CONSTRUCTION PROJECTS, O. Reg. 213/91
Section 161
Cite as CONSTRUCTION PROJECTS, O. Reg. 213/91, s. 161 · current to November 11, 2026 · consolidated from April 20, 2026 · read from e-Laws on November 16, 2026
The text
(1) A competent worker shall perform operational tests on a tower crane to ensure that,
(a) its limiting and indicating devices are installed and functioning in accordance with the manufacturer’s specifications or an engineer’s instructions;
(b) all clearances and alignments are adequate;
(c) gearing and all other moving parts are operating correctly;
(d) controller switches and other control devices are operating correctly;
(e) all limit switches are operating correctly;
(f) all circuits, interlocks, and sequences of operation are operating in accordance with the manufacturer’s specifications;
(g) all protective devices are operating correctly;
(h) the audio device near the base of travelling cranes is operating correctly; and
(i) each motion of the crane operates in accordance with the manufacturer’s specifications. O. Reg. 241/23, s. 17.
(1.1) After the erection of a tower crane but before the tower crane is put into service, load tests shall be performed on the tower crane in accordance with clause 6.3.3 of CSA Standard Z248-17. O. Reg. 241/23, s. 17.
(2) Operational tests shall be done,
(a) after the tower crane is erected on the project and before it is used; and
(b) at one-week intervals after the test under clause (a) while the crane is erected on the project. O. Reg. 213/91, s. 161 (2).
(3) Overload limit devices for a tower crane shall be tested using test blocks designed for the purpose that have their weight clearly marked on them. O. Reg. 213/91, s. 161 (3).
(4) The test blocks shall be kept on the project while the crane is erected. O. Reg. 213/91, s. 161 (4).