NORTHEAST POWER LINE PROJECT, O. Reg. 234/25
Section 12
Different waiting periods
Cite as NORTHEAST POWER LINE PROJECT, O. Reg. 234/25, s. 12 · current to November 11, 2026 · consolidated from October 22, 2025 · read from e-Laws on November 16, 2026
The text
(1) If the Minister has information that, during a comment period mentioned in a provision set out in Column 1 of the Table to this section, an Indigenous community has raised a concern regarding potential adverse impacts of the Northeast Power Line Project or any proposed change to the Project on existing aboriginal or treaty rights, as recognized and affirmed in section 35 of the Constitution Act, 1982, the Minister may, by written notice, extend the waiting period mentioned in the provision set out opposite that comment period in Column 2 of the Table.
(2) If the Minister has information that, during the 30-day waiting period mentioned in subsubparagraph 2 ii B of subsection 2 (1), an Indigenous community has raised a concern regarding potential adverse impacts of the Northeast Power Line Project or any proposed change to the Project on existing aboriginal or treaty rights, as recognized and affirmed in section 35 of the Constitution Act, 1982, the Minister may, by written notice, extend the waiting period mentioned in that subsubparagraph.
(3) If the Minister has information that, during a comment period mentioned in a provision set out in Column 1 of the Table to this section, no Indigenous community has raised a concern regarding potential adverse impacts of the Northeast Power Line Project or any proposed change to the Project on existing aboriginal or treaty rights, as recognized and affirmed in section 35 of the Constitution Act, 1982, the Minister may, by written notice, shorten the waiting period mentioned in the provision set out opposite that comment period in Column 2 of the Table.
(4) A Minister’s notice under subsection (1), (2) or (3) must specify the number of days by which the applicable waiting period is extended or shortened, as the case may be.
(5) The Minister may extend a waiting period under subsection (1) or (2) more than once.
TABLE
Item | Column 1 Provision setting out comment period | Column 2 Provision setting out waiting period
1. | Paragraph 2 of subsection 4 (3) | Subparagraph 1 v of subsection 2 (1)
2. | Paragraph 3 of subsection 9 (3) | Subsubparagraph 2 iii E of subsection 2 (1)
Read the NORTHEAST POWER LINE PROJECT on e-Laws ↗
Made under Environmental Assessment Act, R.S.O. 1990, c. E.18.