- THE STATUS OF COAST GUARD CUTTER ACQUISITION PROGRAMS [House Hearing, 114 Congress] [From the U.S. Government Publishing Office] THE STATUS OF COAST GUARD CUTTER ACQUISITION PROGRAMS ======================================================================= (114-32) HEARING BEFORE THE SUBCOMMITTEE ON COAST GUARD AND MARITIME TRANSPORTATION OF THE COMMITTEE ON TRANSPORTATION AND INFRASTRUCTURE HOUSE OF REPRESENTATIVES ONE HUNDRED FOURTEENTH CONGRESS SECOND SESSION __________ FEBRUARY 3, 2016 __________ Printed for the use of the Committee on Transportation and Infrastructure [GRAPHIC(S) NOT AVAILABLE IN TIFF FORMAT] Available online at: http://www.gpo.gov/fdsys/browse/ committee.action?chamber=house&committee=transportation ______ U.S. GOVERNMENT PUBLISHING OFFICE 98-459 PDF WASHINGTON : 2017 ----------------------------------------------------------------------- For sale by the Superintendent of Documents, U.S. Government Publishing Office Internet: bookstore.gpo.gov Phone: toll free (866) 512-1800; DC area (202) 512-1800 Fax: (202) 512-2104 Mail: Stop IDCC, Washington, DC 20402-0001 COMMITTEE ON TRANSPORTATION AND INFRASTRUCTURE BILL SHUSTER, Pennsylvania, Chairman DON YOUNG, Alaska PETER A. DeFAZIO, Oregon JOHN J. DUNCAN, Jr., Tennessee, ELEANOR HOLMES NORTON, District of Vice Chair Columbia JOHN L. MICA, Florida JERROLD NADLER, New York FRANK A. LoBIONDO, New Jersey CORRINE BROWN, Florida SAM GRAVES, Missouri EDDIE BERNICE JOHNSON, Texas CANDICE S. MILLER, Michigan ELIJAH E. CUMMINGS, Maryland DUNCAN HUNTER, California RICK LARSEN, Washington ERIC A. ``RICK'' CRAWFORD, Arkansas MICHAEL E. CAPUANO, Massachusetts LOU BARLETTA, Pennsylvania GRACE F. NAPOLITANO, California BLAKE FARENTHOLD, Texas DANIEL LIPINSKI, Illinois BOB GIBBS, Ohio STEVE COHEN, Tennessee RICHARD L. HANNA, New York ALBIO SIRES, New Jersey DANIEL WEBSTER, Florida DONNA F. EDWARDS, Maryland JEFF DENHAM, California JOHN GARAMENDI, California REID J. RIBBLE, Wisconsin ANDRE CARSON, Indiana THOMAS MASSIE, Kentucky JANICE HAHN, California MARK MEADOWS, North Carolina RICHARD M. NOLAN, Minnesota SCOTT PERRY, Pennsylvania ANN KIRKPATRICK, Arizona RODNEY DAVIS, Illinois DINA TITUS, Nevada MARK SANFORD, South Carolina SEAN PATRICK MALONEY, New York ROB WOODALL, Georgia ELIZABETH H. ESTY, Connecticut TODD ROKITA, Indiana LOIS FRANKEL, Florida JOHN KATKO, New York CHERI BUSTOS, Illinois BRIAN BABIN, Texas JARED HUFFMAN, California CRESENT HARDY, Nevada JULIA BROWNLEY, California RYAN A. COSTELLO, Pennsylvania GARRET GRAVES, Louisiana MIMI WALTERS, California BARBARA COMSTOCK, Virginia CARLOS CURBELO, Florida DAVID ROUZER, North Carolina LEE M. ZELDIN, New York VACANCY ------ Subcommittee on Coast Guard and Maritime Transportation DUNCAN HUNTER, California, Chairman DON YOUNG, Alaska JOHN GARAMENDI, California FRANK A. LoBIONDO, New Jersey ELIJAH E. CUMMINGS, Maryland BOB GIBBS, Ohio CORRINE BROWN, Florida MARK SANFORD, South Carolina JANICE HAHN, California GARRET GRAVES, Louisiana LOIS FRANKEL, Florida CARLOS CURBELO, Florida JULIA BROWNLEY, California DAVID ROUZER, North Carolina PETER A. DeFAZIO, Oregon (Ex LEE M. ZELDIN, New York Officio) BILL SHUSTER, Pennsylvania (Ex Officio) CONTENTS Page Summary of Subject Matter........................................ iv TESTIMONY Rear Admiral Joseph M. Vojvodich, Assistant Commandant for Acquisition and Chief Acquisition Officer, U.S. Coast Guard.... 3 Michele Mackin, Director, Acquisition and Sourcing Management, U.S. Government Accountability Office.......................... 3 Ronald O'Rourke, Specialist in Naval Affairs, Congressional Research Service............................................... 3 PREPARED STATEMENTS SUBMITTED BY MEMBERS OF CONGRESS Hon. John Garamendi of California................................ 33 PREPARED STATEMENTS SUBMITTED BY WITNESSES Rear Admiral Joseph M. Vojvodich................................. 36 Michele Mackin................................................... 43 Ronald O'Rourke.................................................. 65 SUBMISSIONS FOR THE RECORD Rear Admiral Joseph M. Vojvodich, Assistant Commandant for Acquisition and Chief Acquisition Officer, U.S. Coast Guard, post-hearing responses to requests for information from the following Representatives: Hon. Bob Gibbs of Ohio referenced instances of cracked diesel engine cylinder heads among National Security Cutters and asked if the repairs were covered under contract or warranty, or paid by the U.S. Coast Guard or other entity.. 12 Hon. Garret Graves of Louisiana requested an explanation of efforts by the U.S. Coast Guard to work with the Maritime Administration to maintain a list of vessels for disposal.. 18 Hon. Duncan Hunter of California asked why it wasn't until the testing of National Security Cutter No. 3 that operational capability issues were identified yet were not identified in Nos. 1 and 2................................. 24 Hon. Duncan Hunter of California requested the U.S. Coast Guard's perspective on using multiyear procurement contracting and block buy contracting...................... 30 Hon. Jim Bridenstine of Oklahoma submitted written questions for the record............................................. 40 [GRAPHIC(S) NOT AVAILABLE IN TIFF FORMAT] THE STATUS OF COAST GUARD CUTTER ACQUISITION PROGRAMS ---------- WEDNESDAY, FEBRUARY 3, 2016 House of Representatives, Subcommittee on Coast Guard and Maritime Transportation, Committee on Transportation and Infrastructure, Washington, DC. The subcommittee met, pursuant to notice, at 10 a.m., in room 2167, Rayburn House Office Building, Hon. Duncan Hunter (Chairman of the subcommittee) presiding. Mr. Hunter. Good morning. The subcommittee will come to order. The subcommittee is meeting today to discuss the status of Coast Guard cutter acquisition programs. The Government Accountability Office issued a report on January 12th entitled ``National Security Cutter: Enhanced Oversight Needed to Ensure Problems Discovered During Testing and Operations Are Addressed.'' It raises concerns with the timing of testing during production, the guidance available to guide production, testing and oversight of corrected actions, and the additional costs to address the deficiencies and operational issues. An important discussion I would like to have today is how we ensure the end assets operate as intended and are what the taxpayers paid for. What lessons have we learned during the National Security Cutter and Fast Response Cutter acquisition programs that can be applied to the OPC [Offshore Patrol Cutter] program to minimize, if not eliminate, the same issues. As I have said before, the Coast Guard is operating tens, and in some cases, hundreds of hours short of its operational targets, which puts our Nation at risk. Assets are not available for the Service to secure our ports, protect our environment, and ensure the safety of our waterways. We heard in 2014 the lack of available assets resulted in historic lows in drug interdiction rates. The lack of assets must have affected other mission areas as well. The fact that the new assets may not be performing as intended is a problem that could continue to impact mission capabilities. We have also previously discussed issues with the President's annual budget requests and the Capital Investment Plans, both of which have not supported the infrastructure needs of the Coast Guard. According to the Coast Guard's fiscal year 2016-2020 CIP, annual funding for acquisitions will be roughly $1 billion less than the GAO [Government Accountability Office] and Coast Guard officials have testified is needed on an annual basis to keep the current acquisition program on schedule and on budget. The Capital Investment Plan is nothing more than a roadmap to additional acquisition delays, increased costs for taxpayers, and ongoing mission performance failures. The President's budget requests have followed the poorly designed roadmap provided in the Capital Investment Plan. The fiscal year 2016 request cut funding needed to acquire critically needed replacement assets by 17 percent. The budget request also failed to guarantee the funding needed to begin detailed design for the OPC, and failure to move into detailed design on the OPC by the end of fiscal year 2016 could result in significantly higher costs and substantial acquisition delays. Moving this, and other, acquisitions further to the right will only further degrade Coast Guard mission performance. As we move into reviewing the fiscal year 2017 budget, it would be a welcome change to see the President's budget support funding for the Coast Guard's acquisition programs. Another component of the recapitalization is the Coast Guard's mission need statement. It is used to inform us and everybody the evolution of the Coast Guard's Capital Investment Plan. Up until last month, the Coast Guard was working on a mission need statement from 2004. So it only took them about 11 years to update it. On January 8th the Coast Guard released a new mission need statement, as required by this committee, the Appropriations Committee, and our Senate counterparts. The Howard Coble Coast Guard and Maritime Transportation Act of 2014 required an updated mission need statement to include information on current and projected gaps in Coast Guard mission capabilities and how major acquisition programs would address those gaps. However, that is what it was supposed to do. What the Coast Guard released on January 8th actually states this: ``This document does not seek to identify a material solution to meet future mission needs, but rather to identify the enduring, high-level capabilities required for the Coast Guard to execute its broad statutory authorities effectively and efficiently.'' So it took the Coast Guard 11 years to do an updated mission need statement, and in that mission need statement, they said they are not going to do a future mission need statement. While having an updated mission need statement is better than working off one developed over a decade ago, if it does not provide information on what assets are needed to perform certain missions, does it properly inform the evolution of the Capital Investment Plan and subsequently the President's budget request for Coast Guard assets? Those are questions we have today. I look forward to discussing all of the issues before us today, including any lessons learned from the NSC [National Security Cutter] and the Fast Response Cutter acquisition programs so they could be applied to the Offshore Patrol Cutter acquisition program. In the end, the American public deserves assets that perform as intended and expected. We do not need missions to be continually compromised due to the limitations of old vessels and flaws in new ones. With that I yield to Ranking Member Garamendi. Mr. Garamendi. Thank you, Mr. Chairman. I am listening carefully to your opening statement, and I am thinking, ``What could I add?'' Maybe welcome and good morning. I look forward to your testimony. This chairman has laid out a series of issues. My opening statement repeats much of what he has already covered, and actually covered much more than my opening statement. So I am just going to submit my statement for the record, and we will just get into it and go from there. One thing that the chairman did not cover was our favorite subject, icebreakers. Maybe you did. Did you discuss that? Mr. Hunter. No, I did not. Mr. Garamendi. Come on. Mr. Hunter. This one day, you got me. Mr. Garamendi. So we want to talk about icebreakers a little bit to see where we are with that, but everything else that is in my opening statement he has already talked about. I could repeat it, but welcome, and I will submit it for the record. Mr. Hunter. One reason this is important this morning is because your National Security Cutters are almost done. You only have a block of what, 40 or 50 ships, FRCs [Fast Response Cutters] and OPCs, coming up, and then you are not going to have any acquisition for quite a while. This is it. So we kind of get one shot at this to do it right and to do it as efficiently and as effectively as possible. So hopefully we hear this morning on how we are going to do that. And with that, on the first panel for today's hearing we will start with Rear Admiral Joseph Vojvodich, boom, right there, the Coast Guard's Assistant Commandant for Acquisition and Chief Acquisition Officer. Rear Admiral, you are recognized to make your statement. TESTIMONY OF REAR ADMIRAL JOSEPH M. VOJVODICH, ASSISTANT COMMANDANT FOR ACQUISITION AND CHIEF ACQUISITION OFFICER, U.S. COAST GUARD; MICHELE MACKIN, DIRECTOR, ACQUISITION AND SOURCING MANAGEMENT, U.S. GOVERNMENT ACCOUNTABILITY OFFICE; AND RONALD O'ROURKE, SPECIALIST IN NAVAL AFFAIRS, CONGRESSIONAL RESEARCH SERVICE Admiral Vojvodich. Chairman Hunter, Ranking Member Garamendi, members of the subcommittee, good morning. Thank you for the opportunity to speak about the Coast Guard's ongoing activities to recapitalize the surface fleet. On behalf of the Commandant and the men and the women of the United States Coast Guard, I want to express my appreciation for your oversight and continued support of our Service. I also want to note the Service's thanks for including several Coast Guard priorities in the recently passed authorization bill. These new authorities will allow the Service to improve command structure and overall performance. Our internal efforts to achieve continuous improvement are complemented by the valuable oversight performed by this subcommittee and the organizations represented by my distinguished fellow panel members today. We continue to have a very effective working relationship with the Government Accountability Office, Ms. Mackin, and her team. This was evident during GAO's recent review of the National Security Cutter operational test and evaluation activities, which concluded with recommendations that are consistent with our plans to achieve OT&E. We likewise benefit from the research and knowledge of Mr. O'Rourke and the Congressional Research Service. I am honored to have the opportunity to jointly testify with these committed professionals. As the chief acquisition officer, I have the distinct pleasure to lead a talented team in delivering assets and capabilities needed to accomplish the Service's many missions. The importance of this work is reflected by the efforts put forward by this subcommittee and your colleagues to fully support the Coast Guard acquisition priorities in fiscal year 2016. We are fully prepared to execute these funds in an effective and efficient manner. I can say this because we have made investment to mature our acquisition enterprise. We continue to grow a deep and talented acquisition workforce capable of performing critical program management, contract and support functions. We are actively applying lessons learned from each program to improve decisionmaking across the portfolio. From cutter to cutter, program to program, we are approving our processes in a quality of delivered assets. In the end we are providing more capable products to our end users: the men and women in the field who are responsible for executing the missions. We continue full rate production of the National Security Cutter and the Fast Response Cutter, and we are working hard on designing and delivering an affordable and capable Offshore Patrol Cutter. We recently completed preliminary and contract design phase of the OPC, and we are on schedule to award a follow-on contract for detail design before the end of this fiscal year. At the same time, we are acting on the President's direction to accelerate the acquisition of a heavy icebreaker and begin planning construction of additional icebreakers. We recently completed the operational requirements document and released a draft technical package late last month, which outlines key requirements for a heavy icebreaker to advance our industry outreach strategy. Additionally, we started a preservation and material condition assessment of Polar Star, and we anticipate having results later this summer. The Commandant continues to make fleet recapitalization one of the Service's highest priorities, and we recognize the need to achieve affordability in everything that we do. Thank you for your support of the Coast Guard's effort to provide our men and women in uniform with the mission capability they need in the 21st century. I appreciate the opportunity to testify, and I look forward to the questions that you may have. Mr. Hunter. Thanks, Admiral. Our next witness is Ms. Michele Mackin, Director of Acquisition and Sourcing Management for the U.S. Government Accountability Office. Ms. Mackin, you are recognized. Ms. Mackin. Thank you, Mr. Chairman. Good morning, Ranking Member Garamendi, members of the subcommittee. Thank you for having me here this morning to discuss the Coast Guard's cutter acquisitions, in particular, issues identified in the National Security Cutter's testing and in ongoing operations. As was noted, we reported on these issues last month at the request of the subcommittee. I will also share some observations on lessons learned from the NSC and from our work on commercial best practices as the Coast Guard moves forward with the Offshore Patrol Cutter. By all accounts, the NSC is a more capable vessel than the High Endurance Cutters it is replacing. For example, it has increased range and a larger flight deck. The NSC had an important event in the spring of 2014, its initial operational test and evaluation conducted by the Navy's test agent. This kind of operational testing is the only way to ensure that an asset is ready to meet its missions. At the time of the testing, seven of eight NSCs were either delivered or under contract, and three were operational. The test was done on the third NSC, the Stratton. The Navy determined that the NSC is operationally effective, meaning capable of performing its missions, and operationally suitable, meaning it can sustain operations in terms of availability and reliability. At the same time, however, the Navy identified 10 major deficiencies that could affect the ship's operations. In addition, 7 of the 19 key performance parameters were not fully met. Some areas of concern pertain to the combat systems suite. Others pertain to the sea state requirements for the cutter boats that launch from the NSC. Of note, the unmanned aerial system, key to the NSC's planned capabilities, could not be tested because the Coast Guard has not yet acquired a UAS [unmanned aircraft system]. The Coast Guard has plans to address most of the identified issues, and the items will be assessed again during follow-on operational testing, which is expected to start later this year and continue into 2017 or longer, at which point at least six NSCs will have been delivered. In addition to the testing issues, the Coast Guard will need to replace certain equipment after all NSCs have been built. Examples include the gantry crane, which was not designed for a maritime environment and is experiencing significant corrosion, and the single point davit which cannot be operated in high seas as intended. These and other retrofits will cost over $200 million. Further, we identified problems that have arisen during the 5 years the NSCs have been operational. Some of the problems are proving difficult to fix. Key areas of concern are high engine temperatures, which limit the speed of the NSC in certain conditions; cracked cylinder heads, which are occurring at a rate higher than expected; and overheating generator bearings, which have caused at least one patrol to be cut short. Until corrective actions are identified and implemented, the Coast Guard faces increased costs and the potential for NSC missions to be limited. Finally, regarding lessons learned from the NSC, one element is competition. Our work on commercial shipbuilding best practices has found that competition can save money. The NSC procurement was sole-sourced under the Deepwater program, and the Coast Guard is taking steps to inject competition into the OPC acquisition. Another observation is that the Coast Guard plans to conduct initial operational test and evaluation when one of the 25 OPCs is operational as compared to 3 of the 8 NSCs. A third area is warranty provisions. Who pays for the defects and retrofits? In the case of the NSC, the Coast Guard generally will pay. The planned OPC warranty, which according to the Coast Guard will be similar to that of the Fast Response Cutter, would have stronger provisions that should be more effective in protecting taxpayer dollars. And finally, the Coast Guard has opportunities to incorporate best practices in terms of ensuring that the OPC design is solidified and stable before construction begins, and that quality assurance at the shipyard is robust. Mr. Chairman, Ranking Member Garamendi, members of the subcommittee, this concludes my prepared remarks. Thank you. Mr. Hunter. Thank you, Ms. Mackin. Our last witness is Mr. Ronald O'Rourke, a specialist in naval affairs for the CRS [Congressional Research Service]. Mr. O'Rourke, you are recognized. Mr. O'Rourke. Chairman Hunter, Ranking Member Garamendi, distinguished members of the subcommittee, thank you for the opportunity to appear before you today to discuss Coast Guard cutter acquisition programs. Mr. Chairman, with your permission I would like to submit my written statement for the record and summarize it here briefly. As requested, my testimony focuses on how multiyear procurement and block buy contracting could reduce acquisition costs for new Coast Guard cutters. I have seven points I would like to make. The first is that multiyear procurement can reduce acquisition costs by roughly 10 percent compared to costs under annual contracting, and that block buy contracting can reduce acquisition costs by comparable amounts if the authority granted for using block buy contracting includes authority for making economic order quantity purchases of components. The second point is that the Navy has used multiyear procurement and block buy contracting extensively in recent years in its shipbuilding and aircraft acquisition programs, and as a result estimates that it has saved billions of dollars in acquisition costs. That is billions with a ``B.'' Among other things, using multiyear procurement helped the Navy and Congress to convert a 9-ship buy of DDG-51 destroyers into a 10-ship buy and to convert a 9-ship buy of Virginia- class attack submarines into a 10-ship buy. The third point is that although the Navy in recent years has made extensive use of multiyear procurement and block buy contracting to reduce acquisition costs, the Coast Guard to date has not used multiyear procurement or block buy contracting in its cutter acquisition programs. The Coast Guard has used contracts with options in cutter acquisition programs. A contract with options may look like a form of multiyear contracting, but operates more like a series of annual contracts. Contracts with options do not achieve the reductions in acquisition costs that are possible with multiyear procurement and block buy contracting. The fourth point is that the Offshore Patrol Cutter program and the polar icebreaker program can be viewed as candidates for using block buy contracting, and the Fast Response Cutter program can be viewed as a candidate for using either multiyear procurement or block buy contracting. The fifth point is that from a congressional perspective tradeoffs in making use of multiyear procurement and block buy contracting include reduced congressional control over year-to- year spending and tying the hands of future Congresses; reduced flexibility for making changes in Coast Guard acquisition programs in response to unforeseen changes in strategic and budgetary circumstances; a potential need to shift funding from later years to earlier years to fund economic order quantity purchases of components; the risk of having to make penalty payments to shipbuilders if multiyear contracts need to be terminated due to unavailability of funds; and the risk that materials and components purchased for ships to be procured in future years might go to waste if those ships are not eventually procured. The sixth point is that using block buy contracting might save about $1 billion in the Offshore Control Cutter program; that using multiyear procurement or block buy contracting might save more than $100 million in the Fast Response Cutter program; and that using block buy contracting might save upwards of $100 million in a two-ship polar icebreaker program. The $1 billion in potential savings in the OPC program would be about enough to pay for a polar icebreaker, and the combined potential savings across all three programs of about $1.2 billion is about equal to the average annual funding level in the Coast Guard's acquisition, construction and improvements account. My seventh and final point is that in considering whether to grant authority for using multiyear procurement or block buy contracting, Congress may weigh the potential savings of these contracting mechanisms against the tradeoffs I just listed. Mr. Chairman, this concludes my remarks. Thank you again for the opportunity to testify, and I look forward to the subcommittee's questions. Mr. Hunter. Thanks, Mr. O'Rourke. I am not going to ask questions right now, but I would like you to explain just one thing really quickly and then we will start asking questions. Can you just explain in layman's terms what a block buy does and tie it into appropriations and authorizations here in Congress and how the money is appropriated if you do a block buy and you give money for lead materials through the appropriations process here? How does it actually work? Mr. O'Rourke. A block buy contract is similar to a multiyear procurement contract. You can consider it to be the less formal stepchild or step-sibling of a multiyear procurement contract. Like a multiyear procurement contract, it is one contract. It covers several years' worth of procurement, and it gives the manufacturer, in this case the shipbuilder, the assurance that that firm needs to make investments in its capital plant and in its workforce to optimize the situation for the production of the units covered under the period of the contract. That saves money at the shipyard. A block buy contract, if it also has written into it authority for making economic order quantity purchases of components, that is, batch purchases of components upfront, can save money at the component manufacturers. And when you add those savings together, the savings under a block buy contract can be comparable to those of a multiyear procurement contract, on the order of roughly 10 percent, and this has occurred in a number of shipbuilding and aircraft acquisition programs that the Navy and the other DOD services have pursued in recent years. Mr. Hunter. How was the money appropriated? So if you do a multiyear, so say you are buying ships over 3 years, for example. How does the appropriations process work here in the House? Mr. O'Rourke. The appropriations are generally the same. You are doing annual appropriations. There is no need to fund the entire thing upfront. So you are funding the ships in this case one at a time. The one change from annual contracting is that if you are doing economic order quantity, or EOQ, purchases of components---- Mr. Hunter. Say that again. Mr. O'Rourke. If you are doing economic order quantity, or EOQ, purchases of components and you are ordering those components upfront that would be installed across all the ships in the group, then you do bring some money from later years into earlier years to pay for that. Mr. Hunter. Do you mind pulling that closer to you? I have artillery ears, and the rest of these guys are just old. Mr. O'Rourke. The one difference is that if you are making EOQ purchases of components, batch purchases of components, upfront as part of your strategy for achieving savings, then the money to pay for that is moved from later years into earlier years. So in the first year of block buy contract for a group of cutters, you would pay for that first cutter in that year, but you would also make a payment for some of the components for the downstream ships, and that would be in addition. So there is a shifting or re-phasing of a little bit of the money to the extent that you want to use your authority for making economic order quantity purchases--upfront batch purchases of components. But in general, you are still paying for the ships one at a time as you would under annual contracting. Mr. Hunter. So could the manufacturer buy all the steel they want to as the steel market goes up and down? They can wait and time their buys or no? Mr. O'Rourke. It is usually discussed in terms of components, but the authority may extend I believe to materials as well. You can think about pumps and valves, for example, being the kind of thing that the shipbuilder would then order in batch fashion from the component manufacturer so that they can make them in an economically efficient manner, and then they would be ready for installation on each of the ships as those ships are then funded and produced through the life of the contract. Mr. Hunter. What is the difference between lead time materials and having the money appropriated upfront to buy lead materials, and what you are talking about, or is there a difference? Mr. O'Rourke. Somewhat similar. Long lead time materials are ordered ahead of the ship that it is going on so that they will be ready in time for installation on that one ship. In this case if you are doing 25 OPCs or as many as 26 Fast Response Cutters, you are getting as many as 25 things or maybe 11 things for the OPC program, 11 sets of pumps and valves, all upfront, and they would sit there and wait then to be installed on each of the first 11 OPCs or the 26 Fast Response Cutters. Mr. Hunter. OK. And thanks. We are going to jump right back into this, but I would just like to recognize Mr. Garamendi. Mr. Garamendi. Well, let us not jump out of this for a few moments. So the experience of the National Security Cutter and the Offshore Patrol Cutter would indicate that we may be better off looking at a block buy or a multiyear procurement contract for the OPCs; is that correct, Mr. O'Rourke? Mr. O'Rourke. What I would say is that the Navy's experience in reducing shipbuilding and aircraft acquisition costs through the use of both multiyear procurement contracts and block buy contracting offers an example that can be considered by this committee and the Congress for application in Coast Guard cutter acquisition. In weighing whether to do this or not, you would balance the potential savings of these contracting mechanisms against the tradeoffs that I listed earlier in my opening statement. Mr. Garamendi. Ms. Mackin, do you tend to agree with the theory that Mr. O'Rourke is putting forward? Ms. Mackin. I think block buy multiyear can result in savings, but I will just mention Littoral Combat Ship. That was a block buy contract. It has not gone well in large part because the requirements were not firm, and now the Navy, you know, had 10 ships for each shipyard in these block buy contracts, and that was their strategy. So I think it can result in savings, but the key really is to have the requirements nailed down and firm before construction. You may build a few ships and then move into a block buy situation afterwards, for example. So that would be my only caveat there. Mr. O'Rourke. If I could just add very quickly, the Littoral Combat Ship program has had issues and controversy and difficulties, but I view those as being independent of the Navy's use of block buy contracting in that program, and the actual construction of the ships that are under the block buy contract under the LCS program has gone a lot more smoothly than the construction of the earlier ships that were done under annual contracting. Mr. Garamendi. Why was that? Mr. O'Rourke. In part because the stability provided by working out the problems with the initial designs fed into the block buy contracts, and the shipbuilders were in a position where they could then produce them on a recurring, regular basis. Mr. Garamendi. The first ships in any of these three and I suppose the Littoral Combat Ship also, the first ones are kind of like we are going to discover all of the errors and mistakes and problems and hopefully know what they are and get them out of the way, and then move into a more production type procedure. Is that basically what happens all the time? Mr. O'Rourke. I think as a general matter the Navy discovers design issues and experiences cost growth on lead ships that is then, yes, fed into its understanding of the remainder of---- Mr. Garamendi. These three programs are all new ships. Excuse me. Each program is a new program. It is a new ship that had not previously been in the fleet; is that correct? I think so. I am wrong? Mr. O'Rourke. No, the Fast Response Cutter program is well underway, and so if you were to do a contract for that program, you are in the middle of it already. Mr. Garamendi. I did not communicate well. My apologies. What I am saying is that all three of these ships, each one is a new ship at its outset. When the contract was let, it was a new ship. National Security Cutter had never been built before. There are going to be problems. You are going to find out that this did not fit. You really did not want it done that way. What you really needed was something different. That is kind of like the way it is, is it not? I guess the point to us is we should expect that to happen with the first one off the line. It gets into the water; hopefully it floats, and you go from there. Is that more or less correct, Admiral? And then you find the problems. You solve it. You figure out the solutions to the problems, and then hopefully the next ships coming off the line do not have the same problem, correct? Admiral Vojvodich. Yes, sir, there is a great deal of learning that goes on in the shipyard. Mr. Garamendi. In that process. So we might expect for the first cutter coming off in any of these three, first ships coming off in any of these three different types of ships to have problems, right? Wrong? It is going to be perfect? Ms. Mackin. I doubt it will be perfect, but I think this is where the commercial shipbuilding best practices could help inform the OPC acquisition. They are not the same kind of ships, but the principle of building them, the whole mechanical, electrical, the basic construction of the ships, there are definitely lessons to be learned there. In the commercial world, they deliver a ship that works right off the bat, and largely because they make sure that the design is stable before they begin construction. The Navy typically does not do that, and so I think here is an opportunity for the Coast Guard to try to get that part right on the OPC. Mr. Garamendi. Very interesting. So you want to know before you begin to lay the keel what it is you want it to look like when it is completed. Is that what I heard you say? Ms. Mackin. Yes, sir. Mr. Garamendi. And all of the little elements, including the unmanned aerial vehicle? Ms. Mackin. Those are additional capabilities. You know, I think here we are kind of dealing with a legacy Deepwater issue when you talk about the UAS, the cutter boats. The stern doors have problems. A lot of this is the way that procurement went. It was in a sole source environment. The Government had very little control over the requirements in those days. The Coast Guard obviously has come a long way since then. Mr. Garamendi. So I think what I am trying to get is a good sense of lessons learned, which I think is what we are here for today, and the application of those lessons learned to this next class of ships. Mr. O'Rourke. One of the oldest lessons in shipbuilding that has been learned many times over is to avoid design construction concurrency, and the Navy has moved in recent years to get away from that and to take its designs to a high stage of completion prior to starting the construction of the ships, and the degree of completion of design has been moving upward over time. But, yes, that is one of the oldest and most---- Mr. Garamendi. Now, with that foundation in place I am out of time, well out of time, and so I am going to yield back, but I want to come back and circle back around as to whether those lessons are being applied by the Coast Guard. Thank you, Mr. Chairman. Mr. Hunter. Mr. Gibbs from Ohio is recognized. Mr. Gibbs. Thank you, Mr. Chairman. Admiral, you know, I listened to the testimony from Ms. Mackin and Mr. O'Rourke, and I hear a common theme about the purchasing problems. We could save $1 billion if they do purchasing differently. That would pay for an icebreaker. I hear about the warranty. I have got a paper in front of me that talks about some of the challenges the Coast Guard has had, averages four cracked cylinder heads a year. Then the Coast Guard paid for it. Warranty did not pay for it or the manufacturer. Generator bearings, propulsion systems, stern doors maybe leak, may cause the boat to capsize. I am trying to understand these issues. Why are taxpayers paying for these fixes? I mean, how do you guys negotiate contracts here? I mean, how does this work? I think the other two witnesses, the Government Accountability Office and the Congressional Research Service are pretty critical about the procurement and what is happening. So can you expound or enlighten me why this is happening? Admiral Vojvodich. Yes, sir. Thank you for the opportunity to address that. The National Security Cutter is obviously a very complex cutter derived with many complex systems, and so over time as we learn to operate them in the operational environment, we are going to encounter issues out there. And so, you know, when those issues come up, we engage our technical authority to make sure we understand the engineering aspect of it. We engage the shipbuilder as well as the originating equipment manufacturers to understand the solutions. We put plans in place whether it is in design or prototypes or optimization studies, and we look at mission impact. What we have observed with the National Security Cutter, we are able to meet mission. We are encountering issues along the way, and again, through this whole process of technical authority and the shipbuilder, we are addressing those efficiently to make sure that we have the best capability that we can provide to our operators. Mr. Gibbs. So I guess what you are saying is some of this technology, you are developing it as you are building the ship, and so it is not as clear-cut. I mean, we are talking about cracked cylinder heads on a diesel engine. I mean, I would think I missed something here. Admiral Vojvodich. The application of these technologies in a maritime environment in these complex, harsh environments, and again, when we looked at the initial design, a crane, a boat launch, a certain type of engine that has been used, and then we put it in the operator's hands in terms of how we actually apply and use it from a---- Mr. Gibbs. Well, let me ask you. OK. So you have a problem. So it is the cylinder heads, and you go back to the manufacturer. I mean, what kind of discussion do you have about who is responsible? Why does it fall on the taxpayers? Do they assume some responsibility for the defect, or do you think it is all because of the stress and the pressures that the Coast Guard is putting on these ships? It is above the norm? Admiral Vojvodich. In terms of addressing who pays for it depends on the construct of the contract, whether it is in a warranty or it is missing a capability that we put on contract. In these particularities, it depends, sir, and in the case of the engine and the cracked cylinder head, I would like to get back to you and provide you the accurate detail for that particular case. [The information follows:] The Coast Guard has been responsible for paying for replacement cylinder heads on the propulsion diesel engines. The Coast Guard continues to work with the engine manufacturer to study the root cause of these issues and is committed to developing an engineering solution to reduce the frequency of this repair. There have been other component repairs on the propulsion diesel engines, separate from the cylinder heads, where the Coast Guard and manufacturer have shared costs of failure analyses and repairs, and also situations where the manufacturer assumed all costs. In each instance, responsibility for the repairs was determined based on the specifics of that situation. Mr. Gibbs. Ms. Mackin, do you want to respond since you talked about that this morning? Ms. Mackin. I think generally this is one of the lessons learned that we would point to for the OPC. The NSC, the way that procurement was under, you know, the former Deepwater program, it did not have a strong warranty provision. It just did not. The Fast Response Cutter's warranty is much stronger, more what we would think of as a typical warranty, and as I mentioned, that is the same kind of warranty that is planned for the OPC. So if that plays out as planned, it should be better at protecting the taxpayer investment. Mr. O'Rourke. Could I just add one comment though? Mr. Gibbs. Yes, go ahead. Mr. O'Rourke. Warranties are not free. If you tell the contractor that he is going to operate with a contract under warranty, he is going to price that into the contract. So the idea that you can get warranty protection and not have to pay for it, you know, you could be deluding yourselves on that. It is not a question of avoiding a cost to the taxpayer. It is of balancing risk and when the taxpayer might pay for it. If you do not have a warranty provision, the Government might have a bad surprise down the road and the taxpayer would have to pay for it at that point, but if you put the warranty into the contract, the contractor will price that in, and the taxpayer is paying for it along the way. There is no bad surprise. Mr. Gibbs. No, I would agree with that, but I just want to make sure that the Coast Guard is doing their due diligence here to make sure that they are not getting taken for a ride. Mr. O'Rourke. But when you weigh the cost of that warranty against the risks, it may or may not make sense to have that warranty. When you go to a store and you buy some new piece of electronics equipment, the salesperson says, ``Well, do you want to get a warranty on that?'' Now, how many of you have bought that warranty? Probably not many because it is priced in a way that it is not actually a good deal. So from the Coast Guard's standpoint, it is a matter of weighing what the extra cost of that warranty is against the risks and the exposure that it has. That is not an easy task to do because there is some uncertainty involved, but I wanted to make that point because warranties may or may not make sense based on how they are priced into the contract. Mr. Gibbs. I think that is an excellent point, and I appreciate and would agree with that. But I wanted to make sure that there should be some responsibility in some instances back on the manufacturer when trying to do our due diligence. Mr. O'Rourke. And the Coast Guard needs to address that issue with eyes open and take a careful look at it. That is what really needs to happen, and then make as informed a decision as you can on it. Mr. Gibbs. Thank you, Mr. Chairman. Mr. Hunter. I thank the gentleman. I would say, too, just looking at the NSC equipment problems that Mr. Gibbs was just nailing off, it looks like three or four of those are Coast Guard things, and the rest, the cylinder heads, the generator bearings, the propulsion systems, those are not Coast Guard-centric, right? I mean, those are just boat things. Those have nothing to do with weaponization or launching a UAS or launching a small boat off the back. It is not the gantry crane. That is none of those things. It is the engines, right? Admiral Vojvodich. Yes, sir. Mr. Hunter. And I would separate. I mean, you can expect to have issues with new things like the single point launching for the small boats and the crane and the UAS stop and maybe the modules for weapons, but not the engines. I think that is what is kind of surprising to me at least. The gentlelady from California is recognized. Ms. Brownley. Thank you, Mr. Chairman. And I apologize for being late. I was attending another meeting, but I am glad to be here as of now. So if my questions are repetitive, I apologize. But the first question I had had to do with NSC retrofits, and I believe, Ms. Mackin, in your testimony you noted that the GAO review identified several issues that will require retrofits. The Coast Guard plans to maintain the original equipment for the production of the remaining NSCs and conduct retrofits after accepting delivery. So my question is: does the GAO believe that this decision will result in a cost savings for the Coast Guard? And how long would the new NSCs be out of service while these retrofits are being made? Ms. Mackin. Some of the retrofits have been known for many years, for example, the structural enhancements on the first two NSCs. I am not sure exactly what the timeframe will be, but I would expect many months for those two ships. Others like the gantry crane were never intended for a maritime environment. So obviously it is experiencing corrosion. That will need to be replaced on all the ships, and there are prototypes right now, which is one reason they are testing the prototype on the third NSC before they go back and do the retrofits. Maybe the admiral will have a better idea about how long the retrofits will take. Ms. Brownley. Can you speak to any cost issues relative to that? Is it going to cost more? Will there be cost savings? Ms. Mackin. The Coast Guard estimates a little over $200 million for the known retrofits. How that will play out time will tell because they have not taken place yet, and some of that will depend on how they contract for these and what that will look like, and that is not known at this point. Ms. Brownley. Thank you. Admiral, thank you for your service. If you have any comments. No comment? I mean, any terms of downtime with the retrofit, will it impact the Coast Guard's mission readiness at all? Admiral Vojvodich. Ma'am, thank you for the question. When we leave the cutter production at the shipyard, we incur costs, and sometimes we try to optimize the overall cost in terms of delivering a mission complete cutter. Sometimes it is to our advantage to be able to get it out of the shipyard and put it in the hands of our sailors to operate it, to understand it, and then we get to pick the time and choose the time in between a deployment or an opportunity to learn more about the cutter to put in those retrofits in a place that we could perhaps compete and thoroughly understand the design with our technical authorities, as well as any of the manufacturers that we are involved with. Ms. Brownley. Thank you. Ms. Mackin, again, in your testimony you noted that several weapons systems and the radar were repaired following initial operational test and evaluation, but the post-operational reports indicated persistent problems with these systems. So what types of problems do persist? Ms. Mackin. There have been some problems with the combat systems suites. The air search radar, for example, has had some parts fail, and it is taking some time to get replacement parts from overseas. So that is one issue that has been coming up in operations. In the test event itself, some of the weapons systems did not function as intended. As I noted, the Coast Guard has plans to fix those problems, and we will see how they do in the follow-on testing. Ms. Brownley. So would you describe these problems as isolated incidences or reoccurring in terms of other cutters and issues? Ms. Mackin. Frankly, until the follow-on testing is complete, which as I mentioned will not be until 2017 or later, it is hard to answer that question for sure. The Coast Guard will continue, I am sure, during operations to get more information, but really that operational testing that is very rigorous is the best way to ensure that these are not repeatable problems. Ms. Brownley. And who are the providers of the parts that are late? You said they came from overseas. Ms. Mackin. It is a German firm. I do not recall the name off the top of my head. Ms. Brownley. Thank you. I yield back, Mr. Chairman. Mr. Hunter. Great question there on the end, too. I did not know we were buying German stuff with our taxpayer dollars. That is good. Mr. Sanford, the gentleman from South Carolina is recognized. Mr. Sanford. Thank you, Mr. Chairman. Two quick questions. One, we had a brief conversation about multiyear contracting and block buy contracting, which is ultimately I guess all about fleet modernization, and what hit me is the real next cusp of fleet modernization is really tied to the air. You know, vessels are important in terms of patrol, but ultimately if you really want to leverage that capacity in terms of intelligence, surveillance, reconnaissance, et cetera, you really need to have things attached to you that give you a much wider view than a patrol would. And yet it seems that the stuff that I have read has suggested that we are really behind with Guard unmanned aerial systems on the new National Security Cutters. Bring me up to speed on that. Why the lag? Because it seems to me if you are really going to leverage taxpayer dollars, that is a vital way of doing so. Admiral Vojvodich. Sir, thanks for that question. So the unmanned aerial system requirement exists in the National Security Cutter. We have looked at other solutions in terms of optimizing from an affordability perspective in delivering capability. We are working through a number of options, and one of the ones that we want to team up with is making sure that we are acquiring mature technologies that provide some capability, that some of the risks are wrung out, if you will. So we partnered up with the Navy who has a small UAS program that delivers some capability. Right now we are looking at the design aspect, integrating with the National Security Cutter, and we anticipate in a year or so to be able to deliver some capability on the National Security Cutter here and test its capability accordingly. Mr. Sanford. Yes, ma'am. You had a thought as well? Ms. Mackin. I was just going to note that the UAS capability has long been an integral planned part of the NSC's capability as you mentioned, and it has been delayed. It was supposed to be initially available in 2007. It turned out to be way too expensive and some technology problems existed there. So the Coast Guard has been studying it for many years since then. As the admiral noted, it sounds like a small UAS will be available to be assessed in the follow-on testing. Mr. Sanford. But we still move forward with these vessels, but not the part that really leverages the vessels' capacity. It just seems to me we have got a little bit of that backward, but I will skip to a second question. The GAO report suggested, I guess, the Fast Response Cutter and the HC-144 Maritime Patrol Aircraft that the initial testing basically said it was not fully operational, and this really goes back to my colleague's point with regard to things going wrong on ships and yet full procurement was approved. Why would you go forward with something where in essence there are bolts in the system that are not working so well, yet you are going to go ahead with full production? Help me understand that sequencing. Admiral Vojvodich. We follow a very rigorous process to understand what we are acquiring, and so we go through this initial operating, test and evaluation, and we get in our operators' hands. We demonstrate through an independent operational test authority, again, that it is operational, it is suitable, and effective, and that allows us to move forward to do mission. It allows us to get it into the operator's hand to be able to do---- Mr. Sanford. So let me just interrupt then. So what you'd say is the GAO was off in their report? Because I mean their words were that neither asset met all key, ``key'' in their words, key requirements during initial operational testing. Admiral Vojvodich. At the high level we are ready to operate. There are aspects of the cutter that did not meet some of the testing criteria. Mr. Sanford. So you disagree with their definition of ``key.'' Admiral Vojvodich. Those are our words. Those are key elements of the cutter. We have to demonstrate that. We are committed to complete the testing in the fall, operating test and evaluation. Mr. Sanford. I have got 22 seconds. So let me just throw one other thought at you and respond as best you can, which is the GAO report was also critical with regard to Coast Guard notifying Congress of performance breaches. Anything new that the committee ought to be aware of on that front? Ms. Mackin. We did make a recommendation there largely pertaining to the guidance of the Department of Homeland Security. It was not really clear. If you did not meet a key performance parameter during the testing, does that mean you are in breach and should report to Congress? DHS has since, based on our recommendation, revised its guidance to allow for the follow-on testing to prove that those key parameters can be met before a breach is reported. Mr. Sanford. Thank you very much for your testimony. Thank you, Mr. Chairman. Mr. Hunter. I thank the gentleman. Mr. Garamendi is recognized. [Inaudible.] OK. Mr. Graves is recognized. Mr. Graves of Louisiana. Thank you, Mr. Chairman. The acquisition schedule for NSC, FRC, OPC is concerning for a number of reasons when you look at the increased mission of the Coast Guard, and I think that has come up in several hearings that we have had over the last few years. Mr. O'Rourke, one thing that the Navy last year retired the USS Simpson, which is the last of the Perry-class frigates; those served as a law enforcement platform for Coast Guard law enforcement detachments for operations particularly in the Caribbean. Last year at a hearing Admiral Z noted that he had his eyes, I think, on 90 percent of the transit of drugs, but only had the capabilities to address 20 percent. What does the loss of that Perry-class platform do to the Coast Guard's capabilities? Mr. O'Rourke. I think the admiral was better prepared than I am to speak to that. I have been at hearings where this issue was discussed, and, yes, the shortfall in available cutter hours down in the southern region has reduced the fraction of drug interdiction warnings that the Coast Guard is actually prepared to act on, and they have intelligence that they sometimes cannot act on due to lack of assets. Mr. Graves of Louisiana. Is it safe to say that the acquisition schedule for the vessels I mentioned is not meeting demand, I guess, for lack of a better term, in regard to the Coast Guard's mission? Mr. O'Rourke. In a couple of ways. One is that the total number of cutters planned under the Coast Guard's program of record is well short of the number that the Coast Guard has previously calculated would be needed to fully perform all of the Coast Guard's projected missions in coming years. In fact, the number is about 60 percent. So the program of record would get you about 60 percent of the cutters that the Coast Guard feels it will need in future years under an earlier calculation to do all of its missions. Mr. Graves of Louisiana. OK. Mr. O'Rourke. A second way that the schedule is problematic is that the speed at which you are bringing on those ships is late compared to the end-of-service lives of the older assets they are replacing. Mr. Graves of Louisiana. Sure, sure. OK. Mr. O'Rourke. And that is well established as a function of the schedule. Mr. Graves of Louisiana. Thank you. Admiral, switching topics, the inspector general reported that the MarAd [Maritime Administration] should maintain an inventory of vessels, U.S. vessels that are to be disposed and suggested that MarAd work with folks like the Coast Guard to maintain that inventory of vessels. Are you aware of any efforts by the Coast Guard to work with MarAd to maintain a list of vessels to be disposed for scrapping purposes? Admiral Vojvodich. I am not aware of the specific list that you refer to with MarAd. We do work with MarAd, but I am not--I do not have any knowledge. Mr. Graves of Louisiana. Would you mind submitting on the record just an explanation of efforts by the Coast Guard to work with MarAd? In that same regard, the Coast Guard vessel Storis was scrapped by MarAd, and as I recall, that vessel was scrapped in Mexico, which I believe was contrary to U.S. law, which required that scrapping efforts take place in the United States. Are you aware of any efforts by the Coast Guard to address that inconsistency with MarAd? Admiral Vojvodich. I will provide a response for the record. [The information follows:] MarAd is the program manager regarding scrapping of a variety of mothballed ships in the National Defense Reserve Fleet (NDRF). MarAd does not provide a list of NDRF vessels to the U.S. Coast Guard that are pending scrapping. MarAd does post a list of those vessels available for disposal in our open ship disposal solicitation DTMA-91-Q-2013-0014 posted on the Federal Business Opportunity Web site. The Coast Guard has no engagement regarding the selection of ship recycling facilities used by MarAd. Mr. Graves of Louisiana. Great. Thank you. Mr. O'Rourke, one last question. Certainly you are familiar with increased activities in the Arctic, and could you just give a quick assessment of U.S. ice breaking capabilities compared to some of the other Arctic nations? Mr. O'Rourke. Yes. The Coast Guard currently has two operational polar icebreakers, one heavy polar icebreaker. That is the Polar Star, and one medium polar icebreaker. That is the Healy. There is one additional heavy polar icebreaker. That is the Polar Sea. That ship is nonoperational. So the operational fleet can be characterized as one plus one, one heavy, one medium, and one additional heavy in nonoperational status. Mr. Graves of Louisiana. Do you see those capabilities as being sufficient, noting again increased activities in changes in the Arctic? Mr. O'Rourke. What I can tell you is that the Department of Homeland Security has issued their own mission need statement. That is an official requirement statement expressing the view of the Department of Homeland Security, which states that the Coast Guard in coming years will potentially need up to three plus three polar icebreakers. Mr. Graves of Louisiana. And you mentioned that is in the Homeland Security report. Do you see that mission as solely being a Homeland Security or Coast Guard mission, or do you see other agencies, again, looking at what other nations are doing; do you see other agencies perhaps with the Department of Defense are having additional needs outside the scope of that report? Mr. O'Rourke. Oh, it is well established that the Coast Guard is operating its polar icebreakers as a national asset that serves the needs not only of core Coast Guard missions, but for other agencies as well, in particular, the National Science Foundation. A lot of what we use our polar icebreakers for is to support scientific research activities. Mr. Graves of Louisiana. What about military defense missions? Do you see a need there? Mr. O'Rourke. The icebreakers also have requirements under our military plans to meet national defense requirements. And part of the reason for going up to three plus three potentially is to meet presence requirements for polar icebreakers that the Department of Defense has communicated to the Department of Homeland Security. Mr. Graves of Louisiana. Thank you. Mr. Chairman, I am going to note that CRS just endorsed your bill. Thank you. Mr. Hunter. I thank the gentleman. Mr. Garamendi is recognized. Mr. Garamendi. I am trying to figure out how to structure my work and in a way that has the maximum potential of resolving problems in the two projects that are going forward. Ms. Mackin and Mr. O'Rourke, you have done extensive research on the problems that exist in the National Security Cutter and the OPC. Both the Fast Response Cutter and OPC have work to be done, new ships to be built, new contracts to be let. In reviewing the testimony and reviewing your work, you have information that I think can be put into a checklist, a list of things that need to be done to reduce the potential for problems. But I do not have a list, nor do I see a list in your testimony. I think it would be very, very helpful. I can spend a lot of time asking questions, and I would probably learn a lot, but it seems to me that if we could have the development of a checklist. These are things that the Coast Guard should and must do to avoid problems that we have seen develop in the previous National Security Cutter program or the OPC. Can the two of you, individually or together, develop such a checklist? And we can then hold the Coast Guard responsible to addressing. ``Yep, we did that one. That problem is not going to happen again because we are paying attention. Maybe we ought to pay attention to this one because we have not paid attention to it.'' Is that possible for you guys to do? Mr. O'Rourke. It is not only possible. I have already developed a list of well-established lessons in shipbuilding. I am sometimes asked for it. I will be happy to provide it for you after the hearing. Ms. Mackin. And for our part, I think in my statement I mentioned several items that there are lessons learned from NSC and commercial practices that could be applied to OPC. We could provide that. Mr. Garamendi. I have noticed it is not to say that you have not thought about it because you have, but you know, maybe we can just get a little computer file and it says, ``Check this off. Let us see. We are going to have some sort of a cannon, and does the Navy have that cannon already and can we just use the Naval cannon and, by the way, the control system for it and radar systems which may be available?'' Anyway, just a checklist, if you could develop that, that would certainly be useful to me and save probably a whole round of questions as I pursue trying to figure it out. So I am asking for it from both of you, and if you want to work together that would be OK, too. Ms. Mackin. OK. Mr. Garamendi. Thank you very much. And with that I yield back. Mr. Hunter. I thank the gentleman. OK. Now it is just you and me. Let us go back, multiyear procurement, block buy contracting, advanced procurement. Admiral, what does the Coast Guard have the statutory ability to do out of those three, if any? Admiral Vojvodich. Mr. Chairman, we have authority through title 10 to be able to do a multiyear procurement. We understand the benefits of that in terms of once we have a stable design, enduring need, and a good understanding of the cost. Those are great criteria to use. We are also looking at potential downside. It does commit the Government well in advance of the year of appropriation in terms of things that we are going to buy, and so the downside is that if we are not able to meet that obligation, there could be a real downside in that contract in terms of not providing the expected funding for the multiyear buy. Mr. Hunter. But that is not your job. That is our job. Admiral Vojvodich. Yes, sir. Right. Mr. Hunter. So you have the statutory ability to do advanced procurement. Admiral Vojvodich. Yes, sir, advanced procurement, yes, sir. Mr. Hunter. And multiyear. Admiral Vojvodich. Multiyear procurement, yes, sir. Mr. Hunter. Have you ever used multiyear procurement? Admiral Vojvodich. I have not. I will have to go back in the archives and research that. Mr. Hunter. Well, we have the research right over here. Have they ever used multiyear procurement? Mr. O'Rourke. I am not aware of the Coast Guard having used it in the past. I cannot prove a negative on it, but in the years that I have been here I have not seen it. Mr. Hunter. So I guess that leads to you already have the statutory ability to do multiyear procurement, which you could have done with the FRCs and did not do. You could have done it with the NSC. You did not do it. Did you use advanced procurement? Advanced procurement I am guessing is the batch buys, or is that buying stuff for the one vessel? Admiral Vojvodich. We buy long lead time material that is in front of what is going to come in product. Mr. Hunter. That is per one vessel, right? Admiral Vojvodich. That is per one or a number of vessels that might be coming up in that production cycle within that particular fiscal year. Mr. O'Rourke. Right. That is only for 1 year's worth of procurement. Mr. Hunter. OK. Mr. O'Rourke. Either the ship or the multiple ships being procured that year, and that helps to optimize the construction schedule just for those ships, but that is still implementing annual contracting. Mr. Hunter. So Mr. O'Rourke says you could have saved $1 billion, could have saved, not can still save, but could have saved with the NSC. Mr. O'Rourke. The savings in my testimony are all future savings out there that could be realized. We missed opportunities for doing that with the National Security Cutter and the first 36 ships in the Fast Response Cutter program. Mr. Hunter. OK. So why not do it? If the Coast Guard has the ability to do it, why didn't the Coast Guard do it? Why not save $1 billion? Admiral Vojvodich. We chose a contract strategy that encouraged options, sir. We can look at that further. We will have to work with the Department administration to really understand the upside and the downside of that, but we are willing to take another look at that. Mr. Hunter. Well, let me ask you this, Ms. Mackin and Mr. O'Rourke. When it comes to the Coast Guard then and the administration, where does OMB play in terms of what the Coast Guard can do, meaning what type of contracting strategies they can use? Do they have a play in it? I mean, how does the administration play in terms of what their strategies are for contracting future ships? Mr. O'Rourke. In general, my understanding is that OMB can give directions to agencies regarding the ways in which it can carry its programs forward. Now, what OMB may or may not have said about the use of multiyear procedure or block buy contracting for these programs I do not know, but as a general issue, OMB can issue instructions to executive branch agencies, guidance if you will, for how programs are to be executed. Mr. Hunter. Ms. Mackin? Ms. Mackin. All I would say is for the National Security Cutter, I am not sure that would have been a good approach because the requirements were not stable. We are still seeing problems now. The first two ships are going to have to go through these structural enhancements. They are not representative of the rest of the ships, and so I think, again, not that it is a bad idea, not that it cannot save money, it is just that, as the admiral mentioned, it needs to be carefully considered. Mr. Hunter. And the one example, the LCS is a horrible ship, ships, right? The requirements were not set for and now they are lowering the number of LCS they are going to make in the future because they realize it was not the right ship. They just wanted to get numbers, et cetera, and all of the problems that they had. I am look at one of the big retrofits. It is like $80 million for the C4ISR [command, control, communications, computers, intelligence, surveillance and reconnaissance] in the NSC. Why are things like that not simply taken from the Navy? It is not like the Coast Guard has to do special things that are tens of billions of dollars Navy budgeting has not already had to look at, in terms of weapons systems, C4ISR, radar, UAS. You already talked about piggybacking with the Navy on UAS, thank God. Why the C4ISR retrofit? Why would the Coast Guard possibly need their own type of C4ISR modules or platform? There is no way it is more all-encompassing than what the Navy has. There is no way. Ms. Mackin. One thing I would offer, and the admiral can weigh in, is this, again, is a legacy Deepwater issue. The original C4ISR was an ICGS, Integrated Coast Guard Systems, a contractor system, very proprietary. Mr. Hunter. But why would the Coast Guard want to do that even then? I mean why would you have people in the Coast Guard say, ``Let us develop our brandnew system that is probably much more limited than what the Navy has anyway, but let us do it all for us''? Why would they decide that, even with the flawed Deepwater system, a program that was flawed for other reasons? Who in the Coast Guard would say it is a great idea for us to develop our own multimillion-dollar communication C4ISR platform? Ms. Mackin. That was inherent in the Deepwater strategy. The contractor said, ``Here it is,'' and frankly, the Government did not have adequate insight into the requirements, and the contractor made that call and so now the Coast Guard is opening up, opening up the architecture and implementing actually a very more cost-effective C4ISR system. Mr. O'Rourke. Mr. Chairman, if I could go back to your earlier question about the missed opportunity on the National Security Cutter, Ms. Mackin is right, of course, that there were problems with the design of that ship, but one of the statutory requirements for using multiyear procurement is that the item being procured has to have a stable design. In shipbuilding programs, stable design is demonstrated by completing the construction of the first ship in class and putting it through its initial testing to show that there are no problems. At that point, once those problems had been identified and, in fact, they were cranked into later ships in the NSC, you had a design that might then have met the statutory requirement for stable design, and the follow-on ships in the program could have been pursued under multiyear procurement. So it is correct that you do not want to do this if you think that the design is not stable, but as you review the schedule of how these events transpired, multiyear procurement is never used on a lead ship anyway because of the requirement for stable design. It was a question of whether the program was ready for multiyear procurement for the follow-on ships in the class, and that is a question that people could have looked at and decided, well, yeah, it might have been. Mr. Hunter. I am not clear on that. On the NSC when you had some testing done, you had the first couple of ships done, were the problems that we are looking at, and we are looking at this. We already got this, but this is a nice, little page that has a lot of the issues, right? These were not recognized right away? No one realized that there were issues until the fourth ship, fifth ship? At what point did you realize there were some issues? Admiral Vojvodich. Sir, some of those issues were revealed during operational test and evaluation through the test event. Mr. Hunter. Oh, the first ship? Admiral Vojvodich. In this particular case we used a third ship to demonstrate. Mr. Hunter. But the first ship was working well or these same issues were on the first ship as well? Admiral Vojvodich. Not that I know of, but I can get back to you. If there is a lineage that we can provide, we certainly will do that. A number of those items, sir, if we leverage a Navy program of record like you just commented, that we need a weapons system and we need a particular sensor system; we leveraged the Navy on a number of those things outlined, and we will follow the Navy's priorities and look to them to, you know, help us develop those solutions and implementation. And then over time as we get smarter and better users, we have brought more cutters, and we have more sailors that are accustomed to using the equipment. You know, we will become better and more proficient with the usage of the system. Mr. Hunter. I still do not understand that. OK. So you have one NSC goes into the water and people start operating it and it goes and does its thing. There are no issues there. The second NSC jumps in the water. It goes out and starts being tested, and it is used operationally while it is being evaluated, and no problems there. Nothing changes. You built the third NSC, put it in the water, and you have all of a sudden realized all of these different issues on the third one that no one saw on the first one or second one? Admiral Vojvodich. The third one was our opportunity to really have the capability that is reflective. So Ms. Mackin alluded to the changes---- Mr. Hunter. Can you explain that though? Why is number 3 the charm? Why could you not recognize the operational capability of the first or second ones? I mean, why did you have to wait until number 3 to really delve into it? I am just not understanding. Admiral Vojvodich. I would like to get you a finer detail for the record sir, for that one. Mr. Hunter. No, no, just tell me how. I do not need fine detail. Why is it boat number 3 is the one that we started recognizing issues and not the first one? I am not trying to get you. I just do not understand. Admiral Vojvodich. Right. So that is the one that we said that is the one that we will have crews on it that is going to be indicative of future National Security Cutters. We want that one to be tested because that is going to demonstrate the initial operating capability. Mr. Hunter. Did you dramatically change design after the first two on the third one? Admiral Vojvodich. We did, and I will have to give you a level of detail on that, sir. [The information follows:] The third NSC, USCGC Stratton, was chosen for Initial Operational Test and Evaluation (IOT&E) because it was the first cutter considered representative of the fleet for the foreseeable future. That is to say Stratton's fundamental characteristics and capabilities represent that which is intended for all NSCs. As it relates to the first two NSCs (Bertholf and Waesche), there were two compelling reasons why the Coast Guard, Department, and the Navy's Commander Operational Test and Evaluation Force (COMOPTEVFOR) chose not to use them for IOT&E: 1. Cutter boat handling systems: Based on operational feedback from the first two NSCs, an improvement was needed for these systems. This included the original overhead gantry crane on the stern of the ship and the single-point davit on the starboard side of the ship. The overhead gantry crane was replaced with three folding boom cranes and the side davit was replaced with a new davit system offering improved control and handling during boat launch and recovery. These were first installed and tested on Stratton. To maximize the benefits of, and document best practices during formal testing, it was determined that the new cutter boat handling systems should be tested in IOT&E, and therefore Stratton was selected. The cutter boat handling systems for Bertholf and Waesche will be upgraded during their respective structural enhancement periods. 2. Structural enhancements: Neither Bertholf nor Waesche had undergone the structural enhancement to ensure at least a 30- year fatigue life of the ship's structure. These two cutters were too far along in construction to incorporate the structural enhancements during construction without incurring inordinate contract cost and schedule impacts. Although not a disabling impediment to testing, structural differences between Stratton and the first two NSCs were considered relevant to ensure IOT&E results were most representative of the end-state fleet. Mr. Hunter. OK. And how many of these were built with the Deepwater boondoggle? How many NSCs were built under the Deepwater plan? Mr. O'Rourke. Well, the Coast Guard transitioned out of Deepwater in 2007, and that transition was phased with the completion of contracts that were legacies coming out of that period. I do not know what the exact cutoff point was, but this is now a nine-ship program, and at some point most or all of the significant design issues with that class became known, and any ships procured after that point might have been considered candidates for multiyear procurement or block buy contracting. The prices we paid for those ships suffered for a number of reasons. One is the general Deepwater contracting environment that Ms. Mackin mentioned, but there were two others. One is that the intervals that we had for procuring these ships were not regular and even. So the shipyard did not have a steady drumbeat. And the third was that the final ships in the program were not done under a form of multiyear contracting. These are all ways in which those ships turned out to be more expensive than they might have been. Mr. Hunter. Admiral, do you agree with that? Do you agree that multiyear procurement and block buy contracting can save money? I mean, obviously it is not going to work if your first two ships are not really what you wanted in the first place, where you have actually changed so much design on the third one that it is the real ship that you are going to test against, but if you were going to do it the way that the Navy does it, meaning the right way, building, have all the lead time materials, do it right, do all your testing on that one ship, and then be able to do multiyear going out, does the Coast Guard have an issue with that? Do you think that that would save you money? Admiral Vojvodich. We would have to look at it a lot closer, sir. We would absolutely love to---- Mr. Hunter. Well, I am asking you. You do not have to look at it closer because in general does contracting ships like the Navy does it, especially when you only have really three or four types of ships in the entire Coast Guard, it is not too complicated, right? Do you think that that would save the Coast Guard money? Admiral Vojvodich. As we indicate here, if we have a stable design, we have an enduring need, where the costs are well, well understood, the applicability of the multiyear procurement has some merits, and we will take that back for a high-level consultation. Mr. Hunter. Do you disagree with Mr. O'Rourke that it will save you $1 billion in the NSC? Admiral Vojvodich. I would have to look at that closer, sir. Mr. Hunter. OK. Do you disagree that you would save $100 million with the FRC? Admiral Vojvodich. Again, in the application of that particular strategy in terms of what we have here, I would have to look at it a lot closer. Mr. Hunter. OK. When the Navy went to block buys and multiyear procurement, did they just do it on one design and did they pick that ship design on purpose to do this on, or was it more of a ``we can use this in any kind of ship class; let us just jump into it''? I mean, how did the Navy decide to do it and was there anything special about when they decided to do it and on what type of ship? Mr. O'Rourke. The Navy decides its contracting strategies on a program-by-program basis, but I think there was a general atmosphere within the Navy in recent years that these contracting mechanisms made sense to them, and they began to use them more extensively. I think it is important to note that all three of the Navy's year-to-year shipbuilding programs where you get a ship of that kind every year, year after year, all three of them, the Virginia-class attack submarine, the DDG-51, and the Littoral Combat Ship, are now under multiyear contracting, and collectively those ships represent more than two-thirds of all the ships in the Navy's 5-year shipbuilding plan. That is how extensively the Navy is using this. And in terms of savings, if you looked at the last DDG-51 multiyear, the savings on that were estimated at $1.3 billion or $1.4 billion, and if you look at the last Virginia-class attack submarine multiyear, the savings on that were estimated in the range of $3 billion to $4 billion. So just on those two instances of multiyear procurement contracting, the Navy saved more than $4 billion. Mr. Hunter. Has the Coast Guard looked at what class of ship would best fit the multiyear procurement contracting scheme? Admiral Vojvodich. Well, we read Mr. O'Rourke's report. We understand the utility of a multiyear strategy. We have considered it, and we have chosen the acquisition strategy that we are on right now. Mr. Hunter. When you do multiyear procurement, do you need us in this committee to authorize it? Mr. O'Rourke. Yes, multiyear contracts, more than a certain value, and these would be more than that threshold value, would need---- Mr. Hunter. But does it have the statutory ability right now to do multiyear procurement? Mr. O'Rourke. They have a statutory framework in which the Services can conduct multiyear procurement, and that framework requires approval by Congress on a case-by-case basis for each program. Block buy contracting has no title 10 or permanent statutory framework, and so in the instances where Congress has provided that for the Navy, they have done it through specific legislation. In one time they did it in an NDAA [National Defense Authorization Act], and in another time they did it in an appropriations bill. Mr. Hunter. So it would be the Appropriations Committee or the authorizing committee can both grant that authority? Mr. O'Rourke. Based on the precedent of the two block buy contracts for Virginia-class and Littoral Combat Ship, it appears that the authority can be provided through a single act that can be either a National Defense Authorization Act or an Appropriations Act. Mr. Hunter. Say that the Navy did not want to do it. Say that the Navy was like the Coast Guard and we do not want to save billions of dollars. We just want to spend money. That is not fair, but I am kind of exaggerating. Can Congress make them do it? Mr. O'Rourke. The authorities that were granted for Virginia-class and LCS allowed the Navy to do it. They did not mandate, but it may be that you can write the language so that it mandates the use. For example, the Appropriations Committees in the past have said that the Navy will contract for the ship. It was an amphibious assault ship, which shall be funded on an incremental basis. And that is incremental funding, which is different from what we are talking about here. But the use of the ``shall'' language mandated that to the Navy as the way that the ship would be funded in coming fiscal years. And based on that precedent you might imagine that language for block buy contracting can use the ``shall'' language and not simply to say that the Coast Guard may contract or may do this. Mr. Hunter. So the one last thing, I am not understanding that. How do you see it, and, Admiral, we will start with you; how do you see the Coast Guard? Let us just talk about buying ships. How is the Coast Guard different from the Navy? Now, I do not mean in what size of ship, but in the way that you acquire them, why should the Coast Guard be contracting differently than the Navy? Admiral Vojvodich. Mr. Chairman, fundamentally we acquire and build ships very similarly. We use some of the same facilities that the Navy does. There are a level of requirements that might be different that might change the approach or the testing or the scrutiny of the hardening of the various ships, but fundamentally, you need steel. You need a shipyard. You need a lift. You need proficient workers to put it all together, and so there are some aspects that are exactly the same. There are other ones that are some nuances that we would have to look at closely, but those probably are on a case-by- case basis. Mr. Hunter. Ms. Mackin, why should the Coast Guard ship acquisition be treated differently than the Navy? Ms. Mackin. I think there is one thing that has not been mentioned in this discussion and that is the contract type of the ships. The Fast Response Cutter was firm-fixed-price, and that is consistent with commercial best practices. That is the price is nailed down, and that is one reason they could negotiate a very strong warranty. I believe the plan for the Offshore Patrol Cutter is to transition to firm-fixed-price at some point in time as well. So block buy is one thing to look at, but contract type can also be a way to save a significant amount of money. Mr. O'Rourke. But the statute that regulates multiyear procurement requires that multiyear procurement contracts be fixed-price contracts, and the block buy contracts that are being done for the Littoral Combat Ship program are also fixed- price type contracts. Ms. Mackin. They are fixed-price incentive (firm target), which is a little different than firm-fixed-price. Mr. Hunter. But again, why should the Coast Guard acquisition be treated differently than the Navy? Ms. Mackin. I mean, that is a contracting officer's call in large part. There are lots of factors to consider. I am just offering the contract type is one very important component. Why the Coast Guard did not consider block buy for the Fast Response Cutter, I do not know the answer to that. Mr. Hunter. Admiral? We can get it right now, Ms. Mackin. Admiral Vojvodich. For the OPC that is absolutely considered, but the path that we chose is not a multiyear procurement. I would be happy to take a closer look at the merits and the risks associated with that and provide a more thorough response. We would have to work with the Department and administration and make sure that we collectively understand the approach, and I am happy to follow up with you at some point, sir. Mr. Hunter. Admiral, here is what I am not understanding. If you build one or two ships, whether it is an FRC or the OPC, and you look at it and you test it and you evaluate it and you find problems and you then fix your problems, what is the downside with doing a multiyear procurement? What is the downside, if any? If you have a design that is not flawed like the NSCs that we discovered on ship 3, if your design is good and your ship is good and your requirements are firm and set and fixed, what is the downside? I am not getting it. Admiral Vojvodich. And I understand. Based on my understanding the downside is that if we are unable to not meet that future year commitment---- Mr. Hunter. But that is not your problem. Admiral Vojvodich. I understand. Mr. Hunter. So what is the downside to the Coast Guard? Why would the Coast Guard not want to do that? Ms. Mackin. Can I make an observation? Mr. Hunter. Yes. Ms. Mackin. The FRC had its initial operational test and evaluation and only one of its key performance parameters was even partially met. So it is not proven yet. It still has---- Mr. Hunter. So you are say only one out of a bunch. Ms. Mackin. Out of six. Mr. Hunter. Was partially met. Ms. Mackin. Was partially met, and so they are going to have the follow-on operational test beginning this fall, just like the NSC. So---- Mr. Hunter. How many FRCs have been built now? Anybody? John might know? Mr. O'Rourke. Well, there are 14 or 15 of the FRCs in operation. Admiral Vojvodich. Commissioned number 15 a week or so ago and deliver number 16 at the end of the calendar year. Mr. Hunter. And so is that normal to build that many when the operational requirements, whatever check boxes you have, are not met? Ms. Mackin. It was a fast-paced procurement. I would not say that is consistent with best practices because they still have to go through the follow-on testing and prove that they can meet those key performance parameters. Mr. O'Rourke. Right, but the issue is that even with the deficiencies that have been discovered through initial testing, the Coast Guard's intention is still to continue getting the ships. So the question is: if you are still going to continue getting the ships, does it make sense to continue doing it under a contract with options which operates closer to being a form of annual contracting or under block buy? Mr. Hunter. Mr. Graves is recognized for 5 minutes. Sorry about that. Mr. Graves of Louisiana. Yeah, that is all right. I mean, I am enjoying it. To somewhat channel the chairman's frustration, you know there are two key things obviously that are, I think, his frustrations and ones that we share. One is that looking back over the last several years, certainly I think one can make a strong case for perhaps some taxpayer dollars not being used as wisely as they could have been on the acquisition, and something that is very important to me personally and I know the chairman shares it is the lack of capabilities. I made reference earlier to Admiral Z's statement that eyes are on 90 percent of the drug trafficking shipments, yet capabilities only respond to 20 percent of them. I think when you look across the Coast Guard's mission, which has expanded significantly over the last several years, the demand for the Coast Guard, the demand for the Coast Guard to have greater capabilities is significant, yet this acquisition schedule is continuing to drag on and, I think provide readiness issues that are not just limited to the Coast Guard but also transcends over to some of the support for Navy and other capabilities that are important for this Nation. So looking back, we can talk about Deepwater. We can talk about NSC, FRC, whatever you want, but let us look forward for a minute. Looking at OPC, can you talk about some of the lessons learned that you were applying to that acquisition strategy that will ensure, again, fair use of taxpayer dollars, and ensure that we are delivering solid equipment within an appropriate amount of time? Admiral Vojvodich. Yes, I would be happy to. I appreciate the opportunity. The key to all of this is to make sure that we have well understood, stable requirements that have been vetted throughout the Service with industry to make sure they understand it very well. It allowed us to have the conversation to understand where the cost drivers are, if you will, and to be able to address that, to make those appropriate adjustments. We are using competition to the fullest, and we are also using fixed-price contracting throughout the acquisition, which is at times very difficult in a large ship buy because there are a lot of unknowns in the design. So right now we are in a limited competition, if you will, so they can mature their designs to be able to make a submission that is going to be a fixed-price environment as we move forward. In terms of the testing, we absolutely learn from the testing over time. We are going to test on the first article for the OPC. We have learned that that involvement with test is very important. We have involved the testers from both the Department and our operational test authority early in that development so they can help us make sure that the things that we put in the requirement are testable and it is well understood. So a lot of things that were developed many years ago were unclear, and so even when we have these test events, we are sometimes not quite talking on the same sheet of music. And so those are the kinds of things that we are resolving, and we are clearly moving forward with a lot of lessons learned into the strategy for the Offshore Patrol Cutter. Mr. Graves of Louisiana. Admiral, thank you. In closing I just want to make note that, you know, you have got a great group of Coasties out there, and there is increasing demand upon their services and mission requirements and making sure that we get the equipment out there to them that they need as soon as possible. I think it is critical, and again, we do not need to go through the entire list of drug alien interdictions and many, many other things that you do, but looking back over the history, I know that there are a lot of mistakes that you guys are trying to make up for right now. I just want to encourage you. You know, the Navy obviously, as the chairman pointed out, has some acquisition strategies that may be applicable in this case, but most importantly we have got to get this equipment out there as quickly as we can and make sure that we are respectful of taxpayer dollars moving forward. Thank you. I yield back, Mr. Chairman. Mr. Hunter. I thank the gentleman. I have one last question. If the Coast Guard decided to do a multiyear procurement for the OPCs and the rest of the FRCs, do you have the authority to do that or do you have to get approval from the Department of Homeland Security or the administration? Admiral Vojvodich. Mr. Chairman, I would like to take that back for the record. I will need to understand thoroughly what our options are with that strategy. I understand at a high level what a multiprocurement strategy will allow. I know it was considered, but it sounds like you want me to take it to the next level, and I will thoroughly understand that. Mr. Hunter. I just looked at the bill we passed last year, the Coast Guard bill, and we grant you statutory authority for the OPCs to have multiyear procurement done on those. So my question is though you obviously looked at that, and you have seen that. So do you have the authority, does the Coast Guard have the authority to do that if they want to? Admiral Vojvodich. I would like to take that one back for the record and make sure I thoroughly understand and provide you the best answer possible with that. [The information follows:] Multiyear Procurement (MYP) Contracting: The Coast Guard has considered multiyear procurement (MYP) contracting to acquire new assets; most recently the Coast Guard evaluated this strategy while planning for the Offshore Patrol Cutter. This contracting approach provides stability and promotes efficiencies which are more difficult to achieve when utilizing annual contracting mechanisms. MYP contracting provides an opportunity to generate savings through economic order quantities for materials and equipment, as well as improved production efficiencies and shipyard learning associated with construction stability. MYP contracting is also beneficial for shipyard material and labor cost management. Optimally phased and stable production schedules establish the best scenario for shipyard learning, leading to reduced labor costs. In addition, multiple ship sets of supplies and materials may be procured at reduced costs due to quantity buys. MYP contracting does introduce some risk if subsequent years' funding were not available. In such circumstances the Coast Guard would be required to renegotiate or terminate the contract likely requiring the Government to pay a cancellation fee. Renegotiating the contract would also have a negative financial impact, and therefore one potential disadvantage of using MYP is that it can reduce the flexibility to make changes in future years. The Coast Guard has standing authority to enter into a multiyear contract under 10 U.S.C. 2306(b). In order to qualify, the Coast Guard must show the following: Significant savings. The program must demonstrate that a MYP contract would result in ``significant savings'' compared with annual contracting. Realistic cost estimates. The program's estimates of the cost of the MYP contract and the anticipated savings must be realistic. Stable need for the items. The program must expect its minimum need for the items will remain substantially unchanged during the contract in terms of production rate, procurement rate, and total quantities. Stable funding request for the items. There must be a reasonable expectation that the program will request annual funding for the contract at a level required to avoid contract cancellation. Stable design for the items. The design for the items to be acquired must be stable, and the technical risks associated with the items must not be excessive. Block Buy Contracting: Like multiyear procurement, block buy contracting may provide an opportunity to generate savings through economic order quantities for materials and equipment, as well as improved production efficiencies and shipyard learning associated with construction stability. While Congress has provided the Coast Guard, the other armed services and NASA standing authority for multiyear procurement under 10 U.S.C. 2306(b), there is no similar general authority for block buy contracting. Congress has provided limited authority in specific instances to the Navy to use block buy contracting to acquire Virginia-class attack submarines and Littoral Combat Ships; however, no similar authority has ever been enacted for a Coast Guard acquisition program. The Coast Guard has been responsible for paying for replacement cylinder heads on the propulsion diesel engines. The Coast Guard continues to work with the engine manufacturer to study the root cause of these issues and is committed to developing an engineering solution to reduce the frequency of this repair. There have been other component repairs on the propulsion diesel engines, separate from the cylinder heads, where the Coast Guard and manufacturer have shared costs of failure analyses and repairs, and also situations where the manufacturer assumed all costs. In each instance, responsibility for the repairs was determined based on the specifics of that situation. Mr. Hunter. Ms. Mackin, do you know if the Coast Guard has the authority if they choose to go multiyear after being granted the authority to do so by this committee? Ms. Mackin. I have not looked into that. Mr. Hunter. Mr. O'Rourke. Mr. O'Rourke. Statutory authority versus direction that the Coast Guard may receive within the executive branch. As a matter of statutory authority, the Coast Guard has the authority to use multiyear procurement under title 10, 2306(d), and that is the law that governs multiyear procurement and establishes the statutory framework for conducting it. It states explicitly that the Coast Guard is among the Services that can use it. That same law states that to use multiyear procurement for a contract with a value above a certain level, you need to get congressional approval for each case in an Appropriations Act and a bill other than an Appropriations Act, which is typically an authorization act. That is all part of the legislative framework for multiyear procurement. For using block buy authority, block buy does not have a statutory framework. It just happens through specific legislation that Congress grants to the Service in question, and based on the two precedents of Virginia-class and Littoral Combat Ships, that can be a single provision in an authorization bill or a single provision in an Appropriations Act. Mr. Hunter. All right. Mr. O'Rourke. Now, none of that speaks to then the direction that the Service gets within the executive branch from its superiors, but as a matter of statutory authority, that is where we are. Mr. Hunter. All right. I think that that is all I have got. I do not think there is anybody else here. Thank you very much for kind of getting deep into the weeds on this stuff. That is what we have to do in the end. We want to make the best decision possible. We want to save lots of money so we can buy other stuff, in general. So thank you very much for your testimony. With that our hearing is adjourned. [Whereupon, at 11:33 a.m., the subcommittee was adjourned.] [GRAPHIC(S) NOT AVAILABLE IN TIFF FORMAT] [all]