based and focuses on the highest performing projects with high economic, environmental and public safety returns. By focusing on the highest performing projects, the Corps is working to reduce risk and provide optimal reliability of these projects. Since 2015, the total volume of sediment observed above maintained depths at our highest use projects has been reduced by nearly 25%. The Corps also has been able to address maintenance at emerging harbors, which has resulted in the most recent American Society of Civil Engineers Report Card for America's Infrastructure showing an improved grade for Ports of a B rating. Ports received the highest grade of all categories of infrastructure rated in the report. Questions to Lieutenant General William H. ``Butch'' Graham, Jr., Chief of Engineers and Commanding General, U.S. Army Corps of Engineers, from Hon. Eric A. ``Rick'' Crawford Question 1. In my district, I have the pleasure of working with multiple U.S. Army Corps of Engineers districts, including the Little Rock District, the Memphis District, the Vicksburg District, and occasionally, the Tulsa District. I maintain a strong, productive relationship with each of these districts and appreciate the work they do on behalf of Arkansas. The open-door policy I share with each district commander and their teams has proven to be beneficial in addressing issues and finding effective solutions for my constituents. That being said, since I came to Congress in 2011, I have observed a difference in approach and ideology among the districts operating in Arkansas. On one hand, the Memphis and Vicksburg Districts consistently demonstrate a commitment to improving Arkansas. Their cooperative agenda and alignment with the overall goals of Arkansas have led to meaningful progress. On the other hand, the Little Rock District appears to operate with a fundamentally different mindset. Their actions and culture often seem misaligned with the needs and values of Arkansas, and in stark contrast to the collaborative and constructive approach taken by the other districts. At times, it seems as though the Little Rock District goes out of its way to chart a separate course separate from the other districts which seems to be counterproductive to the Corps overall mission. Question 1.a. Can you speak on how you plan to address and improve the internal culture of the Little Rock District so that it better aligns with the expectations of Arkansans and fosters more productive collaboration between the state and stakeholders? Answer. The Corps and the district are committed to incorporating public input as a core element of how the Corps operates and maintains projects across the state. In 2025, the Little Rock District facilitated or participated in 24 collaborative engagements with our Arkansas state partners, fostering a strong working relationship. The Little Rock District remains committed to holding public meetings at or near project offices, with a focus on engaging property owners, including absentee owners, around Corps lakes. The district will continue to prioritize public safety at all recreational locations, particularly during periods of heightened risk. Question 1.b. In your view, would transferring the Little Rock District from the Southwestern Division to the Mississippi Valley Division result in more cohesive operations within the state of Arkansas? What steps would be necessary to evaluate or implement such a change? Answer. Due to their influence on water resources management, watershed boundaries have traditionally played a strong role in defining the boundaries of Corps' District and Division boundaries, including for the Little Rock District in the Southwestern Division. Some District and Division boundaries have evolved over time in response to a combination of geographic or authority-related factors. The enterprise, including the Little Rock District in the Southwestern Division, leverages centralized expertise and oversight, such as centers of expertise, communities of practice, and vertical teams for consistency regardless of the physical location. The process to evaluate and implement a change to a district's boundary is governed by Engineer Regulations (ERs). The process would begin with a formal analysis, guided by ER 5-1-10, to assess if a permanent boundary change is more effective and efficient for the assignment of work. As required by ER 5-1-13, the analysis and proposal for the permanent movement of the district would then need to be submitted to headquarters to obtain formal endorsement. Following headquarters endorsement, the proposal would then require final approval from the Headquarters of the Department of the Army (HQDA) before implementation could begin. Questions to Lieutenant General William H. ``Butch'' Graham, Jr., Chief of Engineers and Commanding General, U.S. Army Corps of Engineers, from Hon. David Rouzer Question 1. Commitment to Acceleration. General Graham--In July 2024, you committed to Members of the North Carolina Congressional Delegation that you would accelerate the Section 203 study schedule for the Wilmington Harbor Channel Improvement project. Why has the study not been accelerated, and why does it remain on track for a Record of Decision in October 2026? Answer. The Section 203 feasibility study was completed by the non- federal interest (NFI) with the Corps providing a review assessment of that study. The Corps is committed to accelerating the Record of Decision (ROD) and has been successful in getting ahead of schedule. The Notice of Intent to develop an EIS was released four months ahead of schedule and the draft EIS was released for public review on September 19, 2025, over a month earlier. The Corps will continue to work expeditiously to complete actions required to accelerate the ROD before October 2026. Question 2. Duplication of Effort. General Graham--The North Carolina State Ports Authority already spent millions to complete a Section 203 study, which was contingently authorized in WRDA 2020 based on Secretary RD James' May 2020 Review Assessment. Why has the Corps spent the past three years--soon to be four--re-evaluating technical and policy issues that were already reviewed, at significant additional taxpayer cost? Answer. The Corps is not re-evaluating technical and policy issues that have already been addressed. The Corps is developing technical information and responding to policy issues not resolved within the original report. The Secretary's office directed that unresolved policy and legal compliance review comments be addressed. Congress conditionally authorized the project through Section 403 of WRDA 2020, subject to responding to the Secretary's review assessment. Nothing within the responses to the review assessment is a duplication of effort. Question 3. Study Timelines. General Graham--How long does it typically take the Corps to conduct a traditional feasibility study, including an Environmental Impact Statement? Why is the Corps' current process for Section 203 studies taking as long--or longer--than traditional feasibility studies? Answer. Per current policy and in reference to applicable law, traditional feasibility studies are, to the maximum extent practicable, expected to be completed within three years from initiation. However, the Secretary can approve a timeline extension when deemed necessary. Feasibility study timelines vary depending on study purpose, area, and complexity. Note, Section 203 feasibility studies are completed by the NFI with the Corps providing a review assessment of that study. The above timeline requirements are not applicable to NFI 203 studies. Question 4. Execution Delays. General Graham--The project was contingently authorized in WRDA 2020, yet the Corps did not execute a cost-share agreement until October 2022. Why did it take nearly two years to reach that point, and why will it take four more years to issue a Record of Decision? Answer. The project was contingently authorized in WRDA 2020, subject to addressing economic, engineering, and federal environmental compliance responsibilities. A proactive scope of work was developed in coordination with North Carolina State Ports Authority (NCSPA) to respond to the ASA(CW) Review Assessment in FY 2021. Upon receipt of appropriations in FY 2022, the district finalized and executed the scope and associated cost sharing agreement (CSA) with NCSPA on October 25, 2022. The scope to fully respond to the Review Assessment was coordinated with the NCPA and the ASA(CW) and is currently ahead of schedule. Question 5. Commitment to Acceleration (Wilmington). General Graham--Will you commit today to accelerating the Wilmington Harbor Channel Improvement project schedule so that a Record of Decision is issued before October 2026? Answer. Yes, I commit to accelerating this effort and have completed the draft documentation ahead of schedule. We are working to move efficiently through the remaining responsibilities. Submission of a legally sufficient and policy compliant document package, to include a draft ROD, is scheduled before October 2026. Question 6. Broader Reform of Section 203 Reviews. General Graham-- Other ports are facing the same lengthy Section 203 review process. Will you commit to working with this Committee to accelerate and reform the Corps' review of Section 203 studies, so that critical port infrastructure projects can be delivered more efficiently? Answer. Yes, I commit to working with this Committee. An update to Engineering Regulation 1165-2-209: Studies of Water Resources Development Projects by Non-Federal Interests, the guidance for Section 203, is underway. Questions to Lieutenant General William H. ``Butch'' Graham, Jr., Chief of Engineers and Commanding General, U.S. Army Corps of Engineers, from Hon. Rick Larsen Question 1. General Graham, in your oral testimony, you commented on changes to the design threshold that the Corps will implement before it submits project studies to Congress for authorization. You noted that the Corps will not submit completed studies until a certain threshold is reached--which you highlighted will be ``around the 35 percent level.'' Section 1001 of the Water Resources Reform and Development Act (WRRDA) of 2014, as amended, establishes a goal of completing feasibility studies within 4 years, at a cost of not to exceed $5 million, and provides the Corps with the ability to extend that timeframe by an additional 3 years for certain listed exceptions. Question 1.a. Please describe how the policy change on design threshold is consistent with the statutory requirements of section 1001 of WRRDA 2014. Answer. If a study may warrant an exception under Section 1001(b) of WRRDA 2014, as amended, and applicable agency polices for additional funding or time needed to complete, including to achieve a thirty-five percent level of design before completion, any determination is made on a study-by-study basis in coordination with the non-federal interest and approval from the Assistant Secretary of the Army for Civil Works. Question 1.b. How will the policy change in design threshold affect the potential scope, or statutory timeframe for completion, of future feasibility studies? Answer. Robust engineering and design during feasibility and prior to initiating construction are a key component in delivering projects as formulated and within costs identified as part of a project's recommendation. The Assistant Secretary of the Army for Civil Works must approve any additional funding or time needed to complete a study, including achieving a 35% level of design before completion, is made on a study-by-study basis. Further, any request for additional time and funding will require coordination with the non-federal interest. Question 2. Section 105 of WRDA 1986 establishes the general 50-50 cost share for feasibility studies, split between the Corps and non- federal interests. Question 2.a. How will the policy change on design threshold affect the non-federal interests cost share for feasibility studies prior to submission to Congress for authorization? Answer. Any potential increase in total study cost resulting in an increase in the corresponding non-federal interest's share for that study, including to achieve a desired design threshold that allows for greater confidence in project delivery, is coordinated with the non- federal interest. Where an exception for additional time and funding is proposed under Section 1001(b) of WRRDA 2014, as amended, and applicable agency policies, it will require approval from the Assistant Secretary of the Army for Civil Works. Question 2.b. Will changing the design threshold expand that portion of the design phase that is designated as pre-construction engineering and design (PED) that will be required before a project is submitted to Congress for authorization? Please describe the Corps' expectations of that expansion, and any associated change in non- Federal interests' costs. Answer. Expediently delivering studies and projects to communities is a priority within the Civil Works program. Any potential increase in total study cost resulting in an increase in the corresponding non- federal interest's share for that study, including to achieve a desired design threshold that allows for greater confidence in project delivery, is coordinated with the non-federal interest. A proposed exception for additional time and funding under Section 1001(b) of WRRDA 2014, as amended, and applicable agency policies, will require approval from the Assistant Secretary of the Army for Civil Works. The Preconstruction Engineering and Design (PED) phase follows the completion of the feasibility report and associated decision documents. Any potential change to design thresholds during the PED phase is assessed on a project-by-project basis. Cost sharing in PED varies depending on the purpose of a project. It may also depend on the individual project authorization or on the funding mechanism to implement the recommended plan. Question 3. In July 2025, the Corps sent the Committee its estimate for expected completion of the following Chief's Reports that might fall within the formulation timeframe for a new WRDA for 2026. Can you provide an updated estimated schedule for these studies, factoring in this change in design threshold? Question 3.a. Amite River & Tributaries East of Miss River, LA Answer. Study paused. Question 3.b. Little Goose Creek, Sheridan, WY Answer. May 29, 2026. Question 3.c. Buffalo Bayou & Tributaries Resiliency Study, TX Answer. December 31, 2025. Question 3.d. Columbia River Turning Basin Navigation Improvements, WA & OR Answer. September 26, 2025. Question 3.e. Kentucky River, Beattyville, KY Answer. December 12, 2025. Question 3.f. Lower Osage River, at Lock and Dam No.1, MO Answer. May 15, 2026. Question 3.g. Gulfport Harbor, MS Answer. April 17, 2026. Question 3.h. Nassau County Back-Bays, NY (Sandy Focus Area, 115- 123) Answer. Study paused. Question 3.i. Watertown, SD Answer. May 5, 2026. Question 3.j. Lower Missouri Basin--Jefferson City-142, MO Answer. May 8, 2026. Question 3.k. New Jersey Back-Bays Coastal Resilience Study, NJ Answer. No longer expected in 2026. Question 4. In July 2025, the Corps sent the Committee its estimate for expected completion of the following Director's Reports that might fall within the formulation timeline for a new WRDA for 2026. Will the policy change on design threshold affect the estimated schedule for the following Director's Reports? Question 4.a. Inner Harbor Navigation Canal Lock Replacement, LA Question 4.b. Pearl River Basin Question 4.c. North Desoto County, MS Answer to questions 4.a.-4.c. No, there are no significant impacts to the schedules for these project reports. Questions to Lieutenant General William H. ``Butch'' Graham, Jr., Chief of Engineers and Commanding General, U.S. Army Corps of Engineers, from Hon. Frederica S. Wilson Question 1. I have concerns about the proposed Southland Rock Mine, which is planned to be located adjacent to the $4 billion Everglades Agricultural Area Reservoir and involves blasting more than 8,000 acres of rock. Has the Army Corps evaluated what the impact of this proposed project will be? Answer. In response to initial inquiries regarding permitting the proposed project, the Corps is reviewing available information and gathering detailed plans and specifications that will facilitate further analysis to determine whether the proposed project requires a Department of the Army permit or could impair the usefulness of the EAA project. The Corps has concerns about the proposed project's impacts on Everglades restoration. Some concerns relate to the following: (1) water management operations, (2) seepage, and (3) regional/system water availability. Question 2. What role is the Corps playing in advancing cybersecurity protections as part of its resilience projects and WRDA implementation? Answer. The Corps has established a Critical Infrastructure Cybersecurity Mandatory Center of Expertise (UCIC) to provide policy and guidance to advance the cybersecurity of the organization's Operational Technology (OT) systems. The UCIC provides services that ensure new and existing OT systems, which are owned and operated by the Corps, are secured against internal and external cyber threats and authorized according to applicable Department of War and Army regulations. When the Corps is the design and/or construction agent, the UCIC will ensure systems are delivered with appropriate risk-based cybersecurity. For Civil Works owned and operated OT systems, mandatory services are executed using centrally provided funds from the Corps Headquarters' Operations and Maintenance Remaining Item funding. For all others, reimbursable funds are provided by the organizations that request the service. Questions to Lieutenant General William H. ``Butch'' Graham, Jr., Chief of Engineers and Commanding General, U.S. Army Corps of Engineers, from Hon. Eleanor Holmes Norton Question 1. I am deeply concerned that the federal government, including the Army Corps of Engineers (Corps), is not prioritizing identifying a secondary drinking water source and additional drinking water storage capability for the nation's capital. The Potomac River is the only source of drinking water for the District of Columbia, the Corps is responsible for supplying D.C.'s drinking water and there is only one day of backup drinking water supply. If the river became unusable for drinking water, which could happen at any time, whether through man-made or natural events, the federal government, D.C. residents and the national capital region's economy would be at risk. In 2022, at my request, Congress authorized the Corps to conduct a feasibility study on a secondary drinking water source and additional drinking water storage capability for D.C. Question 1.a. Is identifying a secondary drinking water source and additional drinking water storage capability for D.C. a high priority for the Corps? Answer. The Corps recognizes the importance of the secondary source study and additional storage capability for the Nation's Capital. The Corps initiated the feasibility study and is working towards identifying solutions. Question 1.b. What steps has the Corps taken to prepare to respond in the event the Potomac River became unusable for drinking water and what is the status of the feasibility study? Answer. Washington Aqueduct has two intakes on the Potomac River, namely, Great Falls and Little Falls. Due to the differences in geographic locations, these separate intakes provide some time for WA to fill up its raw water reservoirs in the event of an emergency. Additionally, annual tabletop exercises, coordinated by Metropolitan Washington Council of Governments, are conducted with all water utilities in the region to improve communications and coordination/ collaborations. The feasibility study reached the Alternatives Milestone Meeting on June 12, 2025, and the agencies are working on alternative screening. Question 2. In 2020, an unexploded ordnance was discovered in Fort Totten Park. At that time, I was assured by the National Park Service (NPS) that it had conducted a thorough investigation for additional munitions. However, three years later, two WWI-era munitions were discovered in a different location of the park. Fort Totten Park is in a residential neighborhood. It is imperative that the Corps work with NPS to investigate the park for munitions and environmental damage, which is why I have repeatedly requested funding to support this effort. What is the status of the investigation at Fort Totten Park? Answer. The Corps stands ready to support investigations and/or remedial actions on the National Park Service (NPS) land at Fort Totten Park. Questions to Both Witnesses--Hon. Adam R. Telle, Assistant Secretary of the Army for Civil Works, Department of the Army, and Lieutenant General William H. ``Butch'' Graham, Jr., Chief of Engineers and Commanding General, U.S. Army Corps of Engineers--from Hon. Mike Collins Question 1. In its decision in Sackett v. EPA, the United States Supreme Court held that, for Federal jurisdiction under the Clean Water Act to apply, a waterbody must be ``indistinguishable'' from water of the United States (WOTUS).\1\ However, some United States Army Corps of Engineers (Corps) Districts, particularly the Jacksonville District, seem to be disregarding this requirement, and asserting jurisdiction over waters that are clearly distinguishable by distance and other physical characteristics. --------------------------------------------------------------------------- \1\ Sackett v. EPA, 598 U.S. 651 (2023). --------------------------------------------------------------------------- Could you clarify whether such assertions of jurisdiction are consistent with the Supreme Court's ruling in Sackett, and what recourse may be available when a District fails to apply the ``indistinguishable'' standard? Answer. The Corps is implementing the definition of the Clean Water Act term ``waters of the United States'' consistent with the applicable regulations and guidance provided by EPA and the Department of the Army. Information regarding the applicable regulations and guidance is available on EPA's website at: https://www.epa.gov/wotus. An affected party who has received a Corps approved JD and disagrees with the Corps decision can pursue an administrative appeal of the Corps decision if they believe that the Corps committed a procedural error; incorrectly applied the applicable law, regulation, or policy; omitted a material fact, or relied on incorrect data. Question 2. The Institute of Water Resources and the Waterborne Commerce Statistics Center is undergoing a modernization of the 1990s era Microsoft Disk Operating System (MS-DOS). What is the status of that project and what is the expected completion timeframe? Answer. The Center uses a suite of software applications that have been periodically updated to function on contemporary Windows and Linux operating systems. The effort to transition the Waterborne Commerce Statistics data systems to a cloud-based platform is ongoing. Core components of the data system were deployed to the cloud in late 2024 with additional functionality implemented in production in fiscal year 2025. Development and testing of remaining modules required for publication of data are ongoing and slated for deployment to the cloud by the fourth quarter of 2026. Question 3. Section 1154(a) of WRDA 2018 requires the Corps to review the backlog of operation and maintenance projects, producing a report by 2020. Do you have an update on the status of this report? Answer. The mix of funded and unfunded operation and maintenance work, and the priority of each work package, changes from year to year. Following issuance of the FY 2026 Corps work plan and the FY 2027 Budget, the Corps will prepare an estimate of any additional major work that it has identified but not yet proposed for funding. Question 4. In April of 2021, the Corps published an agency guidance document (Engineer Circular No. 1165-2-218) that it intended to establish and fulfill specific performance metrics, conduct annual audits, and deliver recurring independent peer reviews to continually assess and improve levee safety program efficacy and accountability. To help determine its net value to overall national flood protection and the guarantors of levee and flood safety, local project sponsors, please provide the subcommittee with the following: Question 4.a. The established Federal levee safety program performance metrics, annual audits, and independent peer review reports; Answer. In a memorandum dated September 15, 2023, the Corps established metrics to guide and monitor the effectiveness of its implementation of the levee safety program. The memorandum is based on the activities and concepts described in Engineer Circular 1165-2-218. The metrics are grouped into broad categories: Program Management-- includes maintaining qualifications of program leads and governance to promote consistent oversight of the program; Levee Inspections-- includes engaging levee sponsors and meeting minimum frequency of inspections and timeline to finalize reports; Risk Assessments-- includes engaging levee sponsors in the process and frequency of updates; Recommended Actions--includes providing risk management actions to levee sponsors that inform operations, maintenance, repair, replacement, and rehabilitation activities; Sharing Information-- includes working with levee sponsors on tracking recommended actions and updating publicly available information in the National Levee Database; and Data Management--ensuring that the identified priority data in the National Levee Database have been completed. Half of the Corps divisions have initiated the annual programmatic audits, either as part of the Army Organizational Inspection Program, which is a comprehensive process for coordinating various reviews to identify, prevent, and eliminate problem areas, or a separate process. The divisions evaluate two to three districts each year against a series of items linked back to the programmatic metrics and interactions with levee sponsors. It is still the intent of the Corps to initiate an independent review of the Corps Levee Safety Program; however, one has not been conducted yet. Question 4.b. Information on how the Corps coordinated with local sponsors in the establishment and implementation of levee safety program performance metrics, annual audits, and independent peer review; and Answer. The programmatic metrics and audits are meant primarily to guide and monitor the effectiveness of Corps actions under the levee safety program. The metrics are directly aligned with the activities and concepts described in Engineer Circular 1165-2-218. A Federal Register notice was issued announcing the availability of the draft Engineer Circular for public comment from February 2020 to July 2020. In addition, USACE issued email and social media announcements to stakeholders to solicit feedback and hosted national and regional webinars. Regional webinars had the purpose to directly reach out to levee sponsors to hear their concerns and support and identify opportunities to improve the program activities and relationships. USACE also maintains a dedicated email address, EC218@usace.army.mil, to receive any ongoing questions or comments on the Engineer Circular. Levee safety program activities are accomplished by a shared coordinated effort between the Corps and levee sponsors to inform levee sponsor efforts to fulfill daily responsibilities on the levee structure and prioritize actions to manage the future performance of the levee. The program activities are intended to improve the effectiveness of risk management decisions. This continuous working relationship also provides levee sponsors opportunities to provide input on the implementation of program activities. Question 4.c. The list of local sponsors that were involved in the development of levee safety program metrics, auditing, and independent review. Answer. The Corps engaged many local sponsors to seek feedback on Engineer Circular 1165-2-218. From the formal public comment period from February 2020 to July 2020, a total of 54 responses were received by online response form, email, or letter submissions with 514 individual comments. Out of the total commenters, thirty-nine percent affiliated themselves as levee owner/operators. Not all comments received were provided through the formal Federal Register notice or could be attributed to a specific local sponsor. However, stakeholders who submitted comments through the Federal Register can still view them at https://regulations.gov under docket number COE-2020-0003. Based on the comments, the entire document was reorganized to be shorter and simpler with clarifications for applicability, roles and responsibilities, and local sponsor expectations for engagement. The revised document was posted as draft on a public website, and a total of 22 webinars/in person stakeholder sessions were conducted to seek any additional feedback on the revised draft. No additional significant comments were received, and Engineer Circular 1165-2-218 was finalized in 2021. Question 5. The Corps has funded a range of levee safety efforts to prevent future project failures. What has the Corps done to ensure that levee safety program activities, including post-Katrina guidance and standards for levee systems: Question 5.a. Reflect local risk preferences, Question 5.b. Are transparent, collaborative, and reproducible using data and methodologies that are fit for public policy, Question 5.c. Account for local willingness to pay, Question 5.d. Are producing tangible, net beneficial project reliability gains and flood protection supported by a majority of local sponsors and communities, and Question 5.e. Balance resource expenditure against the pursuit of potentially diminishing returns in this space? Answer to questions 5.a.-5.e. The Corps has been working to address levee stakeholder concerns. Some of the most common feedback from stakeholders includes levee practices should be scalable to reflect the capabilities of the levee sponsor and the affected community; the past performance of the levee should also be considered; and there needs to be improved consistency and transparency in data collection. Based on this feedback, the Corps has recommended the use of risk assessments to inform local decisions on how best to plan, design, and manage their levee systems. A risk assessment is an analytical method used across a wide variety of industries to comprehensively understand factors that may impact safety. Each levee is distinct, designed with varying heights and features based on factors such as expected flood levels, local landscapes, and the potential impacts of flooding. Some levees reduce the flood risk of areas that face frequent flooding, while others help to shield regions that experience floods infrequently. Coastal levees are exposed to the harsh conditions of high winds and waves from hurricanes, while those in drier climates may face rapid and infrequent flood events. Levees are constructed by a mix of private and governmental entities, and many have multiple owners or operators. Some were built in the early 1900s and have been retrofitted over time using various engineering methods, while others were designed with more modern techniques. Risk assessments help consolidate the unique factors of each levee into a comprehensive evaluation. This provides a clearer understanding to guide the design of new levees and modifications to existing levees; and to enable local communities to establish their own priorities for maintenance, repairs, and future investments. Current Corps levee guidance emphasizes the involvement of levee sponsors and local communities. These groups are integral to the levee project teams, bringing invaluable local and historical knowledge as well as offering insights into community awareness, values, and priorities regarding flood risk management. Their input helps ensure that results and recommendations are both relevant and feasible. The risk assessment includes an estimate of the level of flood risk reduction provided by the levee allowing for better-informed decisions by levee sponsors on weighing the costs of potential levee improvements or other measures and the flood risk reduction benefits that they offer. The Corps strives for public transparency in its processes for developing levee system procedures and emphasizes the benefits of stakeholder involvement and information sharing related to levees. To this end, the Corps has implemented engagement strategies and has actively sought stakeholder feedback to improve its guidance and tools. One example is the National Levee Database, which the Corps manages as a searchable inventory of all known levee systems across the Nation. Initially launched to the public in 2018, the database has recently been enhanced based on stakeholder input. The updates include more detailed information on data sources, clearer instructions for submitting or updating data, a new search-by-address feature, and login procedures that provide differentiated access for various users (such as the public versus levee sponsors). Question 6. Congress has taken steps to help ensure that annual levee safety program funding is used by the Corps to deliver tangible, location-specific levee project reliability improvements in close collaboration with willing local sponsors. In keeping with Sec. 131 of WRDA 2020, Congress included a directive and funding in the Fiscal Year 2024 Energy and Water Development Appropriations Act to facilitate Corps identification of levee-specific design and maintenance deficiencies and, where necessary, economic remedy options. Where has the Corps used the WRDA 2020 Section 131 authority and Fiscal Year 2024 funding to pursue these location-specific levee reliability improvements? Answer. Section 131 of WRDA 2020 amended a subset of activities under Title IX of WRDA 2007 (33 USC 3303) related to the National Levee Database and the inventory and inspection of levees. The report accompanying the enacted 2024 appropriations included $1 million to implement section 131. Section 131 authorizes the Corps to identify specific engineering and maintenance deficiencies, recommend remedial actions to the levee owner, and, if requested by the owner of a non- federal levee, to provide a detailed cost estimate for any recommended actions to remedy those deficiencies. The Corps has provided such a cost estimate, where requested, for 27 non-federal levees in the states of California, Iowa, Louisiana, Ohio, Oregon, and Texas. Question 7. There has been concern that the Corps' local project partners, the general public, and Congress, frequently lack access to agency data, methodologies, decision tools, and public policy formulation. The absence of these foundations can create gaps that can amplify bias, obscure mistakes, result in project cost overruns and delays, erode trust in agency decision making and performance, and diminish flood protection. Please provide examples of the steps taken by the Corps and its levee safety program to ensure transparency, reproducibility, and intergovernmental collaboration, specifically in regard to the Draft National Levee Safety Guidelines proposal issued by the Corps and FEMA on April 1, 2024. Answer. The Corps conducted three phases of broad stakeholder feedback using a combination of methods including meetings, webinars, email announcements, Federal Register notices, and website comment forms. In addition, a separate set of targeted activities was accomplished to better understand the needs of Tribes. The following is the timeline for the development of the April 2024 draft version of the National Levee Safety Guidelines: 2015-2017: Conducted literature review (1,500+ documents). 2018-2020: Coordinated with 17 federal agencies to develop Principles of Levee Safety for Federal Agencies to initiate the discussions for national guidelines. 2021: Established an oversight team for the Guidelines consisting of eight federal agencies. Jan-March 2022 (Phase 1): Gathered stakeholder/Tribal/ public feedback on the Guidelines' purpose and topics. Activities included posting a Federal Register notice; direct emails to the ``opt- in'' list; social media posts; and conducting nine virtual workshops. 2022-2023: Selected final chapter topics and developed initial content. April-June 2023 (Phase 2): Gathered stakeholder/Tribal/ public feedback on level of detail, scalability, and an example chapter. Activities included posting a Federal Register notice; direct emails to the ``opt-in'' list; social media posts; conducting eight public webinars; hosting eight in-person meetings across the country (four meetings directly for levee owners/operators); conducting two workshops on vegetation management on levees; and conducting one workshop with representatives from 16 states. Spring 2023: Federal agency review of full draft of the Guidelines. April-August 2024 (Phase 3): Gathered stakeholder/Tribal/ public feedback on full draft. Activities included posting a Federal Register notice; direct emails to the ``opt-in'' list; social media posts; conducting nine webinars; and presenting at six conferences. Over 900 comments were received on the draft from individuals associated with federal, state, local government, Tribes, professional organizations, private sector, and non-governmental organizations. Question 8. One of the biggest Corps projects in the Nation, the Sabine Pass to Galveston Bay Coastal Project in Texas, or ``S2G'' project, was fully funded in the Bipartisan Budget Act of 2018 (BBA 2018) at $3.9 billion. Since enactment, the S2G project cost estimate has increased by 182 percent and is now close to $11 billion. One of the three local project sponsors pulled out in 2024 citing the significant cost overruns and delays. Question 8.a. Did the Corps make a good-faith effort to ensure that costs were included prior to giving Congress project estimates? If so, what efforts were taken? Answer. Yes. The Corps incorporated cost information from multiple sources, including other districts and non-government construction efforts, during the feasibility study. However, uncertainty was acknowledged in the Chief's Report and costs at the time of authorization were based on a preliminary conceptual level of design. Question 8.b. Did project adaptability requirements and more stringent design criteria contribute to this? Answer. While adaptability was conceptually included at the feasibility stage, the level of detail and engineering required to fully implement those features was not developed until the Preconstruction Engineering and Design phase. Its implementation during later design phases required more robust features, particularly in the foundations of floodwalls and other hardened structures--to allow for future modifications without full reconstruction. In addition, updates to design guidance and improved data (e.g., rainfall, surge, and wave conditions) resulted in increased size, strength, and complexity of project features. In some instances, incorporating adaptability into design refinements resulted in more robust foundation systems, deeper elements, and increased material quantities than the feasibility level conceptual design. Therefore, while adaptability was always part of the project intent, the refinement and implementation of those requirements at later design stages led to additional upfront costs. These costs are intended to prevent significantly higher future costs and disruptions by allowing floodwalls and hardened features to be raised rather than replaced. S2G is one of the largest and most complex coastal storm risk management projects undertaken by the Corps, spanning multiple systems across a highly developed and industrialized region. As design advanced beyond the feasibility level, the incorporation of refined coastal modeling, updated rainfall data (e.g., NOAA Atlas 14), and evaluating the acceptable risk of combined rainfall and surge resulted in larger and more robust features than originally conceptualized. Additionally, the real estate requirements, utility relocations, and geotechnical challenges associated with soft coastal soils further contribute to increased costs in ways that are more pronounced than in smaller or less complex projects. Importantly, the magnitude of cost growth for S2G remains in line with other large, complex projects across the portfolio. Many projects authorized or funded under the Bipartisan Budget Act of 2018 (BBA18) have experienced similar cost growth--often doubling or tripling from initial feasibility estimates--as they advanced into more detailed design and incorporate updated data, refined engineering analyses, and current construction market conditions. While the percentage growth is consistent with other major projects, the absolute dollar increase appears larger due to the overall scale of the project. Question 8.c. Were these requirements coordinated with the local sponsors? Answer. Yes, the local non-federal sponsors were actively engaged and informed of all project requirements and activities. Question 8.d. Do local sponsors have the ability to opt out if projects, like S2G, become unaffordable with eroded net benefits? Answer. While non-federal sponsors generally do not have the ability to unilaterally opt out of a Project Partnership Agreement, a non-federal sponsor could seek to negotiate a change to that agreement. Non-federal sponsors have responsibilities that impact project delivery, including cost sharing, real estate acquisition, utility relocations, and operation and maintenance of completed projects. The Corps works with non-federal sponsors to develop project construction schedules, which can help to address their concerns in some cases. However, where a local sponsor cannot or is no longer willing to pursue the project as authorized, the Corps can suspend or terminate construction or can recommend a study to evaluate options to modify the project. Question 8.e. How does the Corps intend to ensure that it can deliver good and affordable flood projects on time and on budget? Answer. The Corps is working to deliver its projects on time and on budget, including by ensuring that each of its future project proposals will have a sufficiently advanced design and associated cost estimate prior to issuing a Chief's or Director's report. Question 9. In H. Rept. 119-213, the Corps was directed to establish a Levee Owners Board (Board) to improve communication and collaboration between levee owner/operators from around the nation and the Corps. The Board is also being established to provide its independent views and judgment on the net economic impacts of new Federal requirements and procedures, including requirements and procedures related to levee inspections and accreditation. Finally, Congress is interested in receiving the independent views of the Board regarding the overall effectiveness of the Corps' levee safety program, in operation since 2006, and the separate interagency levee safety initiative, established by section 9005 of WRDA 2007. Question 9.a. Do you agree that viable, economic flood protection involving structural flood control requires integral decision-making involvement by non-Federal project sponsors? Answer. The involvement of non-federal sponsors helps to ensure that the flood risk reduction measures proposed by the Corps are economically feasible, appropriate, and sustainable in the long term. Question 9.b. When do you intend to stand up any sort of Levee Owners Board, comprised of non-Federal project sponsors, and, if so, when will it be up and running? Answer. The Army is aware that some levee owners have expressed concerns and will consider the Committee's request. Questions to Both Witnesses--Hon. Adam R. Telle, Assistant Secretary of the Army for Civil Works, Department of the Army, and Lieutenant General William H. ``Butch'' Graham, Jr., Chief of Engineers and Commanding General, U.S. Army Corps of Engineers--from Hon. Eric A. ``Rick'' Crawford Question 1. Separate from the National Levee Safety Initiative authorized by Congress in 2014 at 33 USC Sec. 3303a, the Corps has operated its own Levee Safety Program for 19 years and has taken a number of actions. These actions include internal agency risk assessments of approximately 1500 Corps program levees; identified, inspected, and inventoried Corps program levees and uploaded data into the National Levee Database website; categorized levees based on the amount of treasure and population they protect; and issued numerous guidance documents, standards, and regulations affecting levee systems and protected communities, including an 886-page National Levee Safety Guidelines proposal assembled with FEMA and others that is expected to go final this year. There has been a lot of activity to develop Corps performance standards and ratings for Corps-program levees that are operated and maintained by a local sponsor. Following Hurricane Katrina, Congress called for more advisory-level information on levees, including their location, ownership, and condition. Included in an April 2021 Corps guidance document, the Corps promised to establish specific performance metrics, conduct annual audits, and pursue recurring independent review to assess performance of the Levee Safety Program itself to help the public, Congress, and the Corps to evaluate its effectiveness, efficiency, and net benefit to the Nation. Question 1.a. Can you provide me with detailed information on who is rating the Corps raters? Answer. The Command organization of the Corps ensures that the resources, personnel, projects, and operations of the civil works program are managed efficiently, ethically, and in accordance with legal and regulatory requirements. Each level of leadership in the Corps is accountable for the people who work under its command, and ensures that they are properly trained, equipped, and rated based on their performing their duties in a manner that will maintain and further the integrity and quality of our mission. Question 1.b. Were those performance metrics for the Corps Levee Safety Program, promised in 2021, ever established? If so, can you provide me with a copy of the published Program metrics, annual audit results, and the independent review reports? Answer. In a memorandum dated September 15, 2023, the Corps established metrics to guide and monitor the effectiveness of its implementation of the levee safety program. The memorandum is based on the activities and concepts described in Engineer Circular 1165-2-218. I have attached a copy of this memorandum. [Editor's note: The aforementioned 27-page memorandum dated September 15, 2023, is retained in committee files.] The metrics are grouped into the following broad categories: Program Management--includes maintaining qualifications of program leads and governance to promote consistent oversight of the program; Levee Inspections--includes engaging levee sponsors and meeting minimum frequency of inspections and timeline to finalize reports; Risk Assessments--includes engaging levee sponsors in the process and frequency of updates; Recommended Actions--includes providing risk management actions to levee sponsors that inform operations, maintenance, repair, replacement, and rehabilitation activities; Sharing Information--includes working with levee sponsors on tracking recommended actions and updating publicly available information in the National Levee Database; and Data Management--ensuring that the identified priority data in the National Levee Database have been completed. Half of the Corps divisions have initiated the annual programmatic audits, either as part of the Army Organizational Inspection Program, which is a comprehensive process for coordinating various reviews to identify, prevent, and eliminate problem areas, or a separate process. The divisions evaluate two to three districts each year against a series of items linked to the programmatic metrics and interactions with levee sponsors. Because these audits are part of a larger evaluation, results for a specific district for Corps Levee Safety Program activities can be extracted upon request at a later time. The Corps still intends to initiate an independent review of its Levee Safety Program; however, one has not been conducted yet. Question 2. In its most recent ``Value to the Nation'' report, the Corps indicates that flood projects built and maintained with local sponsors over the decades have prevented more than $1 trillion in flood damage and that these projects yield an average 12 to 1 return on investment (ROI). The seven-state Mississippi River and Tributaries Project, independent of the national ROI figure, reports an extraordinary 114 to 1 ROI. In both cases, the cumulative ROI data goes back several decades, long before the establishment of our levee safety bureaus. Can you provide detailed data on what incremental, quantifiable benefits, and relatable tangible outputs the Corps Levee Safety Program has contributed to the flood damage reduction outputs generated by the projects and their local sponsors? Answer. There are over 2,300 communities, 23 million people, and $2 trillion in property value behind the more than 6,500 levee systems across the United States. Many of these levees span multiple jurisdictions, have multiple sponsors, and involve various levels of government. The Corps is authorized to assist communities in several ways, including planning, designing, constructing, and modifying levees; assessing the condition of existing systems; operating and maintaining levees; supporting emergency response efforts; providing technical resources; and managing the National Levee Database. The Corps' Levee Safety Program serves as an organizational framework to improve the consistency, efficiency, and effectiveness of its levee- related responsibilities nationwide. The Corps' Levee Safety Program provides significant added value to the Nation. The program contributes to flood damage reduction by improving levee practices, enhancing communication with local sponsors and across Federal agencies, and sharing lessons learned. The program also uses inspections and risk assessments to boost public awareness and enable communities to identify potential improvements and establish their priorities. Local sponsors, working in partnership with the Corps, are key to this entire effort. For example, the levee safety program: Establishes Qualifications and Decision-Making Frameworks: Defines the qualifications of key technical decision-makers and creates a clear framework to resolve issues and address complex technical cases, supporting efficient project delivery. Facilitates Knowledge Sharing: Promotes the exchange of knowledge and expertise across the agency through continuous interaction, collaboration, and problem-solving. Coordinates Across Corps Programs: Ensures effective coordination between levee activities and other Corps programs, such as dam safety, emergency management, flood risk management, and planning. Maintains State-of-the-Art Engineering Practices: Manages and updates levee-related guidance and procedures to apply the latest engineering standards. Supports Technical Competency: Develops and provides levee-related training for both internal Corps staff and external partners. Innovates Assessment Tools: Supports the creation and improvement of tools to assess and manage levee data based on user needs. Establishes Governance for Oversight: Implements a governance structure to monitor, assess, prioritize, and improve the Corps' levee- related activities. Facilitates Risk-Informed Decision Making: Through the levee risk assessment process, in collaboration with levee sponsors, unique data, findings, and recommendations are devised to assist in flood risk management. Provides Support to Levee Sponsors and Communities: Supports levee sponsors and communities with technical assistance, for example with communication efforts or emergency preparedness planning. Question 3. Under the Government Performance and Results Act, the Corps Levee Safety Program has filed annual performance and accountability reports tabulating the number of levee inspections, risk assessments, levee safety classifications, and regulations and guidance it generated for a given year. Question 3.a. Please quantify how much these actions taken have made us safer, specifically what quantifiable benefits are attributed only to the Corps Levee Safety Program, not the projects and local sponsors. Answer. There are over 2,300 communities, 23 million people, and $2 trillion in property value behind the more than 6,500 levee systems across the United States. The levee safety program operates in tandem with the projects that the Corps and others have built and with the ongoing work of non-federal sponsors. It is not possible to quantify separately the economic benefits of the component parts of this integrated effort. Question 3.b. Please provide me with a detailed answer on how many lives the Levee Safety Program has saved since its inception. Answer. There are over 2,300 communities, 23 million people, and $2 trillion in property value behind the more than 6,500 levee systems across the United States. The levee safety program operates in tandem with the projects that the Corps and others have built and with the ongoing work of non-federal sponsors. It is not possible to quantify separately the safety benefits of the component parts of this integrated effort. Question 3.c. Please provide me with data on how much flood damage has been prevented by the Levee Safety Program. Answer. There are over 2,300 communities, 23 million people, and $2 trillion in property value behind the more than 6,500 levee systems across the United States. The levee safety program operates in tandem with the projects that the Corps and others have built and with the ongoing work of non-federal sponsors. It is not possible to quantify separately the flood damage reduction benefits of the component parts of this integrated effort. Question 3.d. What actions by the Levee Safety Program have resulted in quantifiable project performance improvement? Answer. The Corps' Levee Safety Program serves as an organizational framework to improve the consistency, efficiency, and effectiveness of all of the levee-related responsibilities and activities of the Corps nationwide. Question 3.e. From 2016 through 2024, how many flood projects did the Levee Safety Program insist to be included in Section 7001 reports transmitted by the Secretary to Congress? Answer. The Levee Safety Program is not involved in preparation of the Section 7001 reports. These reports, authorized in Section 7001 of the Water Resources Reform and Development Act of 2014 (WRRDA), as amended, present proposals by non-Federal interests for changes to existing project or study authorities, new project or study authorities, and changes to the environmental infrastructure authorities of the Corps. Questions to Both Witnesses--Hon. Adam R. Telle, Assistant Secretary of the Army for Civil Works, Department of the Army, and Lieutenant General William H. ``Butch'' Graham, Jr., Chief of Engineers and Commanding General, U.S. Army Corps of Engineers--from Hon. Bruce Westerman Question 1. As I am sure you are aware, the McClellan-Kerr Arkansas River Navigation System is a major inland waterway system in the United States that provides a navigable shipping route from the Tulsa, Oklahoma area to the Mississippi River, running through parts of Oklahoma and Arkansas. This important waterway system supports 40,000+ jobs in and generates an estimated $5.5B in revenue in the state of Arkansas. The MKARNS 12-foot channel project is part of an effort to improve navigation on the MKARNS by deepening the navigation channel to 12 feet. While this may not seem like a significant change, each additional foot of draft would allow a barge to carry another 200 tons of cargo. Completing this project will allow for increased vessel capacity, improved efficiency, boosted economic impact along the waterway, enhanced safety and will ensure that the MKARNS remains a competitive inland waterway. The MKARNS Three Rivers project was authorized in Section 1401 of America's Water Infrastructure Act of 2018. The purpose of the project is to preserve navigation on the McClellan-Kerr Arkansas River Navigation System (MKARNS). Overland flows have caused significant erosion and head cutting to the land between the Arkansas and White Rivers, threatening the uncontrolled connection of the rivers which would result in the loss of the navigation pool. Question 1.a. Can you further elaborate on the current state of funding and construction for both of these projects? Answer. Three Rivers: Phase 1, which consists of the construction of a weir opening in the historic cutoff structure at an elevation of 145 feet, was awarded as a design-build contract in July 2022. Contract construction completion was originally scheduled for June 2026; however, Phase I was completed in October 2025. Phase 2 was awarded in December 2024 and is currently under construction. Phase 2 consists of the construction of a 2.4-mile-long closure structure at an elevation of 157 feet, modification of Owens Wier, and modification of Lagrues Culvert. Based on the contract, Phase 2 construction completion is scheduled for June 2026. Three Rivers is fully funded with the reprogramming of $82.95 million in February 2024 from 12 ft. Channel and the subsequent receipt of $103.2 million in FY24 appropriations. Excess funds on the Three Rivers project due to the reprogramming of funds from 12 ft. channel are available for use on the project. 12 ft. Channel: On February 27, 2024, $82.950 million in Infrastructure Investment and Jobs Act (IIJA) funds were reallocated from 12 ft. Channel to the Three Rivers project. The overall project cost has increased since 2005 due to price changes in rock and dredging to include both labor and materials. An updated certified cost estimate was completed in April 2024, with a total project cost of $1.022 billion. In addition to updating the cost, the team also completed updates to the National Environmental Policy Act compliance with the Supplemental Environmental Assessment in September 2024. The cultural resources team is continuing coordination for the National Historic Preservation Act (Section 106) compliance. Construction funding is a 75 federal/25 non-federal cost share within the Inland Waterways Trust Fund (IWTF). The design work for Phase 1 has been suspended, and the project is in the final closeout stages. The Corps will remain focused on reinvesting in the existing system by prioritizing critical maintenance. Question 1.b. What barriers remain in the way of completion of both projects? Answer. There are no barriers to the completion of the Three Rivers project. The 12 ft. Channel project is in the process of being closed. Questions to Both Witnesses--Hon. Adam R. Telle, Assistant Secretary of the Army for Civil Works, Department of the Army, and Lieutenant General William H. ``Butch'' Graham, Jr., Chief of Engineers and Commanding General, U.S. Army Corps of Engineers--from Hon. Frederica S. Wilson Question 1. The ICE detention center known as Alligator Alcatraz was built within the footprint of the most recently authorized Everglades restoration project--the Western Everglades Restoration Project (WERP), which was included in last year's WRDA. Question 1.a. What analysis have you done of the effects of Alligator Alcatraz on WERP? Answer. The Corps has not initiated any independent analysis regarding the construction or operation of the ICE detention center which is located on land owned by the County of Miami-Dade, Florida. Question 1.b. Have you analyzed the impact of 20 acres of new asphalt on the goals of WERP? Answer. No, the Corps has not analyzed the impacts of the new asphalt on the project. Question 1.c. How will ongoing operations of the detention center impact the construction and design of WERP? Answer. The Corps does not forecast any potential impacts to the design and construction of WERP. Question 1.d. Do you commit that no Corps of Engineers funding will be utilized with respect to any aspect of the detention center, including potential remediation costs for the center or reimbursements for any center-related impacts? Answer. The Corps uses funds appropriated by Congress for the authorized purposes for which the appropriation was made. The Corps has not received authorization or appropriations related to this center. Questions to Both Witnesses--Hon. Adam R. Telle, Assistant Secretary of the Army for Civil Works, Department of the Army, and Lieutenant General William H. ``Butch'' Graham, Jr., Chief of Engineers and Commanding General, U.S. Army Corps of Engineers--from Hon. John Garamendi Question 1. In California's Eighth Congressional District, the Richmond Outer Harbor Project is a vital part of the San Francisco Bay economy, playing a key role in ensuring regional energy supplies are reliably transported. Unfortunately, navigation of this channel is currently impeded due to incomplete maintenance dredging, which is disrupting the chain of commerce and endangering energy supplies. Last November, after the Richmond Outer Harbor's regularly scheduled dredging event, it became clear that the channel had not been dredged to the necessary depth and width necessary for efficient navigation. The local Corps district has been working with the Port of Richmond to resolve these conditions, and I thank them for their attention to this. Unfortunately, due to funding limitations and permitting constraints, it's proven difficult to quickly address this issue. Lieutenant General Graham and Assistant Secretary Telle, will you commit to looking into this issue and following up with a plan to complete the remedial dredging necessary to ensure that normal operations at the Port of Richmond can continue? Answer. Yes, the Assistant Secretary of the Army (Civil Works) and Chief of Engineers commit to looking into this issue and finalizing a plan to complete the authorized dredging. The San Francisco District is aware of this concern about the Richmond Outer Harbor channel and has scheduled the dredging of this channel in FY2026. The current schedule for dredging of the Richmond Outer Harbor channel is June 2026, and approximately 250,000 cubic yards of material will be dredged from the channel with a hopper dredge, bringing the channel to a depth of -45,. Pending Emergency Declaration by the US Coast Guard or Bar Pilots Association, the Corps may pursue an Emergency Dredging episode, as needed. Question 2. Section 1202 of the Thomas R. Carper Water Resources Development Act of 2024 directed the Army Corps to complete a feasibility study, with the City of Vallejo, to determine the national and homeland security benefits of deep-draft commercial navigation in the Mare Island Strait Channel to improve access to the U.S. Coast Guard Station Vallejo. Lieutenant General Graham and Assistant Secretary Telle, will you commit to efficiently completing this vital study of the Mare Island Strait Channel? Will you follow up with a status update? Answer. Yes, the Assistant Secretary of the Army for Civil Works commits to working with the Chief of Engineers to ensure a status update is provided and the Mare Island Strait Channel study is completed. This feasibility study was authorized in WRDA 2024 but has not received an appropriation, and no Feasibility Study has been initiated; the San Francisco District has used existing authorities to conduct an economic assessment of the Mare Island Strait Channel. This is a portion of the Federal channel that has not been dredged since 1994, though condition surveys have consistently shown that the channel has maintained its authorized depth of 30 feet. This economic assessment will be complete by the end of calendar year 2025. Question 3. Lieutenant General Graham and Assistant Secretary Telle, how many Corps employees participated in the deferred resignation program, were terminated, or have otherwise left the Corps since January? Answer. During the January to August 2025 timeframe, approximately 1,840 employees have left the Corps. Approximately 3,016 employees have signed a Deferred Resignation Program agreement. Questions to Both Witnesses--Hon. Adam R. Telle, Assistant Secretary of the Army for Civil Works, Department of the Army, and Lieutenant General William H. ``Butch'' Graham, Jr., Chief of Engineers and Commanding General, U.S. Army Corps of Engineers--from Hon. Greg Stanton Question 1. The Tres Rios Ecosystem Restoration project is partially constructed with the most recent phase completed in 2012. WRDA 2024 provided additional authorization to complete the Tres Rios project. Over $110M has been spent to date to construct levees, water treatment wetlands, and other engineered and natural infrastructure for Tres Rios. The next phase due for completion is construction of trailheads to allow public access to this important public resource. Total recreation costs are less than 5 percent of the total cost for Tres Rios. Prioritizing the recreation phase at this stage will create positive engagement with the completed phases of this ecosystem restoration project, encourage legitimate recreation uses, foster economic development, and create a sense of resident ownership which will support the long-term operation and maintenance of the current and future flood control and ecosystem restoration phases. Will you please confirm your support for completing this next important phase of the Tres Rios Project, including providing staff and supporting inclusion of this phase in the USACE Work Plan and budget submittal to provide necessary federal funding to fulfill the USACE's committed cost requirement? Answer. WRDA 2024 authorized the Corps to proceed with implementing the next phases of the project (Phases 3A and 3B), which include the recreation features referenced. The Corps and the City of Phoenix, the non-federal sponsor, are aligned in preparing to complete these phases. The Corps stands ready to implement Phases 3A and 3B in accordance with available authorities and appropriations. These phases will be executed through our standard project prioritization process, which assesses key factors including a) available funding and congressional appropriations, b) project costs and benefits, c) local sponsor readiness and d) competing national priorities. The outcome of this process relies in part on actions taken by partners and entities outside the Corps. Question 2. Rio Salado Oeste is a Congressionally authorized project in WRDA 2007 that has not yet been constructed. When completed, it will provide important benefits to the Phoenix Metro area, including expected benefits for economic development. Rio Salado Oeste is currently in the midst of completing a feasibility study update, a process that started in the summer of 2023. The cost and timeframe for this study has already more than doubled from the original $3M estimated cost, and the City of Phoenix was just informed of a new requirement from your office shifting from 20 percent plan completion to get a Chief's Report to a need for 35 percent plan completion. This new requirement is estimated to expand the cost of the feasibility study by another $1M and extend the time of the study by another 20 months. What is the justification for this requirement on ecosystem restoration project studies that don't have significant engineered infrastructure such as levees? Answer. Robust engineering and design during feasibility and prior to initiating construction are a key component in delivering projects as formulated and within costs identified as part of a project's recommendation. The 35% design threshold allows for a more thorough identification of factors that could impact the project's cost and provides a firm basis for controlling costs before and during construction. [all]