CONSTRUCTION PROJECTS, O. Reg. 213/91
Section 33
Cite as CONSTRUCTION PROJECTS, O. Reg. 213/91, s. 33 · current to November 11, 2026 · consolidated from April 20, 2026 · read from e-Laws on November 16, 2026
The text
(1) Subject to subsection (2), work on a building shall not be carried out at a distance higher than the higher of two storeys or the first column splice above the temporary or permanent flooring. O. Reg. 213/91, s. 33 (1).
(2) If the vertical distance between the tiers of column splices on a building exceeds two storeys, work shall not be carried out higher than three storeys above the temporary or permanent flooring. O. Reg. 213/91, s. 33 (2).
(3) This section does not apply to work carried out by a worker,
(a) who is working from a scaffold;
(b) whose fall would be arrested by means of a safety net without endangering the worker; or
(c) who is using a fall arrest system attached to the project. O. Reg. 213/91, s. 33 (3).
Read the CONSTRUCTION PROJECTS on e-Laws ↗
Made under Occupational Health and Safety Act, R.S.O. 1990, c. O.1.