- F-35 ACQUISITION PROGRAM UPDATE [House Hearing, 118 Congress] [From the U.S. Government Publishing Office] [H.A.S.C. No. 118-49] F-35 ACQUISITION PROGRAM UPDATE __________ HEARING BEFORE THE SUBCOMMITTEE ON TACTICAL AIR AND LAND FORCES OF THE COMMITTEE ON ARMED SERVICES HOUSE OF REPRESENTATIVES ONE HUNDRED EIGHTEENTH CONGRESS FIRST SESSION __________ HEARING HELD DECEMBER 12, 2023 [GRAPHIC(S) NOT AVAILABLE IN TIFF FORMAT] ------- U.S. GOVERNMENT PUBLISHING OFFICE 56-026 WASHINGTON : 2024 SUBCOMMITTEE ON TACTICAL AIR AND LAND FORCES ROBERT J. WITTMAN, Virginia, Chairman MICHAEL R. TURNER, Ohio DONALD NORCROSS, New Jersey DOUG LAMBORN, Colorado JOE COURTNEY, Connecticut SAM GRAVES, Missouri RUBEN GALLEGO, Arizona DON BACON, Nebraska SALUD O. CARBAJAL, California LISA C. McCLAIN, Michigan MIKIE SHERRILL, New Jersey PAT FALLON, Texas PATRICK RYAN, New York CARLOS A. GIMENEZ, Florida JEFF JACKSON, North Carolina NICK LaLOTA, New York STEVEN HORSFORD, Nevada RICHARD McCORMICK, Georgia Heath Bope, Professional Staff Member Jay Vallario, Professional Staff Member Brooke Alred, Research Assistant C O N T E N T S ---------- Page STATEMENTS PRESENTED BY MEMBERS OF CONGRESS Norcross, Hon. Donald, a Representative from New Jersey, Ranking Member, Subcommittee on Tactical Air and Land Forces........... 2 Wittman, Hon. Robert J., a Representative from Virginia, Chairman, Subcommittee on Tactical Air and Land Forces......... 1 WITNESSES LaPlante, Hon. William A., Under Secretary of Defense for Acquisition and Sustainment, Office of the Secretary of Defense 4 Ludwigson, Jon, Director, Contracting and National Security Acquisitions, U.S. Government Accountability Office............ 7 Schmidt, Lt Gen Michael J., USAF, Program Executive Officer and Director for the F-35 Lightning II Program, Department of Defense........................................................ 6 APPENDIX Prepared Statements: LaPlante, Hon. William A..................................... 31 Ludwigson, Jon............................................... 63 Schmidt, Lt Gen Michael J.................................... 41 Documents Submitted for the Record: [There were no Documents submitted.] Witness Responses to Questions Asked During the Hearing: [There were no Questions submitted during the hearing.] Questions Submitted by Members Post Hearing: Mr. Courtney................................................. 81 F-35 ACQUISITION PROGRAM UPDATE ---------- House of Representatives, Committee on Armed Services, Subcommittee on Tactical Air and Land Forces, Washington, DC, Tuesday, December 12, 2023. The subcommittee met, pursuant to call, at 2:40 p.m., in room 2118, Rayburn House Office Building, Hon. Robert J. Wittman (chairman of the subcommittee) presiding. OPENING STATEMENT OF HON. ROBERT J. WITTMAN, A REPRESENTATIVE FROM VIRGINIA, CHAIRMAN, SUBCOMMITTEE ON TACTICAL AIR AND LAND FORCES Mr. Wittman. I call the Subcommittee on Tactical Air and Land Forces to order. I would like to welcome everybody to our last subcommittee hearing of the year to receive an update on the F-35 program. Given that we started the 118th Congress with our first hearing on tactical fighter aircraft, it is very fitting that we finish this first session of the 118th Congress discussing what the Department notes as the cornerstone of its future tactical fighter aircraft fleet, the F-35 Joint Strike Fighter. I thank our witnesses today for testifying this afternoon and look forward to your testimony. As I stated throughout this year, the National Defense Strategy is clear in its focus on China as our Nation's pacing threat. And given the continuing provocative actions of the Chinese that we've all witnessed in the Pacific theater this year, it is critically important that we continue to evaluate our military capabilities to ensure we are postured for robust deterrence and, when necessary, prosecute combat operations to overwhelmingly prevail against any aggressor that tests our Nation's military resolve. As I emphasized this past spring while reviewing the tactical fighter aircraft plans for each of our military services, two common threads were evident. First, our fighter force structure continues on the decrease. And second, we are not able to deliver replacement aircraft at affordable prices to achieve similar quantities going forward. Meanwhile, our adversaries continue to outpace us, building and fielding their own lethal fighter aircraft capacities and capability. As it relates to the F-35 program, this subcommittee has made clear our expectations in the oversight of key areas of this program. Technical Refresh 3, better known as TR-3, hardware upgrades and Block 4 software capability development, air system and propulsion modernization, depot standup, and supply chain maturations, operations and sustainment cost reduction, and increasing the full mission capability rates above what the F-35 fleet has demonstrated today are all critical elements of what must be addressed in this program going forward. While program challenges and setbacks always seem to dominate the discussion, I would be remiss if I didn't acknowledge some of the F-35 program's successes from the past year. With the nearly $1 billion in additional investment last year, propulsion system mission capability rates have increased, and the non-mission capable rates of the aircraft due to power module removals has decreased. The program has brought on new foreign military sales customers, expanding the worldwide capability and commonality for operations with our partners and allies. And most recently the F-35 Joint Program Office has moved at a breakneck speed to support our closest partner and ally in the Middle East, Israel. They have done this by accelerating F-35 weapons capabilities and increasing spare part supply rates in their fight against the atrocities committed by Hamas. And now as I pivot to reviewing some of the program's continuing challenges, I want to unequivocally state upfront that the F-35 will be the most advanced tactical fighter aircraft that the U.S. has ever built. But our patience with the program development is wearing thin. Once again, we're going to talk about the prior planned schedules that have slipped and costs that have unexpectedly grown. I want to focus on four issues today. First, TR-3 development and fielding challenges, Second, propulsion and thermal management system modernization and requirements. Third, sustainment strategy planning, given the recent setback regarding the performance-based logistic supply contract. And fourth, potential strategies related to the development and testing of software and mission capabilities, both now and in the future. My friends, the F-35 is a technological marvel, but the delays in fielding required capabilities are disturbing. As the Department of Defense's largest acquisition program, I am committed to providing rigorous oversight to deliver required capability at a reasonable cost. With that, I turn to my good friend from New Jersey, and distinguished ranking member of the subcommittee, Mr. Norcross. STATEMENT OF HON. DONALD NORCROSS, A REPRESENTATIVE FROM NEW JERSEY, RANKING MEMBER, SUBCOMMITTEE ON TACTICAL AIR AND LAND FORCES Mr. Norcross. Thank you, Chairman, and I would like to welcome our witnesses. This subcommittee's last F-35 oversight hearing was 2\1/2\ years ago. Given the fact that it is the DOD's [Department of Defense's] largest weapon program, I think this public hearing is long overdue, and I look forward to our government witnesses updating Congress and the public on the F- 35. The F-35 is one of [the], if not the, most capable fighters on the planet. When I speak to military leaders around the world, I always hear how much they enjoy the flying F-35, how impressed they are with its performance. And I don't want that to be lost in today's hearing. It is a very impressive fighter. But what's important is that we continue to deliver future capabilities to operational forces as soon as possible and at a cost that the Department can afford. That's what this hearing is about, oversight, the execution of development, production, sustainment of this key weapon. Two months ago marked the 22nd anniversary of the start of the F-35 development. Today, the program continues to suffer unforeseen cost overruns and schedule delay. Much needed Technical Refresh 3, or TR-3, will ultimately deliver Block 4 capabilities, and it's not ready. And the government ceased to accept deliveries of this new aircraft until TR-3 testing is complete. Moreover, the Department notified the committee a few months ago of another scheduled delay that pushes delivery of TR-3 to mid-2024. Assuming this schedule holds, and that's a big assumption, that would result in an almost an 18-month delay and almost $1 billion of cost overrun. I hope our witnesses today will explain the root causes of these delays and update us on executing the new schedule. We need to deliver Block 4 capabilities to the operational forces ASAP [as soon as possible], and TR-3 is the hardware that supports future capabilities. The F-35 program is also in early development stages of the future engine necessary to sustain the aircraft through the F- 35's life cycle. This issue is broader than just a discussion on an engine. It encompasses propulsion, system cooling, electrical power generation, and electrical distribution. We want this system and its air system subprogram to meet its cost, schedule, and performance metrics. We want it to be on time and on budget. And we want it to meet the requirements. I look forward to hearing from the witnesses regarding this development effort and hope that they will clearly identify critical paths to success and any mitigating efforts to drive out or minimize the execution risk. Turning to sustainment, fiscal year 2022 NDAA [National Defense Authorization Act] prohibited the Department from entering into a multiyear performance-based logistic and sustainment contract unless and until the Secretary of Defense certified to Congress that this contract would either reduce sustainment costs or increase readiness. I understand the Department recently ceased negotiations with Lockheed Martin regarding a potential sustainment and indicated the primary reasons is they could not meet the congressionally mandated certification requirements. I find it puzzling that a multiyear sustainment contract as compared to the annual sustainment contract could not either deliver and drive down costs or increase readiness. Ultimately, sustainment costs will determine whether the Department can afford to procure its objective fleet of 1,763 aircraft for the Air Force, 420 for the Marines, and 273 for the Navy. I think it would be helpful for our witnesses to update the subcommittee on the sustainment strategy and explain how the strategy will deliver the readiness we need at an affordable cost. And finally, to our GAO [U.S. Government Accountability Office] witness, Mr. Ludwigson, we are very interested in your perspective on many of these thorny issues. This subcommittee relies heavily on the GAO to provide independent objective analysis of the program execution. And your testimony here today will help the subcommittee determine where to best focus our attention as we go forward. In closing, Tactical Air and Land Forces Subcommittee remains supportive of this program. But the Department must continue to work to drive out schedule delays and avoid those cost overruns. And I would like to thank our witnesses for their appearance today, and I look forward to their testimony. And I yield back. Mr. Wittman. I'd like to thank Mr. Norcross, our ranking member, and now I would like to introduce our witnesses. We have today with us the Honorable William LaPlante, Under Secretary of Defense for Acquisition and Sustainment, and the Milestone Decision Authority for the F-35 program; Lieutenant General Michael Schmidt, F-35 Program Executive Officer; and Mr. Jon Ludwigson, director of the Contracting and National Security Acquisition team for the Government Accounting Offices. Gentlemen, with that, I will go to your testimony. Dr. LaPlante. STATEMENT OF HON. WILLIAM A. LaPLANTE, UNDER SECRETARY OF DEFENSE FOR ACQUISITION AND SUSTAINMENT, OFFICE OF THE SECRETARY OF DEFENSE Dr. LaPlante. Thank you, Chairman Wittman, Ranking Member Norcross, and thanks to the committee for your key role in the oversight. And I think just already in the opening statements, you show a balanced view of both the accomplishments of F-35 but the real challenges. And I'm going to address some of those one by one in this opening and then hopefully lead later on with my colleagues with more and back and forth to your questions. The F-35 delivers the most lethal and survivable tactical fighter to U.S. allies and partners. I think it is in the world actually the most lethal. We have still work to do because of the changing threat and the rapidly changing threat. We are now up to--I have to remind ourselves--nine FMS [foreign military sales] partners. We have seven partners in the partnership. In addition to that, nine FMS partners with two more on the way. So we are doing something there that obviously partners and allies are seeing the benefit of this. And so with that happening, and we have nearly 1,000 of these airplanes around the world, including our partners and allies, we have these challenges. And I'm going to go through and kind of address each one at a high level, but then later we can get to it. And I will try to follow the format of the chairman on his four items. A reminder that we are also approaching a full-rate production decision now that we're done with the joint simulation environment mission trials. This would--right now if it's on track, it's going to be in March of this next year. It's important to do that. It's important to close that out. And this is subject to the IOT&E [initial operational test and evaluation] and independent costs estimates. Technology Refresh 3. The chairman and the ranking member correctly identified this as the top modernization issue right now in the program. A reminder again is that TR-3 is the hardware upgrade from TR-2, which as I remember I was putting that back in when I was the Air Force acquisition executive in 2013. But then the software that goes with it, and as the committee knows, and we will be able to talk to, while there has been significant progress, the software maturity is not such that it runs on the hardware in a manner that we are yet to be satisfied with, and hence that's the issue of the delay that was mentioned. So that's point number one. Point number two, I will just cover the propulsion. There has been a lot of work, and this committee, I know, has been very interested in the Engine Core Upgrade work that's been done as well as to extend the engine life of the F135 engine. But also the cooling and thermal management requirements to get to some future power requirements that these new systems we need for the threat have to deliver. So there is a lot of work that has been done there in getting that started. And, of course, the related, I would call it adjacent issue, of the technology of the AETP [Adaptive Engine Transition Program] program, which we have been tracking like for 10 years and where that goes. We can talk about all of that. Mentioned the sustainment. And the core of that, of course, was to get to a good and effective performance-based logistics [PBL] contract at the system level. And we took very seriously the NDAA guidance about having it certified both for performance and cost. And simply put, in the negotiations we have gone through with the industry, up until about a month ago, it was clear we were not going to get a satisfied cost proposal with performance that we would feel comfortable with and that we had to take the team that was very busy working on that and put them on essentially extending where we are now and then come back to the PBL. And simply, we were not going to approve a PBL that did not perform well and didn't get the cost savings. And for the ranking member and how you expressed your question about how could we not have a better price and performance, I completely agree with you. That almost took the words out of my mouth when we made this decision. So we have not given up on it, but we have got a lot more to do there with industry. The other piece on sustainment that I will be happy to talk about in the last year, and this is, I would say, a positive thing, is that we have been doing sustainment tabletop exercises assuming a contested environment, particularly one in the Indo-Pacific, and we are learning a lot. So we have done that there. And finally, what is central to this discussion on PBL, and frankly has been essential to the program since I have been with the program, has been the data itself, and the quality of the data, and the ownership of inventories and understanding the inventories. It impacts lots of things, including our ability to pass an audit. This has also been a factor in the PBL negotiations is making sure that the data that we are getting from industry is something that we can rely on. So we are going to continue to push on that. The legislation of 356 that allowed us to get data from the contractor has been very helpful, and we look forward to working with you further on that. I will close my testimony. I look forward to your questions. Thanks. [The prepared statement of Dr. LaPlante can be found in the Appendix on page 31.] Mr. Wittman. Thank you, Dr. LaPlante. We will now go to Lieutenant General Schmidt. STATEMENT OF LT GEN MICHAEL J. SCHMIDT, USAF, PROGRAM EXECUTIVE OFFICER AND DIRECTOR FOR THE F-35 LIGHTNING II PROGRAM, DEPARTMENT OF DEFENSE General Schmidt. Sir, thank you. Chairman Wittman, Ranking Member Norcross, and distinguished members of the subcommittee, thank you for the opportunity to provide an update on F-35 development and production plans and progress as well as strategies to maximize readiness and reduce sustainment costs. I am grateful that topics such as Tech Refresh 3, engine power and cooling modernization, test infrastructure, and sustainment are priorities for this subcommittee. And I assure you they are also top priorities of mine. Today, our Lightning Sustainment Center is delivering global support to U.S. services, F-35 partners, and foreign military sales customers around the world. We are executing an F-35 war on readiness, war on cost, and war on cyber to get after key program challenges. We are placing strategic focus on depot stand-up, organic warehousing and transportation, and logistics information system modernization. Meanwhile, organic pathfinder initiatives are driving cost- effectiveness as we de-layer our F-35 supply chain. It is clear there is no shortage of innovation and progress being achieved across this enterprise. And there is undoubtedly much work to be done. While maximizing readiness is at the forefront of my mind today, our program-wide focus on TR-3 stability and Block 4 delivery aims to ensure this air system is ready and able to win tomorrow's advanced fight if called upon. We are pursuing game-changing modeling and simulation efforts to minimize requirements for costly real-world flight tests and training. We are combating challenges associated with concurrency to deliver the necessary capabilities on relevant timelines in future lots. And we are closing in on Milestone C in a full-rate production decision. I look forward to the opportunity to update you on progress and plans associated with these and other efforts today. Since I last testified before this subcommittee, the F-35 program has overcome significant challenges and made tremendous progress. Many recent operational and programmatic accomplishments are detailed in my written testimony. Since March, the F-35 program has stood up capability at four new bases and on one new ship. To date, F-35 users have logged over 750,000 flight hours and 450,000 sorties around the globe. F-35 capability and international collaboration are increasing every single day. Within 10 years, there will be over 600 F-35s operating in the European theater alone, and fewer than 60 of them will be U.S. owned. The F-35 partnership's shared commitment and mission brings game-changing value not only for coalition combat, but for our taxpayers as well. I am tremendously proud of our multinational F-35 JPO [Joint Program Office] team members who deliver, innovate, and grow every single day. Together, we are leaning into this ''dig-in'' mentality as we enable fifth-generation capability and pursue readiness and excellence across the F-35 fleet. Thank you once again for the opportunity to join Dr. LaPlante and Mr. Ludwigson as we discuss F-35 progress, challenges, and opportunities. This subcommittee's support and oversight are essential to the success of this program. [The prepared statement of General Schmidt can be found in the Appendix on page 41.] Mr. Wittman. Thank you, Lieutenant General Schmidt. And now we will go to Mr. Ludwigson. STATEMENT OF JON LUDWIGSON, DIRECTOR, CONTRACTING AND NATIONAL SECURITY ACQUISITIONS, U.S. GOVERNMENT ACCOUNTABILITY OFFICE Mr. Ludwigson. Chairman Wittman, Ranking Member Norcross, thank you for the opportunity to discuss our work examining the F-35. The F-35 remains critical to U.S. national security and to that of our international partners and allies. After years of development and the completion of testing, the baseline program is poised to move out of the acquisition phase. Completing baseline development is good news, but the work to keep the F-35 ahead of our potential adversaries continues. The program is committed to modernize the aircraft through the Block 4 and TR-3 efforts aimed at providing enhanced capabilities to keep ahead of evolving threats. The program also plans to upgrade the cooling system, engine, and related systems intending to reduce wear on the engine and reduce costs while enhancing the foundation of the F-35 to receive advancements developed through Block 4 and potentially beyond. Both of these modernization efforts are critical to the future of the F-35. Over the past several years, we have reported multiple concerns about Block 4 and TR-3 and made recommendations aimed at improving them. In particular, we have reported that the program was struggling to develop and field Block 4 capabilities and made numerous recommendations, including updating the schedule to better reflect actual development timeframes and to use better tools for monitoring software development. Earlier this year, we reported that the limited availability of test aircraft posed a risk to the Block 4 test schedule and noted the program was planning on increasing the number of test aircraft to address this. Over the years, we have also raised higher level concerns about how Block 4 is organized. Originally, Block 4 was comprised of 66 capabilities, expected to be completed for $10.6 billion by 2026. In 2016, at the inception of Block 4, we recommended that DOD take steps to manage Block 4 as a separate program and that Congress consider directing DOD to do so. We believe this would provide more visibility and the foundation to hold the program accountable for meeting cost, schedule, and performance goals. The program did not implement our recommendation, but Congress took steps to require enhanced reporting for Block 4. However, we reported that the program has routinely made changes to Block 4. And last year we reported the most recent data indicated Block 4 had grown to 80 capabilities and grown to $16.5 billion and wasn't expected to be completed until 2029. This evolving picture has made it difficult to identify whether cost and schedule increases are a result of increasing scope, developmental challenges, contractor challenges, or something else. Despite enhanced reporting, we continue to face challenges tracking costs for Block 4 capabilities. In our report earlier this year, we recommended that the program take steps to improve how it reports Block 4 costs for individual capabilities. With our impending transition out of acquisition, the concerns we raised are increased in importance. And we continue to believe that the effort would benefit from enhanced oversight as a separate program as we recommended. More recently, the program has taken steps to address longstanding problems with the aircraft cooling system, the engine, and related systems. The original requirements for cooling proved to be incorrect and accelerated wear and higher maintenance costs were the result. Over the past year, the program examined options for addressing this. Earlier this year, we reported that the analysis done to examine these issues lacked some key information. We identified five recommendations aimed at enhancing the basis for proceeding with this modernization effort. For example, we recommended the program office define its estimated future cooling needs, conduct an independent technology readiness assessment, and obtain independent cost estimates. Similar to our Block 4 concerns, we also reported that modernization of the cooling system, engine, and related systems would benefit from enhanced oversight. We recommended that the program take steps to manage these efforts as a separate program and raised a matter for Congress to consider requiring the Department to do so. As the program transitions out of acquisition, it could be difficult to oversee these efforts without traditional acquisition management tools. Much has been accomplished in the development of the F-35, but the modernization efforts appear costly, complex, and critical to staying ahead of our potential adversaries. As such, we believe providing sufficient visibility into these efforts will be important for timely and impactful congressional oversight. Our past recommendations could help Congress oversee these efforts as the baseline program transitions out of the acquisition phase. Chairman Wittman, Ranking Member Norcross, this concludes my statement. I would be happy to answer any questions the subcommittee members may have. [The prepared statement of Mr. Ludwigson can be found in the Appendix on page 63.] Mr. Wittman. Thank you, Mr. Ludwigson. I want to thank our witnesses. And General Schmidt, I will begin with you. We had you all here last spring. You said the delivery date for TR-3 upgrade would be between December and April. Now it looks like it's April to June. I want to drill down and get from you, what are the specific areas that the contractors are having difficulty in delivering the TR-3 upgrade? And I want to ask specifically about what are they doing in trying to replicate the aircraft's operational systems in the laboratory? And it seems like to me that this ought to be a fairly simple paradigm because contractors have done it for other platforms. They've done it for Arleigh Burke destroyers with Aegis systems. They have done it for Virginia-class submarines. So it is not like this is an unknown. Can you give me some drill down about why there is a failure there to deliver this? Is there something in the laboratories? Is there something there that is not connecting in how this TR-3 upgrade is being pursued? General Schmidt. Yes, sir. That is a great question. You know, as I discussed previously, sir, you are absolutely correct. Our labs are not properly representing the flight environment, and there is way too much discovery happening in flight test. Dr. LaPlante directed a tech baseline review that started last summer that they are just wrapping up. And we will get the results. Just in summary, sir, we have seen way too much discovery in flight tests. Also I would say in this program concurrency has been an issue. But especially when we introduce concurrency in the form of hardware in this program, we have a history in this program of not being able to, in a timely manner, deliver hardware fully integrated from a software program, software aspect into the program. We are better on the tactical application side, but when we introduce hardware into a lot in this program and not have the full engineering rigor required to identify what the work scope is required to deliver in that specific lot, we run into problems in this program. And I am happy to discuss, sir, what we are doing going forward if you would like me to do that? Mr. Wittman. Yeah, I would. I would like to know what the course of action to correct this, to be able to get back on track. Because this doesn't only affect TR-3, but it also affects Block 4. And as we have aircraft back up and we are looking at what are the capabilities of these aircraft once they get the TR-3 upgrade, are they going to be as capable as TR-2 aircraft? I think that question, too, comes up. So I wanted to get your specifics about that situation. General Schmidt. In the near term, sir, relative to the stability issues that we are seeing, we are working through them. I wish, I wish I had all of the solutions in place that proved to me that when I do something in the lab, it is going to show up that way in the air. We have a number of fixes addressing the stability challenges. We will get to a stable, capable, maintainable airplane here. The data tells me it will be in the middle of spring. But I would have had a more positive answer 6 months ago of when I thought it would be. So I don't have a super solid I can guarantee you this date. I will tell you that going forward--by the way, the competition in the labs and the limited capacity in the labs between the latest TR-2 software that has great capabilities that will go out to the field early next year, it will be good to get it out of the lab. We are competing right now between the first version of TR- 3 hardware and software and the next version, which takes that combat capability in the field that we're about to deliver early in the year and puts it into a TR-3 version. So we are trying to create capacity in the labs to do that. I will say that for all Block 4 capabilities going forward the team has done, I think, a very good job of taking the many contracts we had across all of the Block 4 capabilities and putting rigorous capability decision points with rigorous system engineering processes so that we don't get ourselves into a situation where we commit hardware or software--but specifically hardware--to a specific lot without all the rigors required to say I can put that into that lot and have that contractually binding with Lockheed or Pratt & Whitney, depending on which it may be. Mr. Wittman. I think this also begs the question about the enterprise on advance systems, especially F-35. It has taken now, we are at year 18 if you count every minute of when it started from concept to where we are now, and then making sure this platform is operational. It really begs the question, if we are going to do things quickly at the speed of relevance, software needs to inform hardware. That is the way things need to go. Listen, a great hardware platform, but it can't do the things that we need for it to do if it is not software enabled. So we want to make sure that that is the baseline. Let me go to performance-based logistics. Dr. LaPlante, I wanted to get your mindset on this. We looked at a performance-based logistics contract to be able to reduce cost, to have more certainty in the supply of spare parts, mission capability metrics. As you know, the non- mission capable rates due to lack of parts is currently at 42.5 percent, absolutely unacceptable. We looked at what you are proposing, and now you seem to be moving away from performance-based logistics because you say it is going to be more expensive than doing sort of one-off, one aircraft mission capable maintenance and mission capability performance efforts. Can you explain where negotiations have led you to come to that point now and why a performance-based logistics contract is not the way to go forward? Dr. LaPlante. Well, thank you, Mr. Chairman. Well, to be clear, we have not made the decision to walk away from performance-based logistics overall at the system level. We had to pause just because of the manpower we had that was doing negotiation to extend the current contract. We have not walked away from the system-level performance-based logistics. Where we were--to do the pause, as I mentioned earlier, is in the proposals that we had received from industry at that time, they were at not sufficient cost savings, if any, and not performance savings. And so we knew we wanted to wrap up the negotiations by about February to be able to switch to the new contract and just didn't have the time. So we put pause on the PBL to focus on extending the current contracting. But I say overall, this is the way we understand it. The key thing is, you know, with performance- based logistics is, number one, picking the right metric---- Mr. Wittman. Yeah. General Schmidt [continuing]. To measure the contractor with. And you also want to do it of some period of time, 5 years, even longer. Sometimes at the system level, a performance-based logistics is very hard to do, and I'll explain an example why. If the contractor themselves or the program office doesn't have control over the metric. I was talking to one of my colleagues in another country who had one system-level performance-based logistics that was actually not working for him because the metric was in there. It was things like flying hours. And he didn't have control of it nor did the contractor. So sometimes you have to get the right metric. Where we have been in the metrics with this discussion is something called the gross issue effectiveness rate requirements. With the percentage of total demands filled at the base with onsite inventory divided by total number of demands and supply response time. We think those are good metrics. But for us to get a good idea on whether we will meet the metrics, that data has to be something that is reliable. And that was part of the issue, but we haven't given up on it. The other piece, and this may be the case, is there is something called in the sustainment community market basket approaches where you decide maybe for subsystems or what we might call systems to do a PBL, but not have one single PBL for the entire plane. So we are looking at all of that. And actually, we were looking at this as part of section 142, because section 142 that you all helped us with really directed us to begin really standing up the organic government management of sustainment. And to do that, the government has to know what it's going to do itself organically and what it's going to contract to do. And so a market basket approach may be there. It's just we were not going to wrap up the negotiation on this one in the time we needed. And I wouldn't have been able to satisfy the requirement to have it certified for the price savings. But we are not walking away from it overall. Mr. Wittman. I think you hit the nail on the head as far as metrics. I would encourage you to look at other organizations out there that do performance-based logistics. When you go to the airport, the airlines make sure they keep their aircraft in the air. They are pretty aggressive about making sure that when that aircraft is at the gate--now some of us had experiences where the aircraft gets rolled away from the gate, but their operational availability is pretty impressive. So they don't make money if they're not in the air. So I would argue there are a lot of things that could be learned from that. Obviously tactical aircraft is different than those passenger aircraft, but I think some of the concepts are probably the same. With that, I will go to our ranking member, Mr. Norcross. Mr. Norcross. Thank you, Chairman. Mr. Ludwigson, in your hearing statement, you referenced Block 4 development effort in 2016. Baseline was at 66 capabilities at a cost of $10.6 billion to be delivered in 2026, that baseline. Presently, Block 4 is comprised of 80 capabilities at a cost of $16-1/2 billion to be delivered 3 years late, 2029. Help us understand. You talked briefly about some of the suggestions that you have made and some of the issues, but the root causes for this, drill down a little bit more. Help us understand what those delays, the cost overruns for delivery, how do we address them given the history as a lesson for us? Mr. Ludwigson. Yes, sir. That is a great question. Block 4 when it was conceived, I think, was this longitudinal idea that you would just continually add new capabilities as the threat evolved. Unfortunately, that's hard to do in a public sector space where you have got--the Congress has to decide to provide the money and provide the other support necessary to proceed. And it was that--and I should say that 66 capabilities number, that is something that was difficult for us to get our hands around from the beginning. But the original---- Mr. Norcross. The original requirement of 66? Mr. Ludwigson. The original 66 capabilities is not something that I think the program wanted to sort of carry forward. They wanted this to be rather an evolving situation. And that is what happened because it wasn't bounded with a specific set of requirements, a specific limitation in terms of this is what it is going to be in terms of composition, cost, and schedule. It didn't have those baseline sort of documents that you would have for a traditional acquisition. And people added capabilities or capabilities were unpacked and some may have been dropped. And eventually you got to what we report as the most recent as 80 capabilities, $16.5 billion, to be completed in 2029. I think when you get to the root cause, some of the challenges that have emerged is because they didn't have requirements, they didn't necessarily have a firm sense of what was technically achievable. They didn't have a strong basis for understanding how long these things were going to take. It became a bit of a journey of discovery and took time for them to figure out it's actually going to take longer. Software development is difficult. And I think they certainly had their fair share of difficulties. But some of it was not setting realistic expectations for the time that they would deliver it and then not executing to meet those or not staffing to meet those. Mr. Norcross. Thank you. General Schmidt, TR-3 hardware, we talked about this at our last hearing as being the major issue in trying to get this going. It seems that that now is in place. But my question has more to do with not only the rate of our current line that is running, but for backfeeding those other ones. Are we near where we need to be in terms of ramping up for those units to be produced so we can not only fill our line going forward but also backfill? General Schmidt. Thank you, sir. Relative to the TR-3 hardware itself, the TR-3 hardware is coming up a ramp that is not where it needs to be. It is not meeting our contractual requirements. And there is really a couple of components within the TR-3 hardware that is driving that, but you need all the components to make a TR-3 kit. The next-generation DAS [Distributed Aperture System], which isn't technically part of the TR-3 kit but it is very much a part of this lot of capability that's going forward, that next-generation DAS hardware is coming pretty well. But there are a couple components in TR-3 that needs to come up the curve very quickly in order to meet our production and really our retrofit requirements after TR-3 is delivered here. Mr. Norcross. So just let me understand, it's not where you said it contractually should be. So do we have enough to fill the line going forward now? And we're missing retrofitting? Where are we in that scale? General Schmidt. Currently, we do not have enough. There were 52 airplanes contractually if TR-3 was fully ready would have been delivered by the end of December. Twenty-one of those airplanes are--let's say crossed the last stage in the production line. The rest of the airplanes are being held in general for moving TR-3 hardware around. But maybe that gives you the scope of where we're at. Again, if we can get these two components to come up, we will catch up quickly. But that's where we're at, sir. Mr. Norcross. So, we are missing any retrofits, but we are not even keeping up moving forward. General Schmidt. Well, the retrofits, sir, would start later, but when you add production and retrofit, so that requires your ramp to go up higher. Mr. Norcross. Thank you. General Schmidt. Yes, sir. Mr. Norcross. Dr. LaPlante, 3 years ago the government prime contractor, Lockheed Martin--speaking of benefits, this is getting back to the PBL. And just to understand this, negotiations have ceased, at least temporarily. You mentioned you didn't have the manpower. Drill down that because, you know, manpower is extremely important but it falls off the table the amount of money for that versus a logistics contract. Dr. LaPlante. Thank you for the question, and I appreciate the question. Let me--it is basically the team that General Schmidt has to do the negotiations and what they focus on. We could have surged manpower, that's exactly right, but we talked and thought about that. But it was probably not practical. And General Schmidt, it is your team. You can maybe talk about that. General Schmidt. Yes, sir. Happy to. So there is a manpower challenge, sir, but part of it is that the people that understand and have been in--this has been years of negotiation moving forward. Whether it is the PBL or the annual sustainment contract, that team of people is rather limited. And to include at Lockheed. You know, these are huge contracts with quotes from all the suppliers that come in. And we definitely got to the point where we had to pivot to something. I had to either show Dr. LaPlante that I had a closure plan that would get us there by right now or pivot to extending our current contracts, otherwise we would be at risk of sustaining our fleet. I am proud of the team who has been working this 7 days a week for a long time. They have closed with Lockheed on a full handshake for the first extension, if you will, to March. We are quickly closing on the extension to June. And as soon as I get that done here in the next, I hope, few weeks, we will pivot to me getting back to Dr. LaPlante with a plan on how we are going to get back to whatever the broader acquisition strategy that in my opinion must be incentive-based in order to drive the proper industry behaviors and commitments going forward, sir. Mr. Norcross. We will pursue that a little bit later on, but I want to give the others a chance. I yield back. Mr. Wittman. Very good. Thank you, Mr. Norcross. We will now go to Mr. LaLota. Mr. LaLota. Thank you, Chairman. Thanks to our witnesses for being here today. I represent the First Congressional District of New York, the eastern end of Long Island. And Long Island is the proud supplier of about 50 different F-35 components. And it is the reason for about 535 jobs. Our folks on Long Island make everything from avionics to the landing gear of Air Industries in Bay Shore, the town where I grew up. I want to talk about supply chain issues. And my first question is for Dr. LaPlante. Post pandemic, and now with real-world requirements in Israel and Ukraine, this committee has spent significant resources in an effort to improve our defense industrial supply chain. Subcommittees like this have brought in experts like yourself to gain some lessons learned to improve our warfighting capabilities. With those lessons learned in mind, can you please tell the committee what steps the DOD acquisition folks are taking to ensure America's defense industrial base is meeting important programs like the F-35? Dr. LaPlante. Thank you for the question. Number one, we are imminently going to release for the first time ever a national defense industrial strategy that has four elements to it, also with an action plan following. That's going to be released any day now. And one of the four items is all about supply chain. We have, under the auspices of the supplementals for Ukraine, but also under the regular budgetary process, pumped billions of dollars into the industrial base and building back in key areas. For example, Defense Production Act on five key components across the industrial base. We have used, I think, up to $800 million there, whether it's for rare earth batteries, solid rocket motors, et cetera. So it is what we do every day. And, yes, COVID threw us all for a loop. The other piece of this that I would like the committee to think about because it is what we are sort of dealing with in munitions. Is one of the reasons that you do--one of the reasons to do multiyears or block buy, depending on what you want to do, is not just the savings in cost. You should get savings in cost. But to the stabilization of the supply chain, the sub-tier suppliers. Because if they see that they can get longer term contracts, it stabilizes them, and it makes them less certain. To do that, a lot of times you have to put in what's called economic order quantity, which think of it as buying bulk, some of the parts, the first 1 or 2 years. And that's something that--that is what industry does in the commercial world. They don't buy things 1 year at a time. And those are things that we believe done right will really help with the supply chain, including on F-35. Mr. LaLota. Thank you and you kind of beat me to my next question for Mr. Ludwigson. What can Congress do better to help strengthen the supply chain? I hear demand signals. We have heard that before. Both Chairman Rogers and Chairman Wittman are trying to get us to be in a better position with the power of Congress' purse to give the industry better demand signals. What else can Congress do to help on this issue? Are there issues of regulations or whatnot where Congress should endeavor to help strengthen our supply chain, Mr. Ludwigson? Mr. Ludwigson. I think the progress that has been made with getting the baseline program through testing so that it can be approved for full-rate production through Milestone C, provides a greater degree of certainty. I would defer to General Schmidt and Dr. LaPlante to provide comments on that. But my impression is that with greater understanding that this is--the program has achieved this goal. It is in a better position to enter into longer term arrangements, get a better understanding of that ramp rate and what the actual production rates are going to be as it relates for F-35. That would be one of the things that I think is going to be very important is that move and the ability to reach those economic order quantities that makes sense for the program with a known production rate and known experience with maintaining the aircraft in the field. Mr. LaLota. Thanks. And with the minute I have left remaining, I want to switch gears a little bit, get back into the field, and look at Israel. Lieutenant General Schmidt, how have the F-35s performed in Israel? General Schmidt. Sir, in here, I will say absolutely outstanding. Their mission capable rates are high. Their full mission capable rates are high. As the chairman mentioned, we have added some capabilities to that airplane in a very short period of time. And our team is doing everything we can to continue to move the ball forward there, sir. Mr. LaLota. Thanks so much. Chairman, I am almost out of time, but Dr. LaPlante, I look forward to reading your report, sir. I yield. Mr. Wittman. Thank you, Mr. LaLota. We will now go to Mr. Courtney. Mr. Courtney. Thank you, Mr. Chairman. I can share with Mr. LaLota that I actually did get a sneak preview of the report, the industrial base strategy report and, again, I really compliment Dr. LaPlante for really doing it really for the first time or the first time in many, many years. And, you know, it answers the question that frankly every service branch is really--needs to get answered. So we are about 2\1/2\ months into the fiscal year, 2024 fiscal year. It doesn't look great that we are going to have a budget passed or an appropriations bill passed before Christmas. And, you know, then obviously the next cliff is fast approaching in January. You know, when we talk about the F-35 engine issue and the ECU [Engine Core Upgrade] upgrade, again, your budget, just to go back to last February or March when it was released, called for increasing the ECU line from $75 billion to over--sorry $75 million to over $400 million was, again, the budget request. And the two defense appropriations committee are sort of roughly in that ballpark that is there. I mean, if, and look at, there has been some other talk about it all year--CR [continuing resolution]. I mean, given, again, the disparity between those two numbers, that doesn't sound pretty in terms of just, you know, moving this program along. So I was wondering if you could comment in terms of just where would that leave us? Dr. LaPlante. Yeah. Well, we all hope it doesn't happen. But if we end up there, we may have to relook, and I will defer to General Schmidt, at the strategy for funding the engines and that work. In some ways, the F-35 program is, believe it or not, faring a little bit better in CR than other programs because we already are in production. I could put a pitch here too. I really believe the key to supply chains is also production. And the F-35, for all the justified concerns we all have had over its program, is doing hot production. It's one of the few programs we have that is doing hot production, and it helps with the supply chains. But, yeah, I would be concerned about the engine. I am also concerned about--we are talking about the industrial base, about the adaptive engine technology. We mentioned the AETP. I have been with that program on and off in the government for about 10 years and its predecessors. It has done more or less what we have asked it to do. It has gotten 30 percent savings in efficiency. We just, we are not able, the Department was not able, to fund a full-scale development program of that. I hope that that, at least that technology keeps going as well. But I also defer to General Schmidt to talk about the budgetary implications for the engine work. General Schmidt. Yes, sir. There are about 600 people at Pratt & Whitney that are honestly doing a great job. I was just up there a few weeks ago. It is very impressive what they are doing to try to quickly go down the road to an Engine Core Upgrade program. We need an appropriation to keep that program moving forward. I also need an appropriation because the power and thermal management system part of that, that I think Ranking Member Norcross discussed, that program really needs to get started. And I really need that funding to have Lockheed and the suppliers for a power and thermal management system really work through the engineering and all of that. So those are the implications. If we don't get an appropriation, I am at a rough spot here in a couple of months, sir. Mr. Courtney. Well, thank you. I mean, I think that's obviously very helpful. So speaking of the power thermal management, actually your office put out an RFI [request for information] fairly recently, right, for my notes here. It's a new PTMS [power and thermal management system] requirement, a 62-kilowatt threshold and an 80-kilowatt objective of cooling. Can you sort of explain what that is sort of in the context of, you know, where the program is moving right now, clarify? General Schmidt. Yes, sir. Well, those would be the requirements, if you will, that we are trying to make sure that this airplane can deliver that kind of electrical power to support all future upgrades to this aircraft. To truly understand what it takes to get to those things, I first need to be able to have Lockheed do a full assessment of the airplane to understand. So there's the actual power in the requirements and then there is how much can every part of this airplane handle to include the electrical power system, the fuel thermal management system, all of those things that we need to get going forward on. There are a number of great suppliers of power and thermal management systems out there that I want to be in this discussion and will be in this discussion. But I got to do some really good engineering work first to try to bring all of that together. Mr. Wittman. Thank you, Mr. Courtney. We will now go to Mr. Gimenez. Mr. Gimenez. Thank you, Mr. Chairman. I am going to be focusing in on the engine and the engine upgrades. We seem to be talking a lot about power and management and cooling and all that. But the one thing that I see that is missing from our dialogue or conversation is performance. And that is what matters to the pilot, to be honest with you. And so is it correct that this engine that we currently have on the F-35 was built around a platform that was supposed to be 30 percent lighter and 13 percent smaller than the current platform? General Schmidt. Sir, I don't know if those numbers are correct or not. You might be---- Mr. Gimenez. Well, there is obviously something wrong because the engine is overheating. And because of the increased demands on cooling, et cetera, that the life span of this engine is going to be shorter than what we thought. And so where are we going? Are we moving on the EEP [Enhanced Engine Package] program or are we looking at the AETP program, the new engines, or are we looking just to upgrade the engines that we have? Dr. LaPlante. Yeah. I will hopefully help with the question here. We are going with the core, the life extension of the core, the 135, as well as the cooling for that engine. Let me just say this, not knowing the history that you know, so I defer to you. What I have seen in the time I have been in this job, and this gets into the requirements issue that GAO mentioned, the requirements have changed in thermal and power because the threat has changed and the systems that have been added to the airplane, even decided to be added in the last 5 years, were something we didn't envision 10, 15 years ago. That's simply true. And so, now, you could argue that we--that is an argument for a much more modular architecture so you can upgrade when the threat changes. But it has changed. The systems that are now on the jet or are planning to be on the jet were not planned even 10 years ago. Mr. Gimenez. I understand that. Now, again, are we looking just to upgrade or putting some kind of an add-on to the engines that we currently have to manage the problem or are we looking at an entirely new engine with new capabilities? And if we are not, could you answer why? Because apparently the new engine with entirely different capabilities are going to give you 30 percent greater range and will give you 20 percent more acceleration. And if we're looking at the INDOPACOM [U.S. Indo- Pacific Command] theater, range is going to be a premium. So what are we looking at? Where are you guys heading? General Schmidt. Sir, so I absolutely understand the question. We did a business case analysis last year. We went out--our requirement was to address the life of the engine. We're running the engine too hot. Significant costs over the life of the engine. And we needed to solve that problem. Additionally, we needed power and cooling, additional power and cooling capabilities. There was also the Advanced Engine Technology Program, which is a very, very promising program, sir, from a performance perspective. One of the challenges in this program, with the AETP program, as we did the business case analysis, is that it is an option for the A model and maybe for the C model and doesn't work for the B model. So if I was going to address all of the requirements of the program from a get the life back in the program perspective, only the Engine Core Upgrade to the current engine fit that. Mr. Gimenez. Could I--I only got so much time. General Schmidt. Yes, sir. Sorry. Mr. Gimenez. I need to cut you off a second. In terms of the numbers of aircraft, A and C versus B, what is the percentage on that? General Schmidt. The A is significantly higher, sir. Mr. Gimenez. And the C? General Schmidt. The A is significantly higher, sir. Mr. Gimenez. But you said that the--a new engine could fit on the A, maybe the C, okay, but not the B. And so we are going to say, okay, because we want the--we are going to choose the least capable engine of all because of the B, which happens to be the smallest number of planes that we have. Dr. LaPlante. That was--yeah, what went into the business case was lots of things. It also---- Mr. Gimenez. With all due respect, I am losing time. Dr. LaPlante. Okay. Sorry. Mr. Gimenez. Okay. So if I am in the jet, and I am the fighter pilot, I want the engine that takes me faster and takes me longer. And I know about your business thing. And now maybe that business argument maybe it should be brought to us and say what is it because there has got to be a tradeoff? Is there a cost benefit to that upgrade? And so, again, we need to delve into this a little bit deeper, Mr. Chairman, because I am not convinced that this is just a business decision. This is a performance issue, too. And for the life of our pilots and the capability of this airplane, especially in a theater which we may be finding ourselves in conflict is going to need this enhanced capability in the future. And thank you. I guess I yield back. Mr. Wittman. Very good. Thank you, Mr. Gimenez. We will now go to Dr. McCormick. Dr. McCormick. Thank you, Mr. Chair. This is for both Lieutenant General Schmidt and Dr. LaPlante. Obviously, we have seen the aircraft perform very well in Israel. I think they were pretty satisfied with its ability to do precision munitions exactly where we want it and how we want it. This goes back to what they have learned in their sustainment side of their aircraft though as they have deployed it more than they probably deployed it in recent years, just how they are feeling about their sustainment portion of their aircraft right now. General Schmidt. Yes, sir. I had the opportunity to talk with their chief of staff just yesterday. I would say that we have a lot--that we are going to learn a lot. They are very satisfied with what their performance from a sustainment enterprise is giving them. I think we could learn a lot from them in terms of the quickness with which they are turning airplanes, all of the things we are learning ourselves with moving parts around the world in support of a conflict. So we are committed to--and I am looking forward to, and right now, collecting a lot of lessons learned for us, as we posture ourselves globally for our--the worldwide F-35 enterprise sustainment. Dr. McCormick. So on that note, actually related note, how is that when we scale that out to like an INDOPACOM, you know, how do we see that? Or do we have that sustainability capability for--we have a lot of things going on right now in a lot of different theaters that could blow up very quickly. Do we have that capability to ramp up as needed? Dr. LaPlante. Yeah, I would add something, and it applies to Indo-Pacific and what we are learning from the current conflicts. One of the--the chairman talked about software and turning software fast. One of the good-news stories in F-35, it's still not where it needs to be on these mission data files. What General Schmidt and his team did in about a week, week and a half, is turned around these mission data files. That is the brick that goes into the airplane. And that, I think, the lessons learned on how you did that can apply all the way around the world. The other piece, and I mentioned earlier, is that we are doing tabletop exercises on sustainment in the Indo-Pacific. And what we are learning, not surprisingly, is that we have to be able to surge, and this gets back to the PBL. We want the PBL to be of something we can surge. So there are a lot of lessons that we are learning that may well affect that as well. Dr. McCormick. Okay. And with that also, I'm just going to go to another related topic, what about critical base shortages of impact, like the industrial base, like, materials? Do we have materials shortages that could affect, especially strategically different countries that control those sort of shortages? Dr. LaPlante. I would say overall this is just the situation in the world right now. Energetics, energetics are a key issue around the world right now, whether it is solid rocket motors or other TNT [trinitrotoluene] or TNT-like things. And I think we are seeing that--we knew we were seeing that with 155 and the issue in Ukraine. But that is an issue we see everywhere in all the scenarios. Dr. McCormick. So are we able to--is there something that Congress can do to address that specific--to protect those assets? Dr. LaPlante. Well, I think helping us with the Defense Production Act. We've already used the Defense Production Act to fund solid rocket motors and energetics. We need more of that. I think we also--then more companies will go into that business. So that is where Congress can help us. Thank you. Dr. McCormick. I see, secure those raw materials then. Okay. Very good. Lieutenant General Schmidt, specific to the importance of technological development, can you talk how the Engine Core Upgrade currently underway is leveraging investments made by the Navy's fuel burn reduction program and other advanced development programs? General Schmidt. Yes, sir. The fuel burn reduction program was very much a precursor to the Engine Core Upgrade program. Pratt & Whitney has modeled the entire Engine Core Upgrade program. And it is my understanding that very much, sir, the fuel reduction program was a significant starter, if you will, to help move forward with the Engine Core Upgrade program. Dr. McCormick. Okay. I don't think I have enough time for another question. But thanks for your time, gentlemen. Mr. Wittman. Thank you, Dr. McCormick. I want to pursue another round of questioning and then we will head from there if folks have questions that need to be answered in the classified setting. I spoke a little bit earlier about how the enterprise today across the Pentagon needs to be a software informed process. Obviously, the F-35 is going to be with us for years. We are in--essentially from a blank sheet of paper and nearly 22 years now from the beginning. Gentlemen, can you tell me, and I will start with Dr. LaPlante, can you tell me how you plan to pursue the enterprise of continued production and maintenance and upgrade of the F-35 in the current structure where we seem to be hardware driven and software is an afterthought. Is there any plan to reverse that to make this a software-informed enterprise? Are there any plans to use digital twin technology where we can immediately test aircraft, download the information and make software updates and do that at the speed of relevance? Because obviously what's happening with TR-3 is not at the speed of relevance with these continued delays. Something has to change with the paradigm as to how we operate within this particular realm. We know that programs like CCA [Collaborative Combat Aircraft] are going to be software-informed programs. So can you give us some insight as to how you see us changing the paradigm for the F-35? Dr. LaPlante. Yes. Thank you for the question. It is an extremely important question. I co-chaired the Defense Science Board study on software acquisition in 2018 that motivated going to the new software acquisition pathway where the old waterfall techniques that the Department had across everywhere needed to be changed to a modern DevSecOps [development, security, and operations] iterative with 8 weeks sprints and dropping to a minimal viable product. One of the first programs that we looked at on the Defense Science Board study, with General Schmidt's predecessor, was F- 35. And one of the questions we asked ourselves was could you go to modern DevSecOps on the mission software for F-35? The challenge that we saw was the architecture. The architecture goes back to 2002. It is highly coupled and integrated. And it would be--you could do it in portions of it. But it was going to be hard to fundamentally do it unless you changed the architecture. What I am very interested in is Aegis because I grew up at Johns Hopkins APL [Applied Physics Laboratory], and we were in the Aegis mafia as we called ourselves. And we were very frustrated in the other parts of Johns Hopkins that Aegis did not go open. Well, finally Aegis has gone to an open system. And so I have not given up hope that we can go to some degree of open system. I will also say this, and I will turn it over to General Schmidt, on the digital twin. We designed the acquisition strategy for B-21 in the wake of the Nunn-McCurdy breach of F- 35. We made sure that that architecture was open. And getting to the changes in the threat, the changes to the requirements, with an open architecture, you can drop changes very quickly. And you can do it by software. It is not that F-35 doesn't have software. It has got 30 million lines of code. It has just got it in a highly integrated way. I will turn it over to General Schmidt. General Schmidt. Sir, I would only add, and we are just getting going here from my perspective. So we do have a digital twin, for instance, of the integrated core processor, which has helped us out significantly in TR-3. I should have it for the entire TR-3 program. As we move forward, we are requiring digital models of each capability in the Block 4 as part of those capability decision points going forward. Your point about the architecture and kind of the closed software environment that we have and Dr. LaPlante's points, we need to eventually get to an open systems architecture. And along the way, for sure, we need to figure out how to make sure we are taking advantage of, for instance, our services software engineering groups to have not only Lockheed working the software in this program but the government organic software developers who are outstanding. Mr. Wittman. Are there additional ways that we can encourage the contractors and their mission system suppliers to adopt and implement new methodologies to be able to do development, testing, and implementation of their changes in upgrades to software? It just seems like to me that we are in a very archaic and antiquated test, failure, retry, test, failure, retry mode instead of changing the whole paradigm that has us operating at the speed of relevance. The technology is there in all these other areas. It just seems like for whatever reason, we are still stuck in this archaic trap with F-35, and TR-3 unfortunately is the example of that. I also understand, too, there may be other things we need to do to accelerate that. It seems like to me the test beds now are aging. Maybe we look at more modern test beds and make sure the test beds are aircraft that are dedicated to rigorous testing. It seems like to me, too, that we have more up-to-date technology where we could immediately take streams of data from the aircraft, send it directly to programmers on the ground that in a digital twin technology can essentially be put into a simultaneously run model. That information can really be put into the model. And you could fly that aircraft this afternoon in some cases and say let's try out these software modifications instead of what we have today, which is trying this in the lab. It fails in the lab. You put it in the aircraft. It crashes in the aircraft. You bring it back to the ground and say we have got to do it again. The trial and error methodology ain't working. And the technology is out there all around us to do things differently. Can you assure me that we are aggressively pursuing these paradigms going forward with how we are doing upgrades to the aircraft? General Schmidt. Well, first, sir, I would say I thank you for the support for replacing our aging flight test aircraft themselves because that is very important to include the things we put on it to make the data flow better and all of the things. Relative to our labs, ourlabs--we have a number of recommendations that are coming forth as part of the tech baseline review. And our teams are working through what kinds of investments we should be making in our labs to make them more realistic and relevant relative to the flight test environment. Specifically, it appears to me that Lockheed is making significant investments in their future programs that are doing a lot of what you described there, sir. Dr. LaPlante's Aegis example is another great example. How are we making sure? And I wish I had a good answer for you because all those things need to be in this program, sir. Dr. LaPlante. I will just note that in 2014, when we put the RFP [request for proposals] out for what is now the B-21, and we said in the RFP you had to have an OMS [open mission systems] standard open system, all of the companies, there were three of them, two of them were teamed together, that were competing for it started putting out press releases on how they could do open systems. So when you put it in the RFP and you make it part of the source selection, it motivates different behavior. The question on F-35 given where we are in the program, that is why Aegis is so interesting. Mr. Wittman. Yes. Dr. LaPlante. We can look at that. The other piece I will just add is the other thing we said in the study about--the software study, it's not just the architecture but something called a software factor. And we defined what it was. That is where that testing, Mr. Chairman, was done. It was called fuzzing. We bombard the code with cloud overnight, and you find all these errors, exactly what you said. Mr. Wittman. Yeah. Dr. LaPlante. They should have a software factory at Lockheed Martin. Mr. Wittman. No. I think software factory paradigm is great. Listen, this isn't a secret how to do this; as you pointed out, Aegis has done it for years. The prime contractor is the lead on that so it is not like this is a secret sauce somewhere that's underneath a pillow that we have to resurrect and put back out there. This is a known entity. It is done on submarines. It is done on surface ships. No reason why it can't be done for F-35. So with that, I will turn it over to Mr. Norcross. Mr. Norcross. Thank you. General, just to drill down a little bit on your statement that up at Pratt & Whitney there are 600 people working, yet you are talking about the CR. Those 600 aren't working on the ECU for the future or 600 dedicated people for the ECU upgrade? General Schmidt. The ECU for the future, the ECU upgrade. Mr. Norcross. Okay. General Schmidt. Yes, sir. Mr. Norcross. So if they are currently working, and we have a CR, how does that impact that other than ramping up? General Schmidt. Yes, sir. We are limited to last year's funding---- Mr. Norcross. Right. General Schmidt [continuing]. Under the CR. And we are good through about February-ish. But at that point, if I don't have the funding to keep--and we are supposed to be ramping up significantly this year in terms of, you know, investment in that program per our plan. So we are capped at the level and then we are actually at risk of it running out if we don't have an appropriation, sir. Mr. Norcross. Nobody wants a CR. But at least we'll continue and hopefully get that. And that is what I wanted to talk about. And Joe has a question concerning the Defense Act. But for this program, we made a decision. We can't fund two engines. Agree with it, disagree with it. This is where we are heading. Talk to me about some of the technical risks that are facing the ECU and how you are addressing that so that we don't run into a problem like we are with the TR-3 upgrade. General Schmidt. For the program as a whole, I mentioned what I think are some of the technical risks is ensuring that the--so one of the requirements I have, sir, is that this engine program is retrofittable. So we have those power requirements, but at the same time our nations and our services have said this must be retrofittable. So I need to do all the work on the airplane side and the power and thermal management system side because if I do run into a fuel thermal management system or wiring gauge that would require me to completely, you know, tear the airplane apart to retrofit the engine, that would drive me to go back to the requirements community and say, hey, we got to figure out the right balance here on the, you know---- Mr. Norcross. Are you suggesting that we need those answers for both the temperature management and the electrical management? That if they don't come in in an area that you can accommodate on the existing that we might have to go back to the decision we made? General Schmidt. Sir, the engine requirements that they are designing to are to the worst case requirements of the worst case, is what we have directed them to design the engine to. And if it turns out that we end up having a power and thermal management system that doesn't get to that, it allows us to go back, and Pratt & Whitney to go back, and adjust because there are changes that they can make in the engine to direct power in the gear box that we are going to go towards running that to additional performance out of the engine. But for right now, we are designing to the most stringent case from an aircraft side, sir. Mr. Norcross. Okay. I yield back. Mr. Wittman. I go to Mr. Courtney. Mr. Courtney. Thank you, Mr. Chairman. And real quick, Dr. LaPlante, the exchange that you had a moment ago with Dr. McCormick about what can Congress do to sort of deal with the issue of these, you know, energetics and critical minerals. When we were in California recently, we talked about one thing that Congress hopefully is in the process of doing is passing the NDAA which has the AUKUS authorization language, which will extend the Defense Production Act authorities to Australia and the U.K. [United Kingdom] as domestic sources, similar to what Canada enjoys today. And actually that is really a huge opportunity, particularly with Western Australia and the mineral resources that are there. So maybe you can just sort of talk about that for a second. Dr. LaPlante. Yeah. Thank you, Congressman. It turns out, tomorrow, I am meeting with the head of strategic industry of Australia, they're in town. And specifically, we are going to talk about the provision that is in the NDAA on Defense Production Act with Australia. So I think they are very excited about it. Actually, the national--the industrial strategy that you read, we are finding the partners are really interested in that, too, because they are looking at things that we have that they may want to do. We are also getting the same interest from our European allies, from NATO [North Atlantic Treaty Organization], about a Defense Production Act like thing for them. So a lot of folks are watching us. I think they see what this Congress has done and authorities. And I think they have seen the effectiveness of it. So I would just thank again, thank you all for what you are doing. And I know the Australians are very eager to talk to us. Mr. Courtney. Again, hopefully we have got about 48 to, you know, 72 hours to wrap this up. So with that, I yield back. Mr. Wittman. Thank you, Mr. Courtney. Mr. Norcross, any other questions? Okay. Very good. Well, I think we are finished with our line of questioning. Gentlemen, thank you all so much. We are--well, before we close, Mr. Ludwigson, I know that you had a comment that you were looking to make there on Mr. Norcross' question. So I'm going to yield the floor to you. Mr. Ludwigson. Sure. Thank you very much. I think General Schmidt did a great job talking about the interconnections between the pieces of the puzzle in the power and thermal management and engine upgrade question. What we have been concerned about is that the program not repeat the mistake that got them here, which is that they underestimated the cooling requirements. Mr. Wittman. Yeah. Mr. Ludwigson. Those proved to be wrong. Then they had to steal from the engine and that caused them to have to get creative. And creativity got expensive in terms of the wear and tear on the engine and all of those sort of cascade of events that we are here talking about. So we think that is why when you look at this, we prefer you think about this as an integrated package of changes that need to be done, not singularly looking at each piece of the puzzle because when you put them together, integration ends up being one of the biggest, most difficult pieces of the puzzle. Just how do you put it all back together. Mr. Wittman. Listen, I think you are spot on. Power, thermal management, electrical system, all the different elements there of what you do, you know, you can put a larger engine in there that generates more power and cooling, but the question is is, you know, what other changes may be needed on the aircraft itself in order to sustain that? And then the big question, I think you all have pointed this out, is that what is the end state of the power and cooling requirements of the aircraft? So where does it need to be before its ESL [extended service life] is expired? So there is no use to say, well, you know, we are going to build an engine that can do 62 kilowatts and then you go, well, gosh, we really needed 80 kilowatts with future upgrades for the aircraft because this aircraft is at a price point where we cannot afford to go through another engine upgrade. If you are going to do it, you want to do it one time. You want to determine what are the total costs, as you said, over the life cycle of the aircraft. Look at the number of hours that you get out of that engine, which obviously we aren't getting out of the current engine configuration, because you are going to have to do that in order to substantiate the cost that it is going to take essentially over a long window of time. So I think those things are incredibly important questions that need to be asked before you take any next step in the final engine decision-making. Mr. Ludwigson. I think when you face a difficult question, the carpenter's analogy springs to mind: measure twice and cut once. A pretty useful way to think of it. Mr. Wittman. That is exactly right. So any other witnesses want to make any additional comments? Dr. LaPlante. No. I think you just described to my GAO colleague, the fundamental systems engineering challenge is you have to get the system engineering right because the coupling between subsystems and the effect on that is something that often needs attention. And really good systems engineers are hard to find as well. Mr. Wittman. Yeah. I think it's a matter, too, as you said, good systems engineering, good look at, you know, the whole element to a performance-based logistics. What do we do over the remaining life cycle of this aircraft? We ought to take every lesson learned in the first 22 years of this program and apply those lessons learned going forward. There is no reason why we should have any of these hiccups going forward. Goodness knows, we probably experienced every one of them that you could in the current history of the aircraft. Let's make sure we get it right going forward so. Gentleman, thank you all so much. I don't think that there is any need for us to go to the SCIF [sensitive compartmented information facility]. I think everybody has had their questions answered here in this open forum, and the others that needed to be answered have been answered previously in the SCIF. So I want to thank you all so much for joining us. And if there is anything that you need from our subcommittee, we stand by ready, willing, and able to help. And with that, the subcommittee is adjourned. [Whereupon, at 3:58 p.m., the subcommittee was adjourned.] ======================================================================= A P P E N D I X December 12, 2023 ======================================================================= ======================================================================= PREPARED STATEMENTS SUBMITTED FOR THE RECORD December 12, 2023 ======================================================================= [GRAPHIC(S) NOT AVAILABLE IN TIFF FORMAT] ======================================================================= QUESTIONS SUBMITTED BY MEMBERS POST HEARING December 12, 2023 ======================================================================= QUESTIONS SUBMITTED BY MR. COURTNEY Mr. Courtney. As we discuss other upgrades needed for the F-35, can you confirm that ECU is being designed for any PTMS configuration to allow for the current schedule to stay on target? Dr. LaPlante and General Schmidt. Yes, the ECU is being designed to integrate with all F-35 PTMS configuration concepts currently being considered. Mr. Courtney. With the RFI released for new PTMS requirements, when do you intend to integrate a new PTMS to support the aicraft? Dr. LaPlante and General Schmidt. The F-35 acquisition program intends to begin the development of an upgraded Power Thermal Management System (PTMS) in FY24, with system qualification by 2032 and production line cut-in beginning in 2033. Schedule milestones will be refined as the PTMS acquisition solution matures. Mr. Courtney. Can you explain the PTMU modernization plan and timing? Dr. LaPlante and General Schmidt. The JPO's near-term priority is to fully validate that all PTMU technical requirements can be met with a materiel solution, which also supports direction included in the FY24 NDAA, SEC. 226. F-35 PROPULSION AND THERMAL MANAGEMENT MODERNIZATION PROGRAM. The concept development contract is planned to commence this summer and will begin competitive PTMU design activities. Mr. Courtney. What is the current PTMS cooling capacity requirement for Block 4? Has the definition changed? And what is the maximum PTMS capacity need over the lifetime of the platform? Dr. LaPlante and General Schmidt. The F-35 Lightning II Joint Program Office will provide a CUI response directly to the House Armed Services Committee. [all]