WELLS, R.R.O. 1990, Reg. 903
Section 14.1
Cite as WELLS, R.R.O. 1990, Reg. 903, s. 14.1 · current to November 11, 2026 · consolidated from January 1, 2020 · read from e-Laws on November 16, 2026
The text
(1) If a new well is constructed by the use of a driven point, the person constructing the well shall comply with section 14 by ensuring that any annular space is filled to the ground surface using a material and a method approved in writing by the Director that, in the opinion of the Director, will ensure that there are no gaps or air spaces in the material placed in the annular space. O. Reg. 372/07, s. 15.
(2) Subsection (1) does not apply to a test hole or dewatering well if abandonment of the test hole or dewatering well is scheduled to take place not later than 180 days after completion of the structural stage of the test hole or dewatering well. O. Reg. 372/07, s. 15.
Read the WELLS on e-Laws ↗
Made under Ontario Water Resources Act, R.S.O. 1990, c. O.40.