NORTHEAST POWER LINE PROJECT, O. Reg. 234/25
Section 13
Minister’s directions
Cite as NORTHEAST POWER LINE PROJECT, O. Reg. 234/25, s. 13 · current to November 11, 2026 · consolidated from October 22, 2025 · read from e-Laws on November 16, 2026
The text
(1) A consultation direction may be issued by the Minister if the Minister is of the opinion that additional consultations in respect of the matters mentioned in subclauses 3 (2) (a) (i) and (ii) must be carried out before the proponent may proceed with the Northeast Power Line Project.
(2) A consultation direction may direct the proponent to take one or more of the following actions:
1. Carry out consultations in addition to any consultations already carried out in respect of the Project or a proposed change to the Project.
2. Carry out consultations with Indigenous communities in relation to potential impacts on rights identified by a community.
3. Report to the Minister on any additional consultations required pursuant to the direction, including on the results of that consultation.
(3) A mitigation or prevention direction may be issued by the Minister if the Minister is of the opinion that the direction is necessary to mitigate or prevent a potentially adverse impact of the Northeast Power Line Project or a proposed change to the Project, as the case may be, on existing aboriginal or treaty rights, as recognized and affirmed in section 35 of the Constitution Act, 1982.
(4) A mitigation or prevention direction may direct the proponent to take one or more of the following measures:
1. Measures respecting the manner in which the Project or proposed change is to be carried out.
2. Measures to protect or conserve archaeological or cultural heritage resources.
3. Measures related to habitat protection, conservation, restoration or improvement.
4. Measures related to vegetation protection, conservation, restoration or improvement.
5. Measures related to monitoring the Project or proposed change.
(5) For greater certainty, the measures mentioned in subsection (4) may include consultations and further studies to be carried out by the proponent.
(6) The measures mentioned in subsection (4) may include measures that are not mentioned in a draft report, final report, draft addendum or final addendum or that are different from or in addition to measures mentioned in a draft report, final report, draft addendum or final addendum.
(7) A direction mentioned in subsection (1) or (3) may direct the proponent to describe in the final report or any final addenda how the proponent has complied with or intends to comply with the direction.
(8) In forming the opinion mentioned in subsection (1) or (3), as the case may be, the Minister may consider,
(a) any comments from Indigenous communities related to potential adverse impacts of the Northeast Power Line Project or any proposed change to the Project on existing aboriginal or treaty rights, as recognized and affirmed in section 35 of the Constitution Act, 1982 and measures to mitigate or prevent adverse impacts on those rights;
(b) any responses the proponent has provided respecting the comments mentioned in clause (a);
(c) if prepared, the draft or final report;
(d) any draft or final addenda; and
(e) any notice given to the Director under section 5 or 10.
(9) The Minister may, at any time, give the proponent a notice amending a mitigation or prevention direction mentioned in subsection (3) and the notice may set out any transitional requirements related to the amendment.
(10) The Minister may give a notice under subsection (9) only if the Minister is of the opinion that the amendment will appropriately address the adverse impact that the direction was issued to address.
(11) In the event of a conflict between a mitigation or prevention direction mentioned in subsection (3) and the final report, or if applicable, any final addenda, the direction prevails.
(12) A consultation direction mentioned in subsection (1) or a mitigation or prevention direction mentioned in subsection (3) may be issued at any time before,
(a) the expiry of the waiting period mentioned in subparagraph 1 v of subsection 2 (1) in the case of a direction respecting the Northeast Power Line Project but not respecting a change mentioned in clause (b) or (c);
(b) the expiry of the waiting period mentioned in subsubparagraph 2 ii B of subsection 2 (1) in the case of a direction respecting a change to the Northeast Power Line Project that the proponent determines is not significant under section 7; or
(c) the expiry of the waiting period mentioned in subsubparagraph 2 iii E of subsection 2 (1) in the case of a direction respecting a change to the Northeast Power Line Project that the proponent determines is significant under section 7.
Read the NORTHEAST POWER LINE PROJECT on e-Laws ↗
Made under Environmental Assessment Act, R.S.O. 1990, c. E.18.