PART II.3 PROJECTS - DESIGNATIONS AND EXEMPTIONS, O. Reg. 50/24
Section 12
Part II.3 exemption, environmental screening process
Cite as PART II.3 PROJECTS - DESIGNATIONS AND EXEMPTIONS, O. Reg. 50/24, s. 12 · current to November 11, 2026 · consolidated from November 3, 2026 · read from e-Laws on November 16, 2026
The text
(1) A project designated as a Part II.3 project under section 9 or 10 is exempt from Part II.3 of the Act if the project is carried out in accordance with the Environmental Screening Process for Electricity Projects.
(2) Despite subsection (1), a project is not exempt from Part II.3 of the Act if,
(a) the Minister issues a notice, in accordance with the Environmental Screening Process for Electricity Projects, requiring the proponent to prepare an environmental assessment in respect of the project;
(b) the proponent applies under subsection 17.2 (1) of the Act for approval to proceed with the Part II.3 project; or
(c) the project is deemed to be a Part II.3 project under section 38.3 of the Act.
Read the PART II.3 PROJECTS - DESIGNATIONS AND EXEMPTIONS on e-Laws ↗
Made under Environmental Assessment Act, R.S.O. 1990, c. E.18.