Construction Act, R.S.O. 1990, c. C.30
Section 36
What liens may be perfected
Cite as Construction Act, R.S.O. 1990, c. C.30, s. 36 · current to November 11, 2026 · consolidated from January 1, 2026 · read from e-Laws on November 17, 2026
The text
(1) A lien may not be perfected unless it is preserved. R.S.O. 1990, c. C.30, s. 36 (1).
(2) A lien that has been preserved expires unless it is perfected prior to the end of the 90-day period next following the last day, under section 31, on which the lien could have been preserved. R.S.O. 1990, c. C.30, s. 36 (2); 2017, c. 24, s. 31 (1).
(3) A lien claimant perfects the lien claimant’s preserved lien,
(a) where the lien attaches to the premises, when the lien claimant commences an action to enforce the lien and, except where an order to vacate the registration of the lien is made, the lien claimant registers a certificate of action in the prescribed form on the title of the premises; or
(b) where the lien does not attach to the premises, when the lien claimant commences an action to enforce the lien. R.S.O. 1990, c. C.30, s. 36 (3); 2017, c. 24, s. 65, 70, 71; 2018, c. 17, Sched. 8, s. 10.
(4) A preserved lien becomes perfected by sheltering under a lien perfected by another lien claimant in respect of the same improvement in accordance with the following rules:
1. The preserved lien of a lien claimant is perfected by sheltering under the perfected lien of another lien claimant in respect of the same improvement where,
i. the lien of that other lien claimant was a subsisting perfected lien at the time when the lien of the lien claimant was preserved, or
ii. the lien of that other lien claimant is perfected in accordance with clause (3) (a) or (b) between the time when the lien of the lien claimant was preserved and the time that the lien of the lien claimant would have expired under subsection (2).
2. The validity of the perfection of a sheltered lien does not depend upon the validity, proper preservation or perfection of the lien under which it is sheltered.
3. A sheltered claim for lien is perfected only as to the defendants and the nature of the relief claimed in the statement of claim under which it is sheltered.
4. Upon notice given by a defendant named in a statement of claim, any lien claimant whose lien is sheltered under that statement of claim shall provide the defendant with further particulars of the claim for lien or of any fact alleged in the claim for lien. R.S.O. 1990, c. C.30, s. 36 (4); 2017, c. 24, s. 31 (2-4).
(5) Subject to subsection 44 (4) (apportionment), a preserved general lien that attaches to the premises shall be perfected against each premises to which the person having the lien desires the lien to continue to apply. R.S.O. 1990, c. C.30, s. 36 (5); 2017, c. 24, s. 72.
(6) A person who has preserved a lien, but who has extended a period of credit for the payment of the amount to which the lien relates, may commence an action for the purpose of perfecting the lien even though the period of credit has not at the time expired. R.S.O. 1990, c. C.30, s. 36 (6).
Read the Construction Act on e-Laws ↗