(1) A perfected lien expires immediately after the second anniversary of the commencement of the action that perfected the lien, unless one of the following occurs on or before that anniversary: 1. An order is made for the trial of an action in which the lien may be enforced. 2. An action in which the lien may be enforced is set down for trial. 1994, c. 27, s. 42 (1). (2) Where a lien has expired under subsection (1), a motion may be made under section 46. R.S.O. 1990, c. C.30, s. 37 (2).